Keith Sevick v. Lifetime Inc

CourtCourt of Appeals for the Third Circuit
DecidedSeptember 18, 2025
Docket24-2384
StatusUnpublished

This text of Keith Sevick v. Lifetime Inc (Keith Sevick v. Lifetime Inc) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keith Sevick v. Lifetime Inc, (3d Cir. 2025).

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _____________

No. 24-2384 _____________

KEITH SEVICK, Appellant

v.

LIFETIME INC; LFT CONSTRUCTION CO LLC, doing business as Lifetime Construction; AGL SPRAY FOAM LLC

_____________________________________

On Appeal from the United States District Court for the District of New Jersey (District Court No. 3:21-cv-02122) District Judge: Honorable Robert Kirsch _____________________________________

Submitted Pursuant to �ird Circuit L.A.R. 34.1(a) September 16, 2025

(Filed: September 18, 2025)

Before: RESTREPO, McKEE, RENDELL, Circuit Judges. _________ O P I N I O N* _________

* �is disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not constitute binding precedent. RENDELL, Circuit Judge.

Appellant Keith Sevick sued Appellees Life Time, Inc. and LFT Construction

Company, LLC (collectively “Life Time”) for negligence that resulted in serious injuries

sustained while applying paint onto foam insulation in Life Time’s building. �e District

Court granted summary judgment to Life Time because it concluded Life Time owed no

duty to protect against the hazard that caused Sevick’s injury. We will affirm.

I.

Sevick’s employer, AGL Foam Spray, LLC (“AGL”), was a subcontractor at Life

Time’s construction site responsible for installing foam insulation. Sevick’s job was to

spray fireproof paint on top of the insulation using a “spray machine.” Sevick v. Life Time

Inc., No. 21-cv-2122, 2024 (RK) (JTQ), WL 3219615, at *1 (D.N.J. June 28, 2024).

Electric heaters were on site to keep the paint warm.

Sevick and his coworker, Steven Appenzeller, had been experiencing problems

with the building’s electrical system. When the spray machine was plugged into a

building outlet, a breaker would trip. Eventually, Appenzeller was able to make the spray

machine work by plugging it into one of the electric heaters. Doing so apparently allowed

the spray machine’s power to “ ‘bypass’ the circuit breaker in the outlets.” Sevick, 2024

WL 3219615, at *3.

At some point, the hose of the spray machine was placed “on top of the heater,”

although the record does not reveal who placed it there. Id. at *4. Heat from the heater

then created a rupture in the hose, from which paint sprayed out. Life Time employee

Wilhelm Haeger, noticing the situation from several feet away, waved his arms and

2 pointed at the spray machine. Sevick approached the machine but was unable to reach the

button to turn it off, as the spraying paint blocked his path. Instead, Sevick grabbed the

hose—causing extensive injuries to his hand and arm. He was then able to turn off the

machine by kicking the power button.

�e spray machine was AGL’s own equipment. �e parties dispute who supplied

the heater, but there is evidence (albeit conflicting) that it was supplied by Life Time. �e

contract between AGL and Life Time “required AGL to supply temporary power and heat

(to the extent not provided by Life Time) to complete AGL’s work.” Id. at *10 (citation

modified). �e contract also generally obligated AGL to assume responsibility for the

safety of its own employees, although there was testimony that, in practice, Life Time’s

supervisors monitored the entire job site for safety issues.

II. 1

�e District Court granted summary judgment to Life Time because it concluded

Life Time owed no duty to guard against the hazard that caused Sevick’s injury.

�e parties agree that Life Time stood in the position of a general contractor in

charge of the worksite. Under traditional negligence principles, a general contractor is

obligated “to exercise reasonable care to maintain the premises in a reasonably safe

condition” but need not eliminate “known hazards which are part of or incidental to the

very work the [sub]contractor was hired to perform.” Wolczak v. Nat’l Elec. Prods. Corp.,

1 �e District Court had jurisdiction under 28 U.S.C. § 1332(a). We have jurisdiction under 28 U.S.C. § 1291.

3 168 A.2d 412, 415, 417 (N.J. Super. Ct. App. Div. 1961). �e District Court reasoned that

Sevick’s injury fell into the latter category because it was caused by AGL’s own

equipment and AGL routinely worked near heaters when needed to keep its paint warm.

Sevick, 2024 WL 3219615, at *7. �e District Court rejected Sevick’s argument that

Appenzeller’s decision to power the spray machine in an unusual way—i.e., from a

heater—should change that result. Life Time had no involvement in that decision, which

reflected, instead, the “subcontractor’s choice to carry out its task in an abnormally

hazardous way.” Id. at *8.

�e District Court also determined that Life Time owed no duty under the modern

negligence principles stated in Alloway v. Bradlees, Inc., 723 A.2d 960 (N.J. 1999). In

that case, an employee of a subcontractor was injured when she attempted to work around

a mechanical flaw in her truck, and the New Jersey Supreme Court reasoned the facts

could support imposing a duty on the general contractor based on its awareness of the

hazard (and unfulfilled offer to repair it), its control over the plaintiff’s work, and its

possible violation of OSHA regulations. Id. at 965–69. But as the District Court here

explained, this case was different: Life Time had no awareness that Appenzeller would

plug the spray machine into a heater, that an unidentified person would place the hose

over it, or that Sevick would reach for the damaged hose. Nor did Life Time have control

over AGL’s equipment or how that equipment would be used, other than general

supervisory control over the worksite. Sevick, 2024 WL 3219615, at *11. Notably, AGL

was supposed to supply its own “temporary power” if needed, leaving “no basis to

conclude that it was foreseeable to Life Time that AGL’s employees would plug their

4 equipment (the spray machine) into a heating unit . . . , let alone that doing so would lead

to the hose being laid on top of the heating unit and a leak forming.” Id. at *10.

As for OSHA regulations, Sevick’s expert had opined that Life Time violated two

regulations, but the District Court found them inapplicable. A regulation requiring

sufficient clearance and ventilation around heaters to prevent fires bore no relation to how

Sevick’s injury occurred. Id. at *12 (citing 29 C.F.R. § 1926.154). �e other regulation

merely defined the word “[b]arricade” but did not require barricades to be placed around

heaters. 29 C.F.R. § 1926.203 (effective prior to July 15, 2019).

Finally, the District Court was “quite dubious” of Sevick’s theory that Haeger, in

pointing at the ruptured hose and waving his arms, negligently performed a “service[]” to

Sevick as provided in Restatement (Second) of Torts § 323 (1965). Sevick, 2024 WL

3219615, at *13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alloway v. Bradlees, Inc.
723 A.2d 960 (Supreme Court of New Jersey, 1999)
Wolczak v. National Electric Products Corp.
168 A.2d 412 (New Jersey Superior Court App Division, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
Keith Sevick v. Lifetime Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keith-sevick-v-lifetime-inc-ca3-2025.