Kelly v. Fejervary

83 N.W. 791, 111 Iowa 693
CourtSupreme Court of Iowa
DecidedOctober 2, 1900
StatusPublished
Cited by18 cases

This text of 83 N.W. 791 (Kelly v. Fejervary) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelly v. Fejervary, 83 N.W. 791, 111 Iowa 693 (iowa 1900).

Opinion

Ladd, J.

1 That the building was not completen by the time stipulated, and no extension granted in the manner required, was fully established by. the evidence, and the jury may well have fixed the period of delinquency at sixty-six days. The sixth paragraph of the contract provided that “the contractors shall and will proceed with the said work, and every part and detail thereof, in a prompt and diligent manner, and shall and will wholly finish the said work, according to the said drawings and specifications and this contract, on or before the 15th day of October, in the year one thousand eight hundred and ninety-two (provided that possession of the premises be given the contractors, and line and levels of the building furnished him, on or before the 25th day of April, in the year one thousand eight hundred and ninety-two), and in default thereof the contractors shall pay to the owner ten ($10) dollars for every day thereafter that the said work shall remain unfinished, as and for liquidated damages.” So that, if the stipulation for ten dollars per day be regarded as liquidated damages, the owner had the right to retain the six hundred’ and sixty dollars from the contract price. But the appellant insists that this should be construed as a penalty, and actual damages only allowed. It is often a matter of great perplexity to determine [696]*696whether a condition, ought to be construed as ascertaining damages or merely as a penalty. Ordinarily, agreements are made to be performed, and the parties' pay little heed to the contingency of a failure. Eor this reason, if the face of the instrument leaves it doubtful whether the parties intended the sum specified as liquidated damages or a penalty, the courts incline to' treat it as a penalty to' cover the actual damages only. Indeed, the fundamental principle underlying our system of jurisprudence is that of compensation, and the ultimate object is always, if possible, to put the injured party in as favorable a position as though the contract had been kept. “So long as the parties themselves keep this principle in view, they will be allowed to agree upon such a sum as will probably be a fair equivalent of a breach of contract. But when they go beyond this, and undertake to stipulate, not for compensation, but for a sum out of all proportion to the measure of liability which the law regards! as compensatory, then the law will not allow the agreement to stand. In all agreements, therefore, fixing upon a sum in advance as the measure or limit of liability, the final question is whether the subject of the contract is such that it violates this fundamental rule of compensation. If it does so, the sum fixed is necessarily a penalty. If it does not do so, the question arises as in any other contract made; and here, as in all other cases, their intention, as ascertained from the language employed, is a guide.” 1 Sedgwick, Damages, section 406. Thus, if damages larger than the law permits are stipulated, as more than the legal rate of interest for the nonpayment of money, oír a sum. certain is specified as ascertained damages for the breach of any one of several stipulations when the losses resulting from such breaches must necessarily differ in amount, or an excessive sum is named in a case where the real damages are certain or readily reduced to a certainty by proof, the sum designated, under any of these conditions, is to be construed a penalty. But when damages are to* result from the breach [697]*697of a single stipulation, and may not be readily ascertained, then the amount agreed upon by the parties, if not disproportionate to the presumable loss, is recoverable as liquidated damages. Wallis Iron Works v. Monmouth Park Ass’n (N. J. Err. & App.) 26 Atl. Rep. 140, 19 L. R. A. 456 (39 Am. St. Rep. 626); Wilhelm v. Eaves, 21 Or. 194 (27 Pac. Rep. 1053, 14 L. R. A. 297); Tennessee Manufacturing Co. v. James, 91 Tenn. Sup. 154 (18 S. W. Rep. 262, 15 L. R. A. 211); Hennessy v. Metzger, 152 Ill. 505 (38 N. E. Rep. 1058, 43 Am. St. Rep. 267); Hall v. Crowley, 81 Am. Dec. 745; Condon v. Kemper, 47 Kan. Sup. 126 (27 Pac. Rep. 829, 13 L. R. A. 671).

