Keiland Construction L L C v. Weeks Marine Inc

CourtDistrict Court, W.D. Louisiana
DecidedJuly 27, 2021
Docket2:20-cv-00827
StatusUnknown

This text of Keiland Construction L L C v. Weeks Marine Inc (Keiland Construction L L C v. Weeks Marine Inc) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keiland Construction L L C v. Weeks Marine Inc, (W.D. La. 2021).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA LAKE CHARLES DIVISION

KEILAND CONSTRUCTION LLC CASE NO. 2:20-CV-00827

VERSUS JUDGE JAMES D. CAIN, JR.

WEEKS MARINE INC. MAGISTRATE JUDGE KAY

MEMORANDUM RULING

Before the court are cross-motions for partial summary judgment [docs. 34, 36] filed on the breach of contract claim brought by plaintiff Keiland Construction, LLC (“Keiland”) against defendant Weeks Marine, Inc. (“Weeks”). Both motions are opposed and are now ripe for ruling. I. BACKGROUND

This suit arises from Weeks’s early termination of its subcontract with Keiland. Weeks, a New Jersey construction company, was acting as general contractor at the Venture Global LNG site in Cameron Parish, Louisiana. Weeks subcontracted work on a storm surge wall at the project site to Keiland, a Louisiana company, and Keiland began this work pursuant to a Short-Form Construction Subcontract executed with effective date of December 18, 2019. See doc. 1, att. 1 (complaint); doc. 36, att. 1 (executed copy of subcontract). Section 5 of the subcontract provides the payment schedule, with compensation due upon the submission of monthly invoices and a total amount of $713,912.00 owed for the work described. Doc. 1, att. 1, pp. 11–12. Meanwhile, Section 9 states that Weeks may, at its option and with written notice to Keiland, “terminate for convenience any of the Work under this subcontract in whole or in part at any time[.]” Id. at 13. Upon receiving notice

of such termination, Keiland is “entitled to the actual and necessary expense of finishing its Work through the date of termination, the actual and necessary expense of withdrawing from the Project site, and twenty-one percent (21%) for overhead and profit associated with its Work through the date of termination.” Id. Weeks sent notice of its intent to terminate “effective immediately” to Keiland by

email on March 18, 2020, and by undated letter received shortly thereafter. See doc. 34, atts. 4 & 5. Up to this point Keiland had sent one payment application to Weeks, for the amount of $252,674.92. Doc. 34, att. 6. After receiving the notice Keiland sent two additional payment applications, bringing the total amount billed to $578,803.25 and representing an 82 percent completion rate for the project. Id.; see doc. 34, att. 2 (affidavit

of Keiland principal Keith DuRousseau). Keiland asserts that Weeks has failed to pay amounts due under the subcontract.1 On May 13, 2020, Keiland filed suit against Weeks in the 38th Judicial District Court, Cameron Parish, Louisiana, raising claims for breach of contract and violation of the Louisiana Unfair Trade Practices Act. Weeks removed the suit to this court on the basis

of diversity jurisdiction, 28 U.S.C. § 1332.2 The parties have now filed cross-motions for partial summary judgment on the breach of contract claim. Weeks argues that, under the

1 In its brief Weeks asserts that it has paid $200,000 to Keiland directly and $98,000 to its suppliers. Doc. 36, p. 8. 2 Keiland also initially raised claims against Weeks’s project manager Jansson Wurster, a Louisiana resident, but those claims were dismissed pursuant to a joint stipulation. See doc. 21. terms of Section 9, Keiland is only entitled to recover the “actual and necessary expenses incurred” for all work performed through the date of termination as well as certain costs associated with the termination. Keiland maintains that it is entitled to be paid based on the

original lump sum for work completed before the notice of termination and then based on the “actual and necessary expenses” for costs associated with finishing the work thereafter. II. SUMMARY JUDGMENT STANDARD

Under Rule 56(a), “[t]he court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” The moving party is initially responsible for identifying portions of pleadings and discovery that show the lack of a genuine issue of material fact. Tubacex, Inc. v. M/V Risan, 45 F.3d 951, 954 (5th Cir. 1995). He may meet his burden by pointing out “the absence of evidence supporting the nonmoving party’s case.” Malacara v. Garber, 353 F.3d 393, 404 (5th Cir. 2003). The non-moving party is then required to go beyond the pleadings and show that there is a genuine issue of material fact for trial. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). To this end he must submit

“significant probative evidence” in support of his claim. State Farm Life Ins. Co. v. Gutterman, 896 F.2d 116, 118 (5th Cir. 1990). “If the evidence is merely colorable, or is not significantly probative, summary judgment may be granted.” Anderson, 477 U.S. at 249 (citations omitted). A court may not make credibility determinations or weigh the evidence in ruling on

a motion for summary judgment. Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S. 133, 150 (2000). The court is also required to view all evidence in the light most favorable to the non-moving party and draw all reasonable inferences in that party’s favor. Clift v. Clift, 210 F.3d 268, 270 (5th Cir. 2000). Under this standard, a genuine issue of material

fact exists if a reasonable trier of fact could render a verdict for the nonmoving party. Brumfield v. Hollins, 551 F.3d 322, 326 (5th Cir. 2008). III. LAW & APPLICATION

Under Erie Railroad Co. v. Tompkins, 304 U.S. 64 (1938), a federal court sitting in diversity jurisdiction applies the substantive law of the forum state. Cates v. Sears, Roebuck & Co., 928 F.2d 679, 687 (5th Cir. 1991). Louisiana law provides that a contract is read for its plain meaning and operates as the law between the parties. In re Liljeberg Enterprises, Inc., 304 F.3d 410, 439 (5th Cir. 2002). “[W]hen the words of a contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties’ intent.” Apache Deepwater, LLC v. W&T Offshore, Inc., 930 F.3d 647, 656 (5th Cir. 2019) (internal quotations and alterations omitted). This rule “does not allow the parties to create an ambiguity where none exists and does not authorize courts

to create new contractual obligations where the language of the written document clearly expresses the intent of the parties.” Omnitech Intern., Inc. v. Clorox Co., 11 F.3d 1316, 1326 (5th Cir. 1994). Additionally, “[e]ach provision in a contract must be interpreted in light of the other provisions so that each is given the meaning suggested by the contract as a whole.” La. Civ. Code art. 2050. Keiland argues that, under the plain language of the contract, it is entitled to be paid on a lump sum basis until the notice of termination and then on a cost-plus basis thereafter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Omnitech International, Inc. v. Clorox Co.
11 F.3d 1316 (Fifth Circuit, 1994)
Tubacex, Inc. v. M/V Risan
45 F.3d 951 (Fifth Circuit, 1995)
Malacara v. Garber
353 F.3d 393 (Fifth Circuit, 2003)
Condrey v. Suntrust Bank of GA
429 F.3d 556 (Fifth Circuit, 2005)
Brumfield v. Hollins
551 F.3d 322 (Fifth Circuit, 2008)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Cates v. Sears, Roebuck & Co.
928 F.2d 679 (Fifth Circuit, 1991)
Reeves v. Sanderson Plumbing Products, Inc.
530 U.S. 133 (Supreme Court, 2000)
Apache Corporation v. W & T Offshore, Incorporated
930 F.3d 647 (Fifth Circuit, 2019)
Whitney Bank v. SMI Companies Global, Inc.
949 F.3d 196 (Fifth Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Keiland Construction L L C v. Weeks Marine Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keiland-construction-l-l-c-v-weeks-marine-inc-lawd-2021.