Keibler-Thompson Corp. v. Steading

907 So. 2d 435, 22 I.E.R. Cas. (BNA) 677, 2005 Ala. LEXIS 18, 2005 WL 327572
CourtSupreme Court of Alabama
DecidedFebruary 11, 2005
Docket1030907
StatusPublished
Cited by8 cases

This text of 907 So. 2d 435 (Keibler-Thompson Corp. v. Steading) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keibler-Thompson Corp. v. Steading, 907 So. 2d 435, 22 I.E.R. Cas. (BNA) 677, 2005 Ala. LEXIS 18, 2005 WL 327572 (Ala. 2005).

Opinion

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 437

Keibler-Thompson Corporation appeals from the trial court's denial of its "postjudgment motion for a judgment as a matter of law, motion for a remittitur, and motion for a new trial." Because we conclude that Keibler-Thompson is entitled to a new trial, we reverse and remand.

United States Steel Corporation ("USS") operates a steel plant in Jefferson County. The plant uses a "blast furnace" to make pig iron, which is eventually refined to produce steel. Essentially, iron ore is heated in a blast furnace until it becomes a liquid; the liquid separates into liquid pig iron and "slag," a liquid by-product of the heated iron ore. Once the liquid reaches a certain temperature, USS employees drill the taphole in the furnace to allow the molten metal to flow out of the furnace and into trenches. When the liquid enters the trenches, the slag rises to the top of the molten pig iron. Using a device known as a "slag skimmer," the USS employees then skim the slag from the top so that it can travel down a trench — the "slag runner" — and drain into the slag pit. The molten pig iron travels down the trench for further refinement.

The USS blast furnace has a slag runner and a slag pit on its east side and on its west side. Each side of the furnace contains an identical set of trenches that lead to the corresponding slag pit. Only one side is used at a time; an alternate side is used with each firing of the blast furnace. In order to control the direction in which the slag flows and which slag runner and slag pit is used at a given time, a "sand dam" is placed in an area known as the "Y," the area where the two slag runners intersect and lead either to the west slag pit or the east slag pit.

In order to ensure that the slag flows freely from the blast furnace to the slag pit, USS employees monitor the flow of the slag. Once slag cools, it turns into a solid crusty material that can clog the slag runner. The runners must be cleaned to remove the dried slag that has accumulated.

In September 1990, James F. Steading began working for USS as a "blast furnace keeper." His duties included monitoring the slag runners, making sure that the slag was moving properly through the runners, and changing the sand dams to divert the slag to the appropriate runner. Occasionally, when USS needed him to, Steading would also serve as a team leader in the blast-furnace area. As team leader, Steading directed his fellow USS workers and made sure they were working safely. *Page 438

In October 1997, USS entered into a contract with Keibler-Thompson under which Keibler-Thompson agreed to provide USS with equipment and labor for cleaning the slag runners. The contract provided that Keibler-Thompson would clean the runners based on USS's scheduling orders. Article 13 of the contract provided that Keibler-Thompson should take all reasonable measures in cleaning the slag runners to prevent injuries not only to its employees but also to any other persons.

On November 16, 1998, Ricky Davis was acting as Steading's team leader. He instructed Steading to move the sand dam so the other slag pit could be used for the next running of the blast furnace. Steading placed a wooden board in the runner to stand on while he changed the sand dam. He climbed onto the board and began to shovel sand. The board on which Steading was standing fell through the crusted slag and reached a layer of molten slag. The molten slag burned Steading's foot and ankle; he suffered second-degree and third-degree burns to that foot and ankle.1

After the accident, USS conducted an accident report; that report indicated that Steading had violated safety job procedure BF-00010. According to the report, Steading had failed to put the board on which he was standing on an even surface. The accident report further indicated that the "slag runner arrangement was previously changed at 10:15 [a.m.] on November 15, 1998."

On August 5, 1999, Steading sued Keibler-Thompson and Thomas Kemble, who was employed by Keibler-Thompson as an assistant area manager, alleging negligence and asserting other claims. Specifically, Steading alleged that Keibler-Thompson had contracted with USS to provide and to maintain a reasonably safe workplace for Steading, and that Steading's injury was the result of Kemble and Keibler-Thompson's negligent design and/or maintenance of the premises where Steading worked. On September 24, 1999, Kemble and Keibler-Thompson answered, denying Steading's allegations.

On August 29, 2001, Kemble and Keibler-Thompson moved for a summary judgment. On November 30, 2001, the trial court dismissed Kemble and, on May 5, 2002, granted Keibler-Thompson's motion for a summary judgment as to all the claims other than the negligence claim.

The trial began on September 29, 2003. Steading testified that if he had known that there was molten slag underneath the crusty slag, he would not have stepped into the slag runner that day. Steading testified that part of the slag runner was clean, but that the area around the sand dam, the "Y," was full of debris. Steading testified that, had the entire runner been clean, he would have noticed the molten slag and he would not have stepped into the runner.

Steading testified that it was impossible to put the board on an even surface because there was too much crusty slag in the runner. Steading argues that "if hot slag had been in this runner just 31 hours *Page 439 prior to [his] getting into the runner to change the dam, then the entire length of the runner should have been filled with dried slag." (Steading's brief, p. 10.) He asserts that a portion of the runner was clean; therefore, he asserts, Keibler-Thompson had cleaned the runner at some point during the 31- to 32-hour period before the accident. Steading further asserts that the area around the sand dam was filled with crusty slag, and he argues, therefore, that Keibler-Thompson had not properly cleaned the entire runner. Keibler-Thompson responds that none of its employees was present at the time of the accident and that it had not performed any duties concerning the operations in the blast furnace in the three and one-half days preceding Steading's accident. Keibler-Thompson also argues that the condition of the runner at the time of Steading's accident was different from its condition when Keibler-Thompson had worked in the area more than three days earlier because the slag runners are alternated daily.

Kemble, who was no longer employed by Keibler-Thompson at the time of the trial, testified that Keibler-Thompson employees worked at the USS plant 24 hours a day. Kemble testified that Keibler-Thompson employees were at the USS plant on November 14, 15, and 16, 1998. Kemble further testified that in November 1998 Keibler-Thompson was solely responsible for cleaning the slag runners.

Mark Fowler, a USS employee who had worked in the blast-furnace area of the plant for over 25 years, testified that Keibler-Thompson was the only entity that cleaned the slag runners at the USS plant. Fowler testified that he was the USS employee who had the most contact with Keibler-Thompson. Fowler testified that he did not generally check on the work performed by Keibler-Thompson employees when he told them to clean the slag runners. Fowler does not remember the job assignment he gave to the Keibler-Thompson employees on November 15 or 16, 1998.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

412 South Court Street, LLC v. Alabama Psychiatric Services, P.C.
163 So. 3d 1020 (Court of Civil Appeals of Alabama, 2014)
Lively v. Kilgore
51 So. 3d 1045 (Court of Civil Appeals of Alabama, 2010)
Chavers v. State
58 So. 3d 829 (Court of Criminal Appeals of Alabama, 2009)
Jordan Ex Rel. Jordan v. Calloway
7 So. 3d 310 (Supreme Court of Alabama, 2008)
Davis v. Hanson Aggregates Southeast, Inc.
952 So. 2d 330 (Supreme Court of Alabama, 2006)
Ex Parte Benford
935 So. 2d 421 (Supreme Court of Alabama, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
907 So. 2d 435, 22 I.E.R. Cas. (BNA) 677, 2005 Ala. LEXIS 18, 2005 WL 327572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keibler-thompson-corp-v-steading-ala-2005.