Kel Weatherstrip Co. v. Rankin

124 F. Supp. 555, 15 Alaska 204, 46 A.F.T.R. (P-H) 803, 1954 U.S. Dist. LEXIS 2901
CourtDistrict Court, D. Alaska
DecidedOctober 5, 1954
DocketNo. A-9450
StatusPublished

This text of 124 F. Supp. 555 (Kel Weatherstrip Co. v. Rankin) is published on Counsel Stack Legal Research, covering District Court, D. Alaska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kel Weatherstrip Co. v. Rankin, 124 F. Supp. 555, 15 Alaska 204, 46 A.F.T.R. (P-H) 803, 1954 U.S. Dist. LEXIS 2901 (D. Alaska 1954).

Opinion

FOLTA, District Judge.

This is a suit for the foreclosure of a mechanic’s lien under Sec. 26-1-1 et seq., A.C.L.A.1949, for labor and material furnished for the modernization of the defendants Rankins’ home, in the sum of $1,397.67, and to recover the sums of $500 allegedly due under the contract pursuant to which such labor and materials were furnished, and $550.70 which the plaintiff paid as an indorser of the note executed by the Rankins to the plaintiff concurrently with the execution of the contract.

It has been stipulated that the mortgage lien of the defendant First National Bank is entitled to priority. The lien of the defendant, United States, for unpaid income taxes of the Rankins for the year 1951, however, remains for adjudication. The Rankins contend that since the plaintiff is only secondarily liable on the note, its payment of $550.70 [557]*557was as a volunteer and that hence they are not liable to the plaintiff. By way of counterclaims, they allege that the plaintiff defaulted in the performance of the work agreed to be done, to their damage in the sums of $1,000, the estimated cost of completion, $2,100 for loss of rentals as a direct result of the alleged failure to complete the job, and $1,875 for unpaid wages.

On April 27, 1953, the plaintiff and the Rankins entered into a contract for the modernization of the Rankin home in consideration of the payment of $3,000. The contract recites the payment of $500 down and requires a payment of monthly installments of $79.85. The job is laconically described as “furnish labor (and) material to repair sidewall and foundation of structure of present building”. For the purpose of obtaining the loan of $2,500, a note was executed by the Rankins. Following default in payment thereof, the plaintiff paid $550.70.

The testimony is in irreconcilable conflict on every point. No useful purpose could be served by attempting to review it.

The Rankins contend that, contrary to its express terms, the contract was for $2,500, the amount of the FHA loan, and that the recital of the payment down of the sum of $500 is false and was made at the behest of the plaintiff to enable them to qualify on paper for the loan. The plaintiff admits that no payment down was made, but contends that it was never intended to relieve the defendants of the payment of the entire sum of $3,000. The “repair” of the “sidewall” was to consist of sheathing the exterior walls, and the “repair” of the foundation was to consist of the erection of basement walls of concrete blocks. It appears that the parties construed this written contract to require the plaintiff to furnish labor and material for the sidewall job and material only for the foundation. When the borrowed funds were exhausted before the job was completed, an oral contract was entered into, the terms of which not only appear to be interwoven with those of the written contract, but are in sharp conflict. The plaintiff contends that so far as the basement job is concerned, it was to supply material under the written contract for the foundation only, and that all materials and labor for all other jobs in the basement, consisting of laying a concrete floor and restoring the apartment to its previously tenantable condition, were to be furnished under the oral contract; whereas the Rankins assert that, so far as the basement job is concerned, including the foundation, the plaintiff, under the written contract, was to supply all the material required to complete that job, and under the oral contract was to supply all the labor in consideration of the defendant Gordon Rankins’ entering its employ as a plumber, and agreeing to the deduction from his wages of 60% to apply on the contract.

I find that under the oral contract the plaintiff was to furnish labor to complete the basement walls, to lay a concrete floor, and furnish materials and labor to restore the basement apartment to its previously tenantable condition, and that the defendant Gordon Rankin was to enter plaintiff’s employ as a plumber because it was deemed more advantageous to the parties to have Rankin work as a plumber than as a laborer in his own basement.

I find that the plaintiff did not abandon his job until after Rankin had quit; that the promises under the oral contract were mutually dependent; that Gordon Rankin was an employee rather than a plumbing subcontractor; that he worked 367 hours as plumber; that the prevailing rate of pay was $3.86 an hour; and that he has not been paid; that the reasonable value of the labor and material furnished to the plaintiff under the oral contract was $1,897.67, from which there should be deducted $1,416.62 due the defendant Gordon Rankin for his services as a plumber, leaving a balance of $481.05, for which plaintiff is entitled to a lien.

