Kelly Enterprises v. New Britain Roofing, No. Cv95 0380171 S (Jun. 3, 1998)

1998 Conn. Super. Ct. 7593
CourtConnecticut Superior Court
DecidedJune 3, 1998
DocketNo. CV95 0380171 S
StatusUnpublished

This text of 1998 Conn. Super. Ct. 7593 (Kelly Enterprises v. New Britain Roofing, No. Cv95 0380171 S (Jun. 3, 1998)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelly Enterprises v. New Britain Roofing, No. Cv95 0380171 S (Jun. 3, 1998), 1998 Conn. Super. Ct. 7593 (Colo. Ct. App. 1998).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION,

I
This is a contract dispute wherein the plaintiff, Kelly Enterprises, Inc. ("Kelly") claims payment in the amount of four thousand dollars ($4,000.00) for work completed pursuant to an agreement with the defendant, New Britain Roofing Co., Inc. CT Page 7594 ("NBR"). Plaintiff's Complaint is in two counts, the first alleging breach of contract, the second, unjust enrichment.

The defendant has answered, denying Kelly's claims and, by way of Counterclaim, alleging that Kelly failed to complete the work it was obligated to perform under the said agreement and failed to perform in a satisfactory manner, as a result of which NBR was "back-charged" twenty one thousand dollars for completion of the work of Kelly.

II
Certain facts are not in dispute: At some time prior to July 28, 1994 NBR entered into an agreement with the Town of East Hampton ("the Town") to provide materials and labor for the re-roofing and renovation of East Hampton High School. The project was a substantial one, with the contract amount being approximately $589,000.00.

Included in this project were certain masonry repairs and renovation on the exterior of the building. On or about July 28, 1994, NBR, as general contractor, and Kelly, as subcontractor, entered into an agreement whereby Kelly undertook to provide all labor and materials to complete the said masonry work at a total cost of eight thousand dollars ($8,000.00). This agreement is recorded on plaintiff's exhibit "C". Kelly began work at the beginning of August, 1994 and left the site on or about October 25, 1994. There is no dispute that NBR paid Kelly the sum of four thousand dollars ($4,000.00) for work done under the contract by check dated 10/1/94. The parties also agree that during the period August to October NBR issued a change order memorializing its request that Kelly, undertake additional work with reference to repair of a wall on the site for an additional payment of five hundred thirty five dollars ($535.00) and that Kelly did the work and was paid the $535.00 by check dated 9/28/94. Finally. NBR claims. and Kelly does not dispute, that NBR was unilaterally terminated from its contract with the Town because of the latter's dissatisfaction with NBR's performance.

Beyond that, the parties disagree. The plaintiff's witness, Gerald Blank, Vice President of Kelly, testified that to the best of his knowledge Kelly had completed its work under the contract and departed the site on or about October 25, 1994. In support of its claims Kelly introduced into evidence a job cost journal (Plaintiffs Exhibit "B") For the project, showing an expenditure by Kelly of 330.84 hours and seven thousand two hundred sixty CT Page 7595 four dollars and eighty four cents ($7,264.89) on the project between July 29, and October 25, 1994. The bulk of the labor and monies was expended in July and August. Mr. Blank testified that Kelly received no complaints from NBR during or after completion of Kelly's work, and that Kelly first learned of NBR's claims at the time NBR filed its Counterclaim. Mr. Blank testified that Kelly had provided staging (scaffolding) as required by the agreement, and removed said staging at the time it completed its work on the project. He was less certain of the installation of a new chimney cap, as required by paragraph 2.10 c of the specifications (Defendant's exhibit #1). He did not know if a new cap had been installed. He did not observe a chimney cap on the occasion of his last visit to the site. Thomas Leith, president of NBR, testified that Kelly never installed a new chimney cap but offered nothing in support of this claim but the bare statement. There is nothing in the record to show that at any time prior to this litigation NBR raised the issue of the alleged failure of Kelly to install a new chimney cap, much less registered complaint or demand regarding such failure.

The standard of proof to be applied in this case is that of a fair preponderance of the evidence. When the evidence is equally balanced the party on whom rests the burden of proof must fail,Brodie v. Connecticut Co., 87 Conn. 363, 364.

The court finds that the plaintiff Kelly has established, by a fair preponderance of the evidence, that it substantially performed its obligations under the contract, Vincenzi v. Cerro,186 Conn. 612, 615-616. The court finds that Kelly has failed to establish by a fair preponderance of the evidence, that it did install a new chimney cap as required by paragraph 2.10 c of the specifications. The court finds the estimate of nine hundred dollars ($900.00) for installation of a new chimney cap to be reasonable and will allow defendant NBR an offset of $900.00 against the outstanding balance of $4,000.00, leaving a net amount of three thousand, one hundred dollars ($3,100.00) due and owing to plaintiff Kelly for work completed under the contract.

III
As to plaintiff's Counterclaim: Mr. Leith testified that NBR had been terminated from the job by the Town at some time subsequent to October 25, 1994. He attributed the Town's dissatisfaction to the incompetence of NBR's subcontractors, including plaintiff. He claimed that Kelly had failed to provide CT Page 7596 scaffolding as required by the contract between the parties and that as a result NBR was compelled to expend $1074.84 for rental of scaffolding. In support of this claim an invoice from American Ladders, Scaffolds Truck Equip., Inc. was introduced, showing a charge to NBR for scaffold rental for the period 10/25/94 to 11/24/94, in the amount of $1,074.84.

Mr. Leith further testified that at some time in November, 1994 an architect did a "walk-through" of the project and rejected all of Kelly's work. Mr. Leith testified that NBR received no payment from the Town for work performed by Kelly and was back-charged by the Town for work which Kelly was supposed to have performed. In support of this claim NBR introduced into evidence two invoices, each from Lupia Renovating Company, Inc. to Eagle Group, Inc. Both invoices are dated 9/20/95. One invoice is for labor for"work completed to East Hampton High School — Aug. 7, 8, 9, 10, 11, 14, 15." and is in the amount of nine thousand, three hundred eighty nine dollars and twelve cents ($9,389.12). The second invoice is for materials, tools and equipment "for entire job" and is in the amount of two thousand, four hundred dollars ($2,400.00). NBR claims the Town "back-charged" it for this amount.

Adding the invoice for scaffolding, the two invoices from Lupia and the $4,000.00 paid by NBR to Kelly, the defendant, plaintiff on the counterclaim, NBR, claims damages in the amount of sixteen thousand, eight hundred sixty four dollars and one cent ($16,864.01). For reasons set forth below the court finds in favor of Kelly, both on the Complaint and on the Counterclaim.

IV
Scaffolding: The agreement between the parties recorded on NBR's purchase order No. 1275 (Plaintiff's exhibit "C") reads, "Included is staging for chimney and from high roof to edge of low back roof approx. 35' long by 16' high." When there is an ambiguity as to the meaning of the terms of a written agreement, the terms at issue must be construed against the author of the writing, Levine v. Advest. Inc. 244 Conn. 732. 755-56, Sturman v. Socha,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vincenzi v. Cerro
442 A.2d 1352 (Supreme Court of Connecticut, 1982)
Sturman v. Socha
463 A.2d 527 (Supreme Court of Connecticut, 1983)
Brodie v. Connecticut Co.
87 A. 798 (Supreme Court of Connecticut, 1913)
Levine v. Advest, Inc.
714 A.2d 649 (Supreme Court of Connecticut, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
1998 Conn. Super. Ct. 7593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelly-enterprises-v-new-britain-roofing-no-cv95-0380171-s-jun-3-1998-connsuperct-1998.