Keller-Pike Co. v. Wetter

97 A. 459, 252 Pa. 340, 1916 Pa. LEXIS 618
CourtSupreme Court of Pennsylvania
DecidedFebruary 14, 1916
DocketAppeal, No. 268
StatusPublished
Cited by2 cases

This text of 97 A. 459 (Keller-Pike Co. v. Wetter) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keller-Pike Co. v. Wetter, 97 A. 459, 252 Pa. 340, 1916 Pa. LEXIS 618 (Pa. 1916).

Opinion

Opinion by

Me. Justice Mesteezat,

George F. Payne & Company, the defendants, were the general contractors for the construction of the new Stock Exchange Building in the City of Philadelphia. The part of the work to be done under the contract, known as the Mechanical Plant, was sublet to Keller-Pike Company, the plaintiff, by a contract dated May 24, 1912. Payne & Company agreed to finish the building on or before December 1,1912, and Keller-Pike Company agreed to do its part of the work by November 13, 1912. Subsequently, the Keller-Pike Company submitted a written proposal with specifications to the architect in which it agreed to install the permanent electrical equipment in the building. That work was not included in the agreement to install the mechanical plant. By an oral agreement, the price of the work was reduced and the architect instructed the plaintiff to do it, of which notice was given the defendants by the plaintiff. The work was done by the plaintiff, bills were rendered the defendants, and they received the contract price from the owner of the building. The Keller-Pike Company finished its part of the work about March 1, 1913, and the building was subsequently completed. Payments were made to the plaintiff during the progress of the work, and this action was brought to recover the balance due on the contract price, and for certain items of extra work done under each contract. The statement avers that the plaintiff completed its work on or about March 1, 1913, and that the delay in the completion of the work beyond the time specified in the contract was not due to the fault of the plaintiff, but wholly to the delay of the architect and of the defendants and their other subcontractors. Wetter filed an affidavit of defense in which, inter alia, he set up a counterclaim for failure to furnish certain items included in the contract and for damages by reason of the delay in the completion of the building which, as alleged, was “due solely and alone to the fault of the [345]*345plaintiff”; admits that the architect requested him to enter into a contract with the plaintiff for the electric wiring and that it did the work and the charge therefor was paid to the defendants by the owner; denies that the temporary lighting plant was ordered orally or otherwise, and sets up, as a defense to this part of the claim, the clause in the mechanical plant contract that “no extra work will be paid for unless price is agreed upon in writing before proceeding with the same.” As a further defense, the defendants deny the jurisdiction of the court because of the provision in the mechanical plant contract between the plaintiff and defendants that all questions of dispute should be submitted for decision to the architect. The defendants’ counterclaim was made up of various items, one of which was $470.40 for furnishing hose reels and racks which, it was claimed, were included in the mechanical plant contract of plaintiff but were installed by defendants.

The court entered judgment for part of the claim for want of a sufficient affidavit of defense, and the parties went to trial as to the balance of the claim. There was a verdict and judgment for the plaintiff for the residue of the claim except four of the five items for extra work which the court directed the jury to disallow. The other item for extra work was $595.31 for installing the temporary electric lighting which, it was conceded, was not part of the original contract between the plaintiff and defendants.

The defendants have filed several assignments of error, but the controlling questions raised may be disposed of without discussing the assignments separately. It is contended that the charge of the court restricted the plaintiff company’s liability for delay in completing the building to its own delay, and excluded from the jury’s consideration the delay of the plaintiff’s subcontractors. Two excerpts from the charge in which the court speaks of the delay of Keller-Pike Company without referring to its subcontractors are the grounds on which defend[346]*346ants rest their contention. The case was tried on directly the opposite theory. The failure to install the boilers and radiators within the time specified in the contract was the principal cause of the delay in completing the building, as alleged by defendants, and this work was to be done by the plaintiff’s subcontractors. The plaintiff alleged that they were installed as soon as the building was ready to receive them which was denied by the defendants. Much testimony was submitted on both sides of the controversy, and the record does not disclose that the plaintiff at any time denied its liability if its subcontractors had failed in the performance of this or any other duty enjoined by its contract with the defendants. The charge itself, as a whole, clearly shows that Keller-Pike Company was treated as responsible for any delay caused by its subcontractors. The court charged: “The contract between Payne & Company and Keller-Pike Company required that Keller-Pike Company should do their part of the work by November 13, 1912......So, therefore, the question will come down to you primarily to decide, whether this building was completed in time and if it was not, whose fault was it?......You will recall that when the plaintiff’s case was before you, correspondence with Keller-Pike Company was called for and read to you, in order to show that the delay in completing this building was occasioned by the subcontractors of Keller-Pike Company.” The court then refers to Faith & Company as plaintiff’s subcontractors for installing the boilers and doing a large part of the plaintiff’s mechanical work, and review's the testimony of the plaintiff’s subcontractors as to how they were delayed by the defendants and their other subcontractors. The court again says: “There was evidently a delay beyond November 13th, and who was responsible for it? Was it Keller-Pike Company, or their subcontractors? Or, was it George F. Payne & Company or their other subcontractors. Now, the same thing relates to the radiators. The last of the radiators were received [347]*347on January 13, 1913, and set during February, 1913. There were letters introduced showing that a demand was made for a delivery of the radiators; Faith & Company said the building was not in a condition to have the radiators installed.”

The appellants’ counsel manifestly understood that the case was tried on the theory that the plaintiff company was responsible for its subcontractors, and that such was the effect of the charge. In his ninth and tenth points, he refers to the “plaintiff’s failure to perform,” and the “plaintiff’s failure and neglect to complete” the work. In none of his eighteen points does he refer to the liability of the plaintiff’s subcontractors or ask the court to say to the jury that the plaintiff is responsible for its subcontractors. On the contrary, at the conclusion of its charge, the court inquired if counsel desired any further instructions, and appellants’ counsel replied that he only desired to call the court’s attention to the item for temporary electric lighting. It was the duty of counsel then to suggest what apparently was assumed throughout the trial that the plaintiff was responsible for its subcontractors, and the court would unquestionably have so instructed the jury. A party may not sit silent and take his chances of a verdict, and then if it is adverse complain of a matter which if an error would have been immediately rectified and made harmless: Commonwealth v. Razmus, 210 Pa. 609, 611.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kranchalk v. Simon
80 Pa. D. & C. 289 (Dauphin County Court of Common Pleas, 1952)
Cook v. Donaldson
145 A. 920 (Supreme Court of Pennsylvania, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
97 A. 459, 252 Pa. 340, 1916 Pa. LEXIS 618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keller-pike-co-v-wetter-pa-1916.