Kelly v. Valley Construction Co.

262 P.2d 970, 43 Wash. 2d 679, 1953 Wash. LEXIS 360
CourtWashington Supreme Court
DecidedNovember 17, 1953
Docket32449
StatusPublished
Cited by8 cases

This text of 262 P.2d 970 (Kelly v. Valley Construction Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelly v. Valley Construction Co., 262 P.2d 970, 43 Wash. 2d 679, 1953 Wash. LEXIS 360 (Wash. 1953).

Opinion

Weaver, J.

This is an action for damages arising from an alleged breach of contract. The case was tried to the court. Defendant appeals from a'judgment against it.

Appellant makes twenty assignments of error, which fall into four classes: (1) twelve assignments directed to the findings of fact (the findings of fact contain fourteen paragraphs) ; (2) three assignments directed to the conclusions of law; (3) three assignments directed to the denial of post-trial motions and entry of judgment (the second and third categories are dependent upon the first); and (4) the nineteenth and twentieth assignments of error are directed to the admission and consideration of certain testimony.

The length of the record, the nature of the assignments of error, and counsel’s method of approach require that we consider the scope of our review. In Peterson v. Schoonover, 42 Wn. (2d) 621, 622, 257 P. (2d) 209 (1953), we said:

*681 “There is a legion of our decisions stating that this court, being an appellate court and not the trier of facts, will not disturb a finding of the trial court unless we can say that the evidence preponderates against it. Our first duty is not to resolve a conflict of fact — that is the province of the trial judge. Our primary duty is to decide whether the opposing evidence exceeds in weight the evidence supporting the finding. If it does exceed in weight, then it can be said that the opposing evidence preponderates, and it is from the opposing evidence that a different finding springs.”

See, also, Rettinger v. Bresnahan, 42 Wn. (2d) 631, 257 P. (2d) 633 (1953).

With this in mind, and being cognizant of the trial judge’s statement that:

“In arriving at my appraisement of the evidence in this case, I am required to state for the benefit of counsel that I feel the witness Adams was mistaken in all of his testimony, except insofar as he was corroborated by other witnesses,”

we set forth the following as the facts necessary to a decision which are established by a preponderance of the evidence.

Appellant had contracted with the city of Spokane to construct a division of a new sewer system. It required 4,820 lineal feet of tunnel construction, fifty-five feet below the surface. The completed sewer was to have an inside diameter of six feet, with a one-foot concrete wall.

May 5, 1950, appellant and respondents entered into a subcontract. Respondents were to furnish and supervise the labor necessary to drive the tunnel. Since this action must be determined by an application of the facts to the written subcontract, it is necessary to set forth the pertinent provisions at some length.

“2. That subject to said prior approval the General Contractor does hereby sub-let to the Sub-Contractor the following portion of said Contract work, to-wit:

“Furnish and perform all labor as may be required to complete the tunnel . . . approximately 4820 lineal feet (excluding the two shafts and the small portion of the tunnel heretofore driven by the General Contractor, and excluding the concrete lining of the tunnel). The term labor, as herein used, shall include the full cost and expense of salaries or wages of all workmen, foreman and superin *682 tendents employed by the Sub-Contractor on the job, and all costs incidental thereto . . . and premiums on public liability and property damage insurance and contingent liability and contingent property damage insurance protecting the City as required of the Sub-Contractor in said Com tract, and in addition all rentals to be paid for the use of mucking machines used by the Sub-Contractor on the job. .
’ “The General Contractor shall furnish all materials, machinery (other than mucking machines), equipment and all electric power and water as may be required by the SubContractor in the performance of this Sub-Contract. . . .
“4. The Sub-Contractor agrees to enter promptly upon the performance of said Sub-Contract work and to pursue the same diligently and continuously without any unnecessary delay and without hindrance to the General Contractor or any other Sub-Contractor, and the General Contractor and the Sub-Contractor mutually and reciprocally pledge to one another full cooperation and coordination of effort subject to all further terms of this Sub-Contract. The Sub-Contractor agrees to complete the performance of said work within two hundred days from the date of commencement.
“5. . . . the General Contractor agrees to pay for and on behalf of the Sub-Contractor all of said costs and expenses as and when the same become due, . . . and the Sub-Contractor agrees that all of said payments made by the General Contractor shall be a legal charge against the earnings of the Sub-Contractor under this Sub-Contract. It is further understood and agreed that the said Thomas Lee Kelly and Walter L. Clark [respondents] . . . shall be entered upon the payroll and be paid at the rate of Twenty Five ($25.00) Dollars for each day worked.
“6. The Sub-Contractor agrees that the cost to the General Contractor for the' performance of this Sub-Contract shall not exceed the sum of Thirty Three ($33.00) Dollars per. lineal foot of shaft or tunnel driven by the Sub-Contractor, and further agrees to, so far as possible, reduce said cost, and in consideration thereof the General Contractor agrees to pay to the Sub-Contractor the actual cost and expense of this Sub-Contract as set forth in Paragraph 5 above, not exceeding the sum of Thirty Three ($33.00) Dollars per lineal foot of shaft or tunnel driven, plus two-thirds (%) of the difference between said actual cost and expense (if less than Thirty Three ($33.00) Dollars per lineal foot) and the sum of Thirty Three ($33.00) Dollars *683 per lineal foot, the General Contractor having the right to retain the other one-third (%) of such difference.
“If when the work has progressed to such point that the General Contractor can determine that the average cost for the performance of the work is exceeding Thirty Three ($33.00) Dollars per lineal foot, then the General Contractor shall have the option to terminate this agreement and take over the performance of the remaining work under this Sub-Contract, and all rights of the Sub-Contractor shall be terminated and at an end, provided, however, that if said excess cost is due to unusual conditions encountered in the performance of the work and unanticipated by both the General Contractor and the Sub-Contractor, then both parties will endeavor to mutually agree upon such additional compensation as may be just and equitable and under such unusual conditions and circumstances. . . .
“8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vangemert v. McCalmon
414 P.2d 617 (Washington Supreme Court, 1966)
Patterson v. Bixby
364 P.2d 10 (Washington Supreme Court, 1961)
State v. Tatum
360 P.2d 754 (Washington Supreme Court, 1961)
Crofton v. Bargreen
332 P.2d 1081 (Washington Supreme Court, 1958)
Bosscher v. Leenders
301 P.2d 1080 (Washington Supreme Court, 1956)
Kerns v. Pickett
287 P.2d 88 (Washington Supreme Court, 1955)
Carns v. Shirley
269 P.2d 804 (Washington Supreme Court, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
262 P.2d 970, 43 Wash. 2d 679, 1953 Wash. LEXIS 360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelly-v-valley-construction-co-wash-1953.