Kehne Electric Co. v. Steenberg Construction Co.

177 N.W.2d 309, 287 Minn. 193, 1970 Minn. LEXIS 1103
CourtSupreme Court of Minnesota
DecidedMay 15, 1970
Docket42110
StatusPublished
Cited by6 cases

This text of 177 N.W.2d 309 (Kehne Electric Co. v. Steenberg Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kehne Electric Co. v. Steenberg Construction Co., 177 N.W.2d 309, 287 Minn. 193, 1970 Minn. LEXIS 1103 (Mich. 1970).

Opinion

Peterson, Justice.

Defendant, Steenberg Construction Company, and plaintiff, Kehne Electric Company, Inc., are prime contractor and subcontractor, respectively, upon a project of the Minneapolis-St. Paul Sanitary District situated in a low-lying area close to the Mississippi River in St. Paul, Minnesota. Plaintiff sustained flood damage to electrical work it had performed and sued defendant upon its subcontract to recover the amount of those damages. 1 Defendant appeals from an order denying its motion for a new trial and from the judgment in favor of plaintiff.

The basic issue is one of contractual interpretation: Whether *195 by contract the defendant prime contractor is responsible for loss to plaintiff subcontractor resulting from flooding of the project premises. There is no allegation that defendant is liable to plaintiff because of negligence. Interpretation and application of the contractual documents to this situation involve two interrelated questions: (1) Whether the plaintiff subcontractor had itself contractually assumed the defendant prime contractor’s general responsibility for flood protection, a question the trial court answered in the negative; and (2) whether, if defendant retained responsibility for flood damage under its general contract with the project owner, it was liable to plaintiff subcontractor for such flood damage, a question the trial court answered in the affirmative. Because the contractual documents do not give unambiguous answer to these questions, the trial court appropriately received and considered evidence of prior conversations and contemporaneous conduct of the parties as an aid in interpretation of the documents and their application to the fact situation.

The general contract contains this express “special condition” :

“1.21 Possibility op Flooding. This Contractor will be responsible for all damages due to flooding of the work during the life of this contract and until final acceptance of the work by the [Minneapolis-St. Paul] Sanitary District.” 2

*196 The subcontract provides that the subcontractor agrees:

“XI. To be bound to the Contractor by the terms of the General Contract * * * and to assume toward the Contractor all the obligations and responsibilities that the Contractor assumes in and by the General Contract toward the [Sanitary District], insofar as they are applicable to this Sub-Contract.” 3

Ambiguity is imported into the subcontractual assumption of general contractual obligations by the phrase “insofar as they are applicable to this Sub-Contract.” We hold that the circumstances surrounding the contractual relationship, admissible in aid of interpretation where there is such ambiguity, support the trial court’s finding that the parties did not intend plaintiff to assume defendant’s responsibility for flood damage. Among such circumstances are these:

a. The general contract stated specific measures which the prime contractor was to take in protecting the project from flood damage, such as preflooding and diking, 4 measures which could *197 not practicably be undertaken by each of the several subcontractors. Defendant, in fact, did this work itself and without consulting plaintiff.

b. The subcontract, which is a standard form prepared by the Associated General Contractors of Minnesota, contains a provision requiring the subcontractor to obtain and maintain various types of insurance “with limits in amounts at least equal to the greater of those specified in the General Contract or those specified [in the subcontract] ; and builders risk or installation floater * * * insurance, if required by the General Contract.” Although the subcontract specified amounts for bodily injury and property damage liability, the space designated for “ [b] uilders risk or installation floater (if required)” was left blank. During negotiations and prior to submission of plaintiff’s bid for the subcontract, the president of defendant corporation told the president of plaintiff corporation that defendant would carry the builders risk insurance and that plaintiff need not do so. 5 Defendant did, in fact, take out insurance covering flood damage, and in the full amount of its general contract bid. The nature of the insurance required of plaintiff reflects an intention that it insure itself only with regard to risks inherent in performance of its own work.

c. The subcontract contains explicit references to the subcontractor’s liability for damage caused by forces within its con *198 trol 6 but, unlike the general contract, it is conspicuously silent regarding responsibility for acts of God, warranting an inference that the prime contractor was to accept responsibility for such events.

Once it is determined that defendant retained exclusive responsibility for flood damage under its general contract with the Minneapolis-St. Paul Sanitary District, it follows from the terms of the subcontract that defendant is liable to plaintiff. It is not a question of whether the subcontractor is a beneficiary of the general contract but whether, under the subcontractual relationship itself, the prime contractor was to bear the risk of loss resulting from floods.

The critical finding of the trial court, interpreting the subcontract, is:

“That considering all of the provisions of the sub-contract agreement and the specifications, including the insurance provisions of the sub-contract and the specifications relating to flood damage, and the testimony of the parties, the sub-contract agreement between plaintiff and defendant means, and the parties so intended, that the risk of physical loss or damage sustained was to be borne by defendant; and that the parties intended that protection against such possible loss or damage would be by insurance coverage obtained by defendant.”

We hold that this finding of fact is not without evidentiary support. To a considerable extent, it is the same evidence that re- *199 suited in the finding that plaintiff had not assumed defendant’s responsibility for flood damage. 7

Plaintiff’s basic obligation under its subcontract was to perform all electrical work on the project according to the architect’s plans and specifications stated in the general contract. There is no indication in this record that all the work performed prior to the flood was not in full accord with those plans and specifications, and there is no claim that the damage to the electrical installation was the result of plaintiff’s negligence or breach of contract. The controlling principle, as stated in Friederick v. County of Redwood, 153 Minn. 450, 190 N. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sayer v. Minnesota Department of Transportation
790 N.W.2d 151 (Supreme Court of Minnesota, 2010)
Mutsch v. Rigi
430 N.W.2d 201 (Court of Appeals of Minnesota, 1988)
ICC Leasing Corp. v. Midwestern MacHinery Co.
257 N.W.2d 551 (Supreme Court of Minnesota, 1977)
Christy v. Menasha Corporation
211 N.W.2d 773 (Supreme Court of Minnesota, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
177 N.W.2d 309, 287 Minn. 193, 1970 Minn. LEXIS 1103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kehne-electric-co-v-steenberg-construction-co-minn-1970.