Kelsey v. Nathey

869 S.W.2d 213, 1993 Mo. App. LEXIS 1942, 1993 WL 512911
CourtMissouri Court of Appeals
DecidedDecember 14, 1993
DocketWD 47583
StatusPublished
Cited by16 cases

This text of 869 S.W.2d 213 (Kelsey v. Nathey) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelsey v. Nathey, 869 S.W.2d 213, 1993 Mo. App. LEXIS 1942, 1993 WL 512911 (Mo. Ct. App. 1993).

Opinion

ELLIS, Judge.

Robert and Laura Nathey appeal a $1500 judgment entered against them by the Boone County Circuit Court after a bench trial. We affirm.

Kelsey filed a petition in small claims court on January 31, 1992, alleging breach of contract against the Natheys in connection with a real estate sale. A $1500 judgment was entered in Kelsey’s favor on June 5, 1992. The Natheys timely filed an application for a trial de novo in the circuit court and the trial “anew” was held on January 21, 1993. During trial, the Natheys moved for dismissal on the grounds that Kelsey’s claim was barred by the doctrine of merger. The court overruled their motion. On February 4,1993, the court entered judgment in favor of Kelsey for $1500 and assessed costs against the Na-theys. On February 16, 1993, the Natheys filed a “Motion to Amend Judgment and/or for Dismissal; and Alternative Motion for New Trial.” A hearing on the motion was conducted on March 1,1993. Later that day, the court denied the motion and, apparently in direct response to arguments made by the Natheys at the hearing, entered a supplemental order clarifying certain aspects of its February 4, 1993 judgment. This appeal by the Natheys followed.

Although this case originated in small claims court and is now before us on appeal after a trial de novo in the circuit court, our standard of review is the same as in other court-tried cases. Wampler v. Mueller, 623 S.W.2d 27, 28 (Mo.App.1981). We must defer to the trial court and affirm its judgment “unless there is no substantial evidence to support it, or it is against the weight of the evidence or it erroneously declares or misapplies the law.” Brownstein v. Rhomberg-Haglin & Assoc., Inc., 824 S.W.2d 13, 15 (Mo. banc 1992). “Credibility of witnesses and the weight to be given their testimony is for the trial court, which is free to believe none, part or all of the testimony of any witness. We assume the trial court believed the testimony and evidence consistent with its judgment, consequently, we accept as true *215 the evidence and permissible inferences which may be drawn favorable to the prevailing party, and disregard the contradictory testimony.” Snowden v. Gaynor, 710 S.W.2d 481, 483 (Mo.App.1986) (citations omitted). So viewed, the evidence establishes that John Kelsey and his wife Susan Kelsey were interested in certain residential Boone County real estate owned by Robert and Laura Na-they. As the Natheys had apparently experienced problems with the home’s septic system in the past, the contract of sale, which they signed on June 15, 1991, had a section titled “Financing, Contingencies, and/or Special Agreements” containing this handwritten provision:

Seller shall within 2 weeks prior to closing complete the following: ... 9) Install additional laterals to septic tank drainfield so that all effluent is absorbed. [Emphasis added.]

Kelsey hired a local engineering firm, Marshall Engineering, to perform an inspection of the property. During the inspection, which was completed on June 21, 1991, William Marshall, an engineering expert with 20 years’ experience, observed that the aeration unit for the septic tank was “not working” and was “taking in water, surface water from the yard.” He also saw effluent leaching out of the ground around the septic tank to form standing pools by the fence in the back yard, in violation of county and state regulations. In a note to the Natheys’ real estate agent, Marshall expressed his opinion that “perhaps a sand mound [drainage system] would be a better solution than adding an additional lateral,” and offered to install such a system for $450. Kelsey also asked the Natheys to speak to Marshall about the possibility of a sand mound system, but Marshall and Kelsey never heard from either the Natheys or their agent. In early July, 1991, Nathey hired another firm, Lonnie Nichols Trucking and Excavating, to do the work required by the contract.

