Kelly v. Ford Motor Co.

139 N.E.2d 99, 104 Ohio App. 185, 76 Ohio Law. Abs. 170, 4 Ohio Op. 2d 352, 1957 Ohio App. LEXIS 896
CourtOhio Court of Appeals
DecidedJanuary 9, 1957
Docket23619
StatusPublished
Cited by12 cases

This text of 139 N.E.2d 99 (Kelly v. Ford Motor Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelly v. Ford Motor Co., 139 N.E.2d 99, 104 Ohio App. 185, 76 Ohio Law. Abs. 170, 4 Ohio Op. 2d 352, 1957 Ohio App. LEXIS 896 (Ohio Ct. App. 1957).

Opinion

OPINION

By HURD, J:

Plaintiff commenced this suit in Common Pleas Court by filing a petition against three defendants, namely, Johnson, Drake & Piper, Inc., Smith & Oby Company, and the Ford Motor Company, to recover damages for injuries sustained when a step ladder fell upon plaintiff from the platform of a scaffolding approximately thirty feet above the place where he was working. In the midst of trial, Johnson, Drake & Piper, Inc. and Smith & Oby Company, were dismissed as defendants to the action pursuant to a covenant not to sue, executed in their favor by the plaintiff in consideration of the sum of $30,000 paid to him by them. Plaintiff expressly reserved his right of action against the defendant, the Ford Motor Company. The trial continued as to Ford, resulting in a jury verdict for the plaintiff in the sum of $20,000, upon which judgment was rendered. Motions for a directed verdict and for judgment non obstante veredicto, and also a motion for a new trial having been overruled, the case is appealed to this court on questions of law.

The evidence shows that late in 1950 Ford began the construction of a foundry building and a boiler house on its property at 17601 Brook-park Road, Cuyahoga County, Ohio. Because the accident, which is the subject of this suit, occurred at the boiler house, the evidence in the record is generally confined to the area of its construction and environs. The record shows that Ford entered into contracts with several different contractors for the construction of the boiler house and for its overall preparation for operation. The contractors were designated as general contractors in agreements with Ford, but none of the contractors had supervisory control over the other. Part of the work of these contractors was subcontracted to other firms. Thus, Johnson, Drake & Piper, Inc., one of the original defendants, whose contract related to the building of the foundation and the erection of the walls and roof on the structural steel frame, had its own cement finishers, but engaged Smith & Oby Company, another original defendant herein, as a subcontractor to do the steamfitting. The employer of plaintiff, The Thomas J. Waldron Company, was hired to install fire brick in the boilers. As work on the boiler house progressed, a scaffold or construction platform was erected by Johnson, Drake & Piper, Inc. Its workmen, particularly cement finishers, used the overhead platform in the performance of their work. At times, that platform was also used by employees of Smith & Oby Company. The plaintiff, as an employee of a subcontractor, The Thomas J. Waldron Company, worked with a crew that operated a power saw which was used to cut fire brick to desired sizes. The saw was located *172 at a place beneath the overhead construction platform because it was convenient to the boiler. The crew had been working there for several days prior to the accident.

On June 7, the day preceding the accident, Smith & Oby Company employees had done some work on the overhead platform for which they used a stepladder, also known as an “A” frame ladder, which was owned by their employer. At the same time, the platform was used by cement finishers employed by Johnson, Drake & Piper, Inc. At the end of the day the Smith & Oby Company employees left the stepladder lying on the platform close to the edge. The following morning the same cement finishers came back to the platform and resumed their work. The record shows that they observed the stepladder lying near the edge of the platform, but since it was not their employer’s property, did nothing about it. The work being done by the cement finishers caused the platform to vibrate, and about fifteen minutes after work commenced on the morning of June 8th, the ladder fell over the side of the platform and struck the plaintiff, who was working on the floor below, causing him serious injuries.

A careful examination of the record demonstrates that Ford was not guilty of any active or affirmative negligence in respect to the injuries sustained by the plaintiff. Johnson, Drake & Piper, Inc. built the platform and scaffolding. The ladder was furnished by Smith & Oby Company. Smith & Oby Company left the ladder in a precarious position on the platform. It was Johnson, Drake & Piper, Inc. workmen who caused the platform to vibrate and the ladder to fall. There is no evidence in the record showing that Ford was aware of these events. There were no employees of Ford involved in the accident nor was there any equipment of Ford in use at the time and place of the accident.

In the amended petition filed by the plaintiff against the three original defendants, there were nine specifications of negligence charged against defendant, Smith & Oby Company, the substance of which was that the Smith & Oby Company was negligent in failing to rope off or block off the area or otherwise guard the floor immediately below the opening in the scaffolding so that workers would not be injured by falling equipment, or by leaving a loose and unattached stepladder in a precarious position on the platform forty feet above the floor where men were working, thereby creating a nuisance and a great source of danger to all persons; in failing to warn plaintiff and in failing to move the ladder from its position on the platform so that it could not be dislodged or knocked down to the floor below.

The original defendant, Johnson, Drake & Piper, Inc. was also charged with nine specifications of negligence substantially the same as the specifications charged against Smith & Oby Company, and also that it permitted its subcontractor, Smith & Oby Company, to engage in an unsafe practice with regard to the ladder; that it constructed the overhead platform without toe boards or railing so that the ladder could fall therefrom; that it failed to warn plaintiff of his danger and failed to provide plaintiff with a safe place to work.

Ford was charged with negligence in failing to make its premises *173 safe and in failing to exercise ordinary care because plaintiff avers that he was an invitee of Ford in the boiler house which was under control and supervision of Ford and that Ford failed to provide a safe place of employment; in failing to warn plaintiff of his danger, and that it allowed Smith & Oby Company to set the ladder on the platform without securing same.

On this appeal, defendant assigns as error:

1. That the trial court erred in refusing to grant defendant’s motion for judgment at the conclusion of plaintiff’s case;

2. In refusing to grant defendant’s motion made at the conclusion of all of the evidence;

3. In refusing to grant judgment for defendant based on plaintiff’s release of the other defendants to the original action for the sum of $30,000 on the theory that said defendants were primarily liable for plaintiff’s injuries; and

4. The trial court erred to the prejudice of the defendant by overruling Ford’s alternative motion for judgment non obstane veredicto or for a new trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lycan v. Cleveland
2022 Ohio 4676 (Ohio Supreme Court, 2022)
St. Julian v. Owens-Illinois, Inc.
394 N.E.2d 359 (Lucas County Court of Common Pleas, 1978)
Butcher v. Pollard
288 N.E.2d 204 (Ohio Court of Appeals, 1972)
Seaboard Air Line Railroad Co. v. Coastal Distributing Co.
273 F. Supp. 340 (D. South Carolina, 1967)
New York, Chicago & St. Louis Rd. v. Heffner Construction Co.
223 N.E.2d 649 (Ohio Court of Appeals, 1967)
Holcomb v. Flavin
216 N.E.2d 811 (Illinois Supreme Court, 1966)
Schultz & Lindsay Construction Company v. Erickson
352 F.2d 425 (Eighth Circuit, 1965)
Schultz & Lindsay Construction Co. v. Erickson
352 F.2d 425 (Eighth Circuit, 1965)
Tice v. E. I. Du Pont De Nemours & Co.
106 S.E.2d 107 (West Virginia Supreme Court, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
139 N.E.2d 99, 104 Ohio App. 185, 76 Ohio Law. Abs. 170, 4 Ohio Op. 2d 352, 1957 Ohio App. LEXIS 896, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelly-v-ford-motor-co-ohioctapp-1957.