Keiland Construction L L C v. Weeks Marine Inc

CourtDistrict Court, W.D. Louisiana
DecidedMay 5, 2023
Docket2:20-cv-00827
StatusUnknown

This text of Keiland Construction L L C v. Weeks Marine Inc (Keiland Construction L L C v. Weeks Marine Inc) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keiland Construction L L C v. Weeks Marine Inc, (W.D. La. 2023).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA LAKE CHARLES DIVISION

KEILAND CONSTRUCTION LLC CASE NO. 2:20-CV-00827

VERSUS JUDGE JAMES D. CAIN, JR.

WEEKS MARINE INC ET AL MAGISTRATE JUDGE KAY

MEMORANDUM RULING

Before the court are cross-motions for summary judgment [docs. 95, 97] filed, respectively, by plaintiff Keiland Construction LLC (“Keiland”) and defendant Weeks Marine, Inc. (“Weeks”) on the proper calculation of damages. Both motions are opposed. Docs. 98, 104. I. BACKGROUND

This suit arises from Weeks’s early termination of its subcontract with Keiland. Weeks, a New Jersey company, was acting as general contractor at the Venture Global LNG Site in Cameron Parish, Louisiana, and subcontracted work on a storm surge wall at the site to Keiland, a Louisiana company. Keiland began this work pursuant to a Short- Form Construction Subcontract executed with effective date of December 18, 2019. Weeks sent notice of its intent to terminate the work “effective immediately” to Keiland by email on March 18, 2020, and by undated letter received shortly thereafter. Under the terms of the subcontract, it maintains, this action converted Keiland’s compensation from a lump sum basis to a cost-plus basis for all work performed. Keiland asserted, however, that the termination only converted compensation to a cost-plus basis for work performed between the notice of termination and the termination and that Weeks failed to pay outstanding sums

due under the subcontract. Accordingly, it filed suit in the 38th Judicial District Court, Cameron Parish, Louisiana, raising a claim of breach of contract.1 Doc. 1, att. 1. Weeks removed the matter to this court on the basis of diversity jurisdiction, 28 U.S.C. § 1332. The matter was bifurcated for trial with damages deferred until after the contract interpretation issues had been resolved. After a bench trial, the undersigned sided with Weeks on the contract interpretation and concluded that the termination converted

Keiland’s compensation to a cost-plus basis of 21 percent for all work performed through the date of termination. Doc. 91. The parties have now filed cross-motions for summary judgment on the damages due to Keiland. Docs. 95, 97. Specifically, Weeks asserts that Keiland cannot show any remaining actual costs after its (Weeks’s) prior payments of $298,452.18, and that Weeks is instead entitled to a return of the excess amount it paid.

Keiland maintains that it incurred $563,391.77 in costs with the applicable 21 percent markup and is thus owed $264,939.59 after deducting Weeks’s prior payments. Both parties also assert that they are the prevailing party in this dispute and entitled to attorney fees from the other under the subcontract.

1 Keiland initially raised claims against Weeks employee Jansson Wurster, but these were dismissed pursuant to a joint stipulation after Weeks raised allegations of improper joinder in its Notice of Removal. Docs. 1, 21. It also raised a claim under the Louisiana Unfair Trade Practices Act, but later dismissed same pursuant to Federal Rule of Civil Procedure 41(a)(2). Docs. 53, 54. II. SUMMARY JUDGMENT STANDARD

Under Rule 56(a), “[t]he court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” The moving party is initially responsible for identifying portions of pleadings and discovery that show the lack of a genuine issue of material fact. Tubacex, Inc. v. M/V Risan, 45 F.3d 951, 954 (5th Cir. 1995). He may meet his burden by pointing out “the absence of evidence supporting the nonmoving party’s case.” Malacara v. Garber, 353 F.3d 393, 404 (5th Cir. 2003). The non-moving party is then required to go beyond the pleadings and show that there is a genuine issue of material fact for trial. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). To this end he must submit

“significant probative evidence” in support of his claim. State Farm Life Ins. Co. v. Gutterman, 896 F.2d 116, 118 (5th Cir. 1990). “If the evidence is merely colorable, or is not significantly probative, summary judgment may be granted.” Anderson, 477 U.S. at 249 (citations omitted). A court may not make credibility determinations or weigh the evidence in ruling on

a motion for summary judgment. Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S. 133, 150 (2000). The court is also required to view all evidence in the light most favorable to the non-moving party and draw all reasonable inferences in that party’s favor. Clift v. Clift, 210 F.3d 268, 270 (5th Cir. 2000). Under this standard, a genuine issue of material fact exists if a reasonable trier of fact could render a verdict for the nonmoving party.

