Kelly Concrete Company, Inc. v. Jim Sattler, Inc.

CourtCourt of Appeals of Iowa
DecidedJuly 21, 2021
Docket20-1158
StatusPublished

This text of Kelly Concrete Company, Inc. v. Jim Sattler, Inc. (Kelly Concrete Company, Inc. v. Jim Sattler, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelly Concrete Company, Inc. v. Jim Sattler, Inc., (iowactapp 2021).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 20-1158 Filed July 21, 2021

KELLY CONCRETE COMPANY, INC., Plaintiff-Appellant,

vs.

JIM SATTLER, INC., Defendant,

and

BRETT A. STEPHENSON and LISA A. STEPHENSON, Defendants-Appellees. ________________________________________________________________

Appeal from the Iowa District Court for Linn County, Lars G. Anderson,

Judge.

Kelly Concrete Company, Inc. appeals the district court’s pre-answer

dismissal of its petition to foreclose on a mechanic’s lien. REVERSED AND

REMANDED.

William H. Roemerman of Elderkin & Pirnie, P.L.C., Cedar Rapids, for

appellant.

Kevin J. Caster and Graham R. Carl of Shuttleworth & Ingersoll, P.L.C.,

Cedar Rapids, for appellees.

Heard by Doyle, P.J., and Mullins and May, JJ. 2

DOYLE, Presiding Judge.

Kelly Concrete Company, Inc. (Kelly) appeals the dismissal of its petition to

foreclose on a mechanic’s lien. The district court granted the pre-answer motion

to dismiss because the petition failed to state a claim upon which relief may be

granted. In viewing Kelly’s allegations in the light most favorable to Kelly with

doubts resolved in Kelly’s favor, we cannot conclude the petition on its face shows

no right of recovery under any state of facts. Thus, the district court erred in

granting the Iowa Rule of Civil Procedure 1.421(1)(f) motion. So we reverse and

remand the case for further proceedings.

I. Facts and Procedural history.

Brett and Lisa Stephenson (collectively, “the Stephensons”) hired Sattler

Inc. as a general contractor to build a custom home. Sattler subcontracted with

Kelly to do the concrete work. Kelly performed concrete work on the project

between March 28 and June 24, 2019. The amount of its services totaled

$64,392.81. By August 7, 2019, Kelly had received $37,266 from Sattler, leaving

an outstanding balance of $27,126.89 owed to Kelly.

On December 4, 2019, Kelly posted with the Mechanic’s Notice and Lien

Registry (MNLR) a Notice of Commencement of Work, a Preliminary Notice, and

a Mechanic’s Lien. See Iowa Code § 572.8 (2019). On April 16, 2020, Kelly’s

registered agent received a demand to file suit from the Stephensons. See id.

§ 572.28. By agreement between Kelly and the Stephensons, the section

572.28(1) thirty-day deadline to file suit was extended to May 22, 2020. On May

21, 2020, Kelly petitioned to foreclose on its mechanic’s lien. 3

On June 5, 2020, the Stephensons filed an acceptance of service of the

lawsuit and also filed a pre-answer motion to dismiss pursuant to rule 1.421(1)(a),

(b), and (f). In their motion to dismiss, the Stephensons alleged Kelly failed to

perfect its lien because they were “never personally served with [Kelly’s]

mechanic’s lien as required by Iowa Code § 572.10.” Attached were affidavits from

the Stephensons stating they were never personally served with Kelly’s

mechanic’s lien. Kelly resisted claiming, among other things, the Stephensons

were served a copy of the lien when they accepted service of the lawsuit, and in

any event, they “tacitly concede[d] that they had actual notice of the existence of

the lien” as evidenced by their demand for suit. The Stephensons replied

contending Kelly “conflates service of this lawsuit with service of its lien as

mandated by Iowa Code § 572.10.” They also asserted Kelly was obligated, but

failed, under rule 1.302(5), to serve notice of the lien within ninety days of its

posting with the MNLR, and that the Stephensons knowledge of the lien was

irrelevant.