On July 29,1991, the date the contract was closed, the septic tank drainfield was dry and there were obvious indications to Kelsey that some modifications to the septic system had been made. He accepted a deed from the Natheys a few days later after releasing funds escrowed for a plumbing inspection, and moved in to the home on August 8,1991. The following weekend, they noticed the ground around the septic tank had once again become completely saturated and standing puddles of effluent had re-formed in the area. The ground was so wet Kelsey wasn’t able to mow the grass in the area where the septic system was located. Over the next two to three weeks, the situation worsened and Kelsey asked Nathey to make appropriate repairs under the terms of the contract, but he refused, saying “he had repaired the system, and since [Kelsey] now owned the property, that it was [his] problem.” Kelsey had Marshall reinspect the septic system on September 16, 1991. This inspection revealed that effluent was seeping out of a shallow, recently-excavated 70-foot long trench near the fence in the back yard. Marshall saw “no evidence” a sand mound system had been constructed and “it appeared [to him] that, if anything had been done, [there] had been maybe one or two laterals put across that area and covered and then put — they filled it back over with dirt.”

After obtaining repair bids from three contractors, Kelsey contacted Nathey again, who once more refused to make any further repairs to the septic system. Kelsey then hired the lowest of the three bidders, Davis Excavating, to install the additional laterals at a total cost of $1674.08. 1 Marshall came back on September 23, 1991 while this repair work was in progress. He examined the entire, area, including the earth exposed during the course of the excavation work. These excavations began at the aeration unit, crossed the existing 70-foot trench, and extended down to the fence. He “saw no sand *216 in the excavation” and concluded that “in [his] professional opinion, no sand mound” drainage system had been constructed on the lot. Upon completion of the work, Kelsey sent Nathey a certified letter requesting reimbursement for the cost of the repairs, which was later returned to him when Na-they refused to accept it. Another letter and a subsequent phone call were equally futile, and Kelsey filed his petition in small claims court approximately three weeks after their last exchange.

In their first point, the Natheys argue that Kelsey failed to join a necessary and indispensable party under Rule 52.04. Kelsey responds that because the Natheys first raised this issue in their post-trial motion, they waived it, citing DeBacker v. Forbes, 406 S.W.2d 811 (Mo.App.1966). DeBacker was decided prior to adoption of Rule 55.-27(g)(2), which became effective on September 1, 1973. It provides, in pertinent part:

[A] defense of failure to join a party indispensable under Rule 52.04 ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kennedy Jones v. Leath & Sons, Inc.
Missouri Court of Appeals, 2022
Frontenac Engineering Group v. Uka
331 S.W.3d 676 (Missouri Court of Appeals, 2010)
Cason v. King
327 S.W.3d 543 (Missouri Court of Appeals, 2010)
Jones v. Jones
285 S.W.3d 356 (Missouri Court of Appeals, 2009)
Libby v. Uptegrove
988 S.W.2d 131 (Missouri Court of Appeals, 1999)
Cabinet Distributors, Inc. v. Redmond
965 S.W.2d 309 (Missouri Court of Appeals, 1998)
Gee v. Payne
939 S.W.2d 383 (Missouri Court of Appeals, 1997)
Pil Dong Han v. Min Ho Yang
931 P.2d 604 (Hawaii Intermediate Court of Appeals, 1997)
Judy v. Arkansas Log Homes, Inc.
923 S.W.2d 409 (Missouri Court of Appeals, 1996)
Slankard v. Thomas
912 S.W.2d 619 (Missouri Court of Appeals, 1995)
Page v. Lewis
902 S.W.2d 359 (Missouri Court of Appeals, 1995)
Paull v. Shop 'N Save Warehouse Foods, Inc.
890 S.W.2d 401 (Missouri Court of Appeals, 1995)
M.F.M. v. J.O.M.
889 S.W.2d 944 (Missouri Court of Appeals, 1995)
Obaidullah v. Kabir
882 S.W.2d 229 (Missouri Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
869 S.W.2d 213, 1993 Mo. App. LEXIS 1942, 1993 WL 512911, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelsey-v-nathey-moctapp-1993.