Brumfield v. Hollins, 551 F.3d 322, 326 (5th Cir. 2008). III. LAW & APPLICATION

Under Erie Railroad Co. v. Tompkins, 304 U.S. 64 (1938), a federal court sitting in diversity jurisdiction applies the substantive law of the forum state. Cates v. Sears, Roebuck & Co., 928 F.2d 679, 687 (5th Cir. 1991). Louisiana law provides that a contract is read for its plain meaning and operates as the law between the parties. In re Liljeberg Enterprises, Inc., 304 F.3d 410, 439 (5th Cir. 2002). “[W]hen the words of a contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties’ intent.” Apache Deepwater, LLC v. W&T Offshore, Inc., 930 F.3d 647, 656 (5th Cir. 2019) (internal quotations and alterations omitted). This rule “does not allow the parties to create an ambiguity where none exists and does not authorize courts

to create new contractual obligations where the language of the written document clearly expresses the intent of the parties.” Omnitech Intern., Inc. v. Clorox Co., 11 F.3d 1316, 1326 (5th Cir. 1994). Additionally, “[e]ach provision in a contract must be interpreted in light of the other provisions so that each is given the meaning suggested by the contract as a whole.” La. Civ. Code art. 2050.

As determined at the bench trial, Weeks’s termination converted Keiland’s compensation structure to cost-plus under § 9 of the subcontract, entitling the latter “to the actual and necessary expenses of finishing its Work through the date of termination, the actual and necessary expenses of withdrawing from the Project site, and twenty-one percent (21%) for overhead and profit associated with its Work through the date of termination.”

Doc. 91, p. 4. Keiland claims it is owed the following: (1) $92,621.77 for labor costs for the E&A Craft Laborers incurred between January 31 and March 20, 2020; (2) $142,400.18 for labor costs incurred by its own employees who were billed to the project; (3) $2,396.35

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Omnitech International, Inc. v. Clorox Co.
11 F.3d 1316 (Fifth Circuit, 1994)
Tubacex, Inc. v. M/V Risan
45 F.3d 951 (Fifth Circuit, 1995)
Malacara v. Garber
353 F.3d 393 (Fifth Circuit, 2003)
Brumfield v. Hollins
551 F.3d 322 (Fifth Circuit, 2008)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Reeves v. Sanderson Plumbing Products, Inc.
530 U.S. 133 (Supreme Court, 2000)
Burdette v. Drushell
837 So. 2d 54 (Louisiana Court of Appeal, 2002)
Lambert v. Allstate Insurance Company
195 So. 2d 698 (Louisiana Court of Appeal, 1967)
Dikert v. Ruiz
231 So. 2d 633 (Louisiana Court of Appeal, 1970)
M. Carbine Restoration, Ltd. v. Sutherlin
544 So. 2d 455 (Louisiana Court of Appeal, 1989)
Provenzano v. Populis
428 So. 2d 556 (Louisiana Court of Appeal, 1983)
Breaux v. Laird
88 So. 2d 33 (Supreme Court of Louisiana, 1956)
Lho New Orleans v. Mhi Leasco New Orleans
983 So. 2d 217 (Louisiana Court of Appeal, 2008)
CK DFW PARTNERS LTD. v. City Kitchens, Inc.
541 F. Supp. 2d 839 (N.D. Texas, 2008)
Apache Corporation v. W & T Offshore, Incorporated
930 F.3d 647 (Fifth Circuit, 2019)
Pollard v. Schiff
161 So. 3d 48 (Louisiana Court of Appeal, 2015)
Foster v. Soule
310 So. 2d 170 (Louisiana Court of Appeal, 1975)
Higgins v. Rini
597 So. 2d 1238 (Louisiana Court of Appeal, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Keiland Construction L L C v. Weeks Marine Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keiland-construction-l-l-c-v-weeks-marine-inc-lawd-2023.