No hearing was held on the motion. After considering “the file, relevant

case law, and written arguments of the parties,” the district court found, in part:

The Court finds that giving written notice of the lien at the same time as service of the petition to foreclose is inappropriate. The statute gives contractors an extension of time to perfect a lien, and [Kelly] attempted to utilize that benefit. [Kelly], though, delayed over five months in giving written notice to the Stephenson Defendants. The statutory scheme appears to contemplate a relatively simultaneous process of first posting the notice in the registry and then serving it; not posting and then waiting many months. Moreover, the Court does not believe that acceptance of the Petition in this case by counsel constitutes service of the required notice. Service of notice is a required precursor to an enforceable lien. The statutory scheme appears designed to maximize notice to the owner. Allowing a subcontractor to post notice, not serve it for 4

half a year, and only do so as part of litigation to enforce the very same lien contradicts this scheme. If [Kelly]’s position is correct, there would be no point to the separate statutory requirement of service of notice. Any subcontractor could avoid separate service of the notice and simply file a petition with notice attached. Plaintiff argues that service of written notice need only comply with the requirements of original notice, however, original notices must be served on defendants within 90 days of filing the petition. Iowa R. of Civ. P. 1.302(5). Likening a posted lien to a petition, Plaintiff should have, under their theory, served Defendants with written notice of the lien by March 3, 2020. The Court concludes that, to the detriment of [Kelly], the lien was never perfected under Iowa Code § 572.10, and [Kelly] has no mechanic’s lien on Stephenson Defendants’ property. The Motion to Dismiss should be and is granted for failing to state a claim upon which relief may be granted.

Kelly appeals.

II. Standard of Review.

Our review of a district court’s ruling on a motion to dismiss is for the

correction of errors at law. Shumate v. Drake Univ., 846 N.W.2d 503, 507 (Iowa

2014). We will sustain a motion to dismiss only if the petition on its face shows no

right of recovery under any state of facts. Leuchtenmacher v. Farm Bureau Mut.

Ins. Co., 460 N.W.2d 858, 861 (Iowa 1990). A motion to dismiss admits the well-

pleaded facts in the petition and waives any ambiguity or uncertainty. Id. In

construing a petition on appeal from a motion to dismiss for failure to state a claim,

the appellate court views the plaintiff’s allegations in the light most favorable to the

plaintiff with doubts resolved in that party’s favor. Mlynarik v. Bergantzel, 675

N.W.2d 584 (Iowa 2004)

III. Analysis.

A mechanic’s lien is purely statutory. Griess & Ginder Drywall, Inc. v.

Moran, 561 N.W.2d 815, 816 (Iowa 1997). “A person who furnishes any material 5

or labor for improvements to building or land is generally entitled to a lien to secure

payment for the labor and materials furnished.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marcus v. Young
538 N.W.2d 285 (Supreme Court of Iowa, 1995)
Schultz v. Board of Adjust. of Pottawattamie Co.
139 N.W.2d 448 (Supreme Court of Iowa, 1966)
Unertl v. Bezanson
414 N.W.2d 321 (Supreme Court of Iowa, 1987)
Stessman v. American Black Hawk Broadcasting Co.
416 N.W.2d 685 (Supreme Court of Iowa, 1987)
Mlynarik v. Bergantzel
675 N.W.2d 584 (Supreme Court of Iowa, 2004)
Sanford v. Manternach
601 N.W.2d 360 (Supreme Court of Iowa, 1999)
Griess & Ginder Drywall, Inc. v. Moran
561 N.W.2d 815 (Supreme Court of Iowa, 1997)
Leuchtenmacher v. Farm Bureau Mutual Insurance Co.
460 N.W.2d 858 (Supreme Court of Iowa, 1990)
U.S. Bank v. Barbour
770 N.W.2d 350 (Supreme Court of Iowa, 2009)
Mark Peak v. Ellis Adams and Rachel Adams
799 N.W.2d 535 (Supreme Court of Iowa, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Kelly Concrete Company, Inc. v. Jim Sattler, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelly-concrete-company-inc-v-jim-sattler-inc-iowactapp-2021.