Courts are not even agreed that the intention of the parties is of controlling importance. Christiancy, J., in Jaquith v. Hudson, 5 Mich. 123, declared: “The attempt to place this question upon the intention of the parties, and to make this the governing consideration, necessarily implies that, if the intention to make the sum stipulated damages should clearly appear, the court would enforce the contract according to that intention. To test this, let it be asked whether in such a case, if it were admitted that the parties actually intended the sum to be considered as stipulated damages, and not as a penalty, a court of law would enforce it for the amount stipulated. Clearly, it could not, without going back to the technical and long-exploded doctrine, which gave the whole penalty of the bond, without reference to the damages actually sustained. Courts would thus be simply changing the names of things, and enforcing under the name of stipulated damages what in its own nature is but a penalty. The real question in this class of cases will be found to be, not what the parties intended, but whether the sum is in fact in the nature of a penalty; and this is to be determined by the magnitude of the sum in connection with the subject-matter, and not at all by.the words or the understanding of the parties. The intention of the parties cannot alter it. While the courts of law gave the penalty of [698]*698"the bond, the parties intended the payment of the penalty .as much as they now intend the payment of stipulated damages. It( must, therefore, we think, be very obvious that the actual intention of the parties of this class of cases, and relating to this point, is wholly immaterial; and, though the •courts have very generally professed to base their decisions upon the intention of the parties, that intention is not and cannot be made the real basis of these decisions. >In endeavoring to reconcile their decisions with the actual intention of the parties, the courts have sometimes been compelled ••to use language wholly at war with any idea of interpretation, and to say ‘that the parties must be considered as not meaning exactly what they say.’ ” It would be difficult, ■•indeed, to make a satisfactory response to this criticism, but it may be said that the difference lies largely in the use of words, and that whether or not the understanding of the parties be held to control the same result is uniformly attained. In Sanford v. Bank, 94 Iowa, 683, Neemer, J., stated the general rule, laid down in former decisions of this court: “In construing such contracts, the court will endeavor to ascertain the intention of the parties, and will give the forfeiture clause such effect as they intended it should have. The words used, whether ‘forfeiture,’ ‘liquidated damages,’ or ‘penal sum’ are not alone conclusive. Nor, indeed, is the language of the contract generally. The court will look to the nature of the contract, the situation of the parties, and to all the surrounding facts and circumstances which- throw light upon the intent of the parties, for ■the purpose of determining what meaning they placed upon the words used.” De Graff, Vrieling & Co. v. Wickham, 89 Iowa, 720; Foley v. McKeegan, 4 Iowa, 1. Thus, the circumstances mentioned by Justice Christiancy .are taken into consideration in this state as pointing out the intention of the parties rather than as indicating none existed.

[699]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bennett v. Eldon Miller, Inc.
106 N.W.2d 257 (Supreme Court of Iowa, 1960)
Huntsman v. Eldon Miller, Inc.
101 N.W.2d 531 (Supreme Court of Iowa, 1960)
Aultman v. Meyers
33 N.W.2d 400 (Supreme Court of Iowa, 1948)
Iowa Electric Co. v. Home Insurance
17 N.W.2d 414 (Supreme Court of Iowa, 1945)
Seeger v. Manifold
231 N.W. 479 (Supreme Court of Iowa, 1930)
Lu-Mi-Nus Signs, Inc. v. Jefferson Shoe Stores, Inc.
257 Ill. App. 150 (Appellate Court of Illinois, 1930)
Battin v. Merchants State Bank
208 N.W. 343 (Supreme Court of Iowa, 1926)
Shockley v. Paul Davis Dry Goods Co.
205 N.W. 966 (Supreme Court of Iowa, 1925)
Holt v. Doty
193 Iowa 582 (Supreme Court of Iowa, 1922)
Rath v. Schoon
192 Iowa 180 (Supreme Court of Iowa, 1921)
Joeckel v. Johnson
178 Iowa 231 (Supreme Court of Iowa, 1916)
Eller v. Newell
141 N.W. 52 (Supreme Court of Iowa, 1913)
Lucas v. Purdy
120 N.W. 1063 (Supreme Court of Iowa, 1909)
Routledge v. Elmendorf
116 S.W. 156 (Court of Appeals of Texas, 1909)
Sanders v. McKim
115 N.W. 917 (Supreme Court of Iowa, 1908)
Charleston Lumber Co. v. Friedman
61 S.E. 815 (West Virginia Supreme Court, 1908)
Selby v. Matson
114 N.W. 609 (Supreme Court of Iowa, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
83 N.W. 791, 111 Iowa 693, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelly-v-fejervary-iowa-1900.