Keller v. Hyland Builders Corp.

186 N.E.2d 787, 38 Ill. App. 2d 209, 1962 Ill. App. LEXIS 416
CourtAppellate Court of Illinois
DecidedDecember 10, 1962
DocketGen. 48,673
StatusPublished
Cited by6 cases

This text of 186 N.E.2d 787 (Keller v. Hyland Builders Corp.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keller v. Hyland Builders Corp., 186 N.E.2d 787, 38 Ill. App. 2d 209, 1962 Ill. App. LEXIS 416 (Ill. Ct. App. 1962).

Opinion

MR. PRESIDING JUSTICE BURMAN

delivered the opinion of the court.

This is an appeal from an order of the Superior Court refusing to vacate a confessed judgment.

The action concerns promissory notes given to plaintiff by defendants in partial payment for a certain motel property. Plaintiff was the owner of and held title to the real estate in question in the name of Green Bay Washington Motel Corporation. The land had been purchased from Jerome Morrison and Harry Porett and plaintiff owed them money on the purchase price. When construction of the motel was commenced, plaintiff paid $25,000 to Porett and Morrison for the construction of off-site improvements.

Prior to the completion of the motel, in December, 1960, defendants negotiated with Morrison, Porett and plaintiff for the purchase of their respective interests in the motel. On December 17,1960, a purchase price of $106,000 was agreed upon. $10,000 was to be paid in cash with promissory notes for the balance. Nine days later, defendants agreed to execute separate judgment notes of $50,000 payable to Porett and Morrison and $44,000 payable to plaintiff. The notes were executed and delivered to the respective parties. The $50,000 due Morrison and Porett was payable as follows :

$20,000 due May 10,1961,
5.000 due July 1,1961,
5.000 due February 1,1962,
5.000 due April 1,1962,
5.000 due June 1,1962,
10.000 due July 1,1962.

The $44,000 due plaintiff was payable as follows:

$ 5,000 due July 1,1961,
10.000 due September 1,1961,
10.000 due November 1,1961,
5.000 due February 1,1962,
5.000 due April 1,1962,
5.000 due June 1,1962,
4.000 due July 1,1962.

Among other things, the purchase agreement provided that Porett was to deliver to defendants a letter guaranteeing installation of off-site improvements on or before May 1, 1961, while plaintiff was to deliver a letter certifying that he had not caused any liens to be placed on the premises other than for architectural or engineering services rendered.

The first two installments of the notes payable to Morrison and Porett, due May 10, 1961, and July 1, 1961, were paid. The first payment on the notes payable to plaintiff, due July 1,1961, was not paid. On August 24, 1961, after the forty-day grace period had lapsed, plaintiff confessed judgment for the entire amount due, pursuant to the acceleration clause.

On September 7, 1961, defendants filed a petition seeking to open up the confessed judgment, alleging that neither Porett nor plaintiff had provided the letters outlined, and “that the guarantee of the installation of off-site improvements and the certification that no liens had been placed on the premises other than for architectural and engineering services constituted a substantial portion of the consideration for defendants’ execution of the promissory notes on which judgment has been taken, and that said consideration has therefore failed.” On September 18, 1961, defendants filed a supplemental affidavit setting forth offsetting claims against plaintiff in the following amounts:

$ 2,166, the amount of a mechanic’s lien filed by Soil Testing Service for services requested by plaintiff,
30.000, cost of off-site improvements not completed as per contract,
25.000, damages arising from failure to complete off-site improvements.

The affidavit did not contain a copy of the lien nor were the damages or cost of off-site improvements explained.

On September 25, 1961, the court ordered the judgment be opened up for the purpose of permitting defendants to offer evidence. The only evidence offered by defendants consisted of the testimony of Howard Nadolna, one of the defendants. Morrison, Milton Staven, a consulting engineer, and plaintiff testified for plaintiff. Mr. Nadolna’s testimony was devoted primarily to the off-site improvements. In addition to a sanitary and storm sewer and water main, Mr. Nadolna contended the off-site improvements included a paved street.

The power to open or vacate a judgment by confession is an equitable one, to be governed by equitable principles. 23 ILP, Judgments, sec 191, p 278. “A motion to set aside a judgment is addressed to the sound legal discretion of the court, the invocation of which must be preceded by an adequate showing, . . . that a meritorious defense can be made. . . . A court should not undo a matter simply to redo it at a later date unless there is a reasonable expectancy that it might do it differently.” Sarro v. Illinois Mut. Fire Ins. Co., 34 Ill App2d 270, 273, 275, 181 NE2d 187. “The mere statement that a defendant has a meritorious defense is not sufficient. The grounds and facts upon which the merits of the defense arise must be stated so that the court will be enabled to judge the merits of such defense.” Whalen v. Twin City Barge & Gravel Co., 280 Ill App 596, 605-6. Thus the question before this court is whether defendants, by their petition, testimony and affidavit, have adequately shown that they can make a meritorious defense.

The supplemental affidavit set forth offsetting claims for a mechanic’s lien resulting from services ordered by plaintiff in connection with the subject premises; for the cost of off-site improvements not completed, and for damages for failure to complete off-site improvements. After the court opened the judgment to allow presentation of evidence, defendants waived presentation of proof as to claims for mechanic’s liens. Mr. Nadolna did not mention the mechanic’s lien in his testimony. With regard to the off-site improvements, Mr. Nadolna admitted that only the road remained incomplete, but he could not offer any proof, beyond his own testimony, that the road was included in the off-site improvements. Mr. Morrison denied that the road was included in the off-site improvements. The final claim concerned alleged damages for failure to complete off-site improvements. The purchase agreement provided that Mr. Porett was to deliver a letter guaranteeing installation of the off-site improvements on or before May 1, 1961. Mr. Nadolna testified that all off-site improvements, with exception of the road, were completed by early July, 1961. The motel, which contains 144 rooms, was opened for occupancy in late July. The record contains no allegations that the opening of the motel was in any way delayed because of the failure to complete tbe off-site improvements by May 1st.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
186 N.E.2d 787, 38 Ill. App. 2d 209, 1962 Ill. App. LEXIS 416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keller-v-hyland-builders-corp-illappct-1962.