Keller Construction, Inc. v. State

50 Ill. Ct. Cl. 338, 1998 Ill. Ct. Cl. LEXIS 58
CourtCourt of Claims of Illinois
DecidedApril 6, 1998
DocketNo. 95-CC-0425
StatusPublished

This text of 50 Ill. Ct. Cl. 338 (Keller Construction, Inc. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keller Construction, Inc. v. State, 50 Ill. Ct. Cl. 338, 1998 Ill. Ct. Cl. LEXIS 58 (Ill. Super. Ct. 1998).

Opinion

OPINION

Epstein, J.

In this breach of contract claim against the Department of Transportation (“IDOT”), the Claimant contractor seeks $37,905 in additional compensation for installation of sheet piling that was required for “railroad protection” for the Clark Bridge construction project in Alton, Illinois. This “railroad protection” claim, which arises largely on the standard provisions of IDOT construction contracts, is before us for final decision following trial to our Commissioner, Patrick Hanley. This appears to be the first “railroad protection” construction contract claim to be decided by this Court.

Nature of the Claim

The dispute in this case is over labor and material charges for sheet-piling installation that was required for the protection of railroad traffic and structures adjacent (and under) the bridge construction project that was the subject of Claimants contract with IDOT. This temporary sheet piling for “railroad protection” was not set forth in the contract bid specifications, and was not computed as a cost element of the Claimant’s winning contract bid to IDOT. The piling was required as excavation protection by the railroad’s engineer — after the Claimant’s work had commenced — under the railroad protection provisions of IDOT’s standard specifications, which are incorporated into virtually all IDOT road and bridge construction contracts:

“§105.02 Authority of Railroad Engineer. Whenever the safety of railroad traffic during construction is concerned, the Railroad Engineer will have jurisdiction over safety measures to be taken and his/her decision as to methods, procedure and measures used shall be final, and any and all Contractors performing work near or about the railroad shall be governed by such decision. Instructions to the Contractor by the Railroad Engineer shall be given through the Engineer. Unless otherwise specified, all costs incurred in conforming to the requirements, specified herein, shall be considered as incidental to the contract and no additional compensation will be allowed.”

The Claimant contends that this sheet pile installation, which was not called out in the contract specs, was a contract “extra” that requires additional compensation under the “Extra Work” provision of IDOT’s Standard Provisions:

“§101.15 Extra Work. An item of work not provided for in the contract as awarded but found essential to the satisfactory completion of the contract within its intended scope as determined by the Engineer.”

Claimant also contends, alternatively, that IDOT, by its custom and practice of specifying the “railroad protection” work in its bid documents and of paying for such work (either as part of the bid price or as extra compensation) in cases where it failed to specify the particulars, has waived its rights under section 105.02. Claimant also asserts, alternatively, that IDOTs custom and practice of prior payment to this contractor, as well as its prior practice of specifying the railroad protection work, effects an estoppel against IDOTs invocation of section 105.02.

The Facts

Claimant was awarded the Clark Bridge approach construction contract (IDOT Contract No. 96294) pursuant to its low bid on June 10, 1991. At the time of the bidding, adjacent railroad tracks were scheduled to be relocated at the bridge site, and the railroad relocation plans were included in the bid drawings, although the timing of the railroad relocation project was unspecified. As planned and as ultimately constructed, the new Clark Bridge spanned over the relocated railroad tracks and the approach that was constructed by the Claimant.

Although the IDOT bid plans and specifications did show the specific plans for the railroad track relocation, IDOTs bid plans and specifications did not specifically call for the use of sheet piling (or any other method) to protect railroad property during the bridge/approach construction. When the Claimant’s work commenced, the railroad construction had not yet progressed to where bridge construction would interfere with the railroad. The Claimant did not include sheet piling for railroad protection in its bid.

After construction began, it became necessary for the Claimant to provide protection to the railroad relocation. After long negotiation with the engineer of the Norfolk & Southern Railroad, Claimant was directed to install temporary sheet piling to protect the railroad tracks (pursuant to the authority provided by section 105.02 and section 107.12 of the IDOT standard provisions). Claimant installed a sheet pile wall 95 feet long and 21 feet deep. After the contract was performed, the Claimant submitted its final billing, including $37,905 as an extra work item for the sheet piling (computed at $19/square foot, the contract pay item rate for such work) that was not included in the bid but was used on the project as mandated by the railroad. The Department refused to pay, based on its finding that the sheet piling was not an extra item but was an incidental item to be included in the bid price under section 105.02. This claim ensued.

The Trial; Evidentiary Rulings

A hearing was held on November 26, 1995 and March 19, 1996 before Commissioner Hanley, who filed his report to the full Court.

Testimony was presented by Richard Call, IDOT studies and plan senior squad leader; Bobby D. Martin, IDOT railroad technician; Larry Lipe, IDOT estimating technician; Alan Goodfield, IDOT engineering geologist in its bureau of bridges and structures; Jerry Wibbenmeyer, IDOT supervising field engineer; Dale Klohr, IDOT District 8 Engineer for District 8; Jerry Hamam, Claimants EEO officer, safety officer and corporate secretary; William Ulivi, IDOT supervisor in its department of planning.

Much of the testimony concerned contract interpretation and administration matters, but the IDOT witnesses did acknowledge that they had intended to include specific railroad protection material — warnings that it would be necessary in the Clark Bridge project at a minimum, if not actual work specs — and that their omission of such references was an unintentional mistake. The testimony also showed, without dispute, that during the approximate 28 days that the bidders had to formulate their bid submissions, it was virtually impossible to obtain a definitive “railroad protection” plan from this or any railroad involved.

Numerous documents were also admitted into the record, including a memorandum written by Richard Call, a copy of the contract and plans for the Clark Bridge project, plans for other jobs, excerpts from the Stanford Specifications for Road and Bridge Construction, the preconstruction conference report letters from the railroad, and letters to and from the Claimant.

Evidence of other IDOT construction contracts with this Claimant and with other contractors, and of the payment treatment accorded to various railroad protection work under those contracts, as well as testimony about IDOTs practices in this area, was admitted by the Commissioner over IDOTs objections on relevance grounds primarily.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
50 Ill. Ct. Cl. 338, 1998 Ill. Ct. Cl. LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keller-construction-inc-v-state-ilclaimsct-1998.