The defendant also contends that the plaintiff is not entitled to recover on his counter-claim for $550.70 because, [558]*558he asserts, an indorser of a note may not recover from the maker a partial payment. Although the matter is not free from doubt, it would appear that the authorities support the proposition that such a payment may be recovered. Wright v. Butler, 6 Wend., N.Y., 284, 21 Am.Dec. 323; Clark v. Northern Pacific Railway Co., 55 N.D. 454, 214 N.W. 33; Rawlings v. Poindexter, 14 Smedes & M., Miss., 66, 53 Am.Dec. 125; Dittmar v. Frye & Co., 200 Wash. 467, 93 P.2d 717; Whitten v. Kroeger, 183 Okl. 327, 82 P.2d 668.

I conclude, therefore, that the plaintiff is entitled to reimbursement for the $550.70 paid on the Rankin note and credited thereto by the FHA.

The plaintiff urges the inclusion of an order in the judgment holding it harmless on its indorser’s obligation on the note. No authority is cited or theory stated upon which such a provision could be based. If the plaintiff has in mind something in the nature of a bill quia timet, the answer is that there is apparently no authority for extending that remedy to the field of negotiable instruments. The Rankins insist that the parties should be held in pari delicto for participating in the fabrication of documentary evidence of the down payment, and the completion of the job. Since, however, the written contract has been fully executed and no evidence was introduced for the purpose of showing that fraud was actually perpetrated on the FHA, there is an insufficient basis for the application of the rule.

Priority of Liens

The question of priority as between the plaintiff’s lien and that of the defendant United States arises under the cross-claim of the United States for income taxes. On July 8, 1953, the plaintiff filed its claim of lien under Sec. 26-1-1 et seq., A.C.L.A.1949. In conformity with the provisions of 26 U.S.C.A. § 3670, the United States filed its claim of lien on June 15, 1953. Sec. 3671, Title 26 U.S.C.A., provides that such lien shall arise at the time the assessment list is received by the Collector of Internal Revenue, and Sec. 3672 provides that the lien is not valid as against any mortgagee, pledgee, purchaser, or judgment creditor until notice has been filed by the Collector.

Since the foregoing federal statutes and the insolvency statute, R.S. 3466, 31 U.S.C.A. § 191, have undergone a strikingly parallel development, culminating in United States v. Security Trust & Savings Bank, 340 U.S. 47, 71 S.Ct. 111, 95 L.Ed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Snyder
149 U.S. 210 (Supreme Court, 1893)
County of Spokane v. United States
279 U.S. 80 (Supreme Court, 1929)
United States v. Guaranty Trust Co. of NY
280 U.S. 478 (Supreme Court, 1930)
New York v. MacLay
288 U.S. 290 (Supreme Court, 1933)
United States v. Texas
314 U.S. 480 (Supreme Court, 1941)
United States v. Waddill, Holland & Flinn, Inc.
323 U.S. 353 (Supreme Court, 1945)
Illinois Ex Rel. Gordon v. Campbell
329 U.S. 362 (Supreme Court, 1946)
United States v. Security Trust & Savings Bank
340 U.S. 47 (Supreme Court, 1950)
United States v. Gilbert Associates, Inc.
345 U.S. 361 (Supreme Court, 1953)
United States v. City of New Britain
347 U.S. 81 (Supreme Court, 1954)
United States v. Guaranty Trust Co. of New York
33 F.2d 533 (Eighth Circuit, 1929)
In Re Taylorcraft Aviation Corporation
168 F.2d 808 (Sixth Circuit, 1948)
United States v. Eisinger Mill & Lumber Co.
98 A.2d 81 (Court of Appeals of Maryland, 1953)
Clark v. Northern Pacific Railway Co.
214 N.W. 33 (North Dakota Supreme Court, 1927)
Whitten v. Kroeger
1938 OK 442 (Supreme Court of Oklahoma, 1938)
Dittmar v. Frye & Co.
93 P.2d 717 (Washington Supreme Court, 1939)
Hawkins v. Savage
110 F. Supp. 615 (D. Alaska, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
124 F. Supp. 555, 15 Alaska 204, 46 A.F.T.R. (P-H) 803, 1954 U.S. Dist. LEXIS 2901, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kel-weatherstrip-co-v-rankin-akd-1954.