Keeven v. St. Charles County Utilities Co.

542 S.W.2d 349, 1976 Mo. App. LEXIS 2199
CourtMissouri Court of Appeals
DecidedSeptember 28, 1976
DocketNo. 36933
StatusPublished
Cited by3 cases

This text of 542 S.W.2d 349 (Keeven v. St. Charles County Utilities Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keeven v. St. Charles County Utilities Co., 542 S.W.2d 349, 1976 Mo. App. LEXIS 2199 (Mo. Ct. App. 1976).

Opinion

NORWIN D. HOUSER, Special Judge.

Anthony D. Keeven and wife Martha Ann filed suit against St. Charles County Utility Company, Inc. in Count One for damages, alleging trespass and unlawful entry without their consent and permission upon their 100-acre tract in St. Charles County, cutting down trees, opening a trench, installing a sewer line and operating vehicles, equipment and machinery to their damage, and in Count Two for injunctive relief to compel removal of the sewer line and restrain future entry upon and further damage to their land. The utility company filed an answer denying trespass, pleading permission and consent to the entry, denying any intention to re-enter the land and continue the work, and a counterclaim invoking its power of eminent domain, to acquire by condemnation a 20-foot-wide easement right of way across the 100-acre tract for sewer line uses and purposes.

There is no controversy over the fact that the utility, through its contractor, entered Keevens’ land, felled trees, cut a trench and laid a 12-inch sewer line through all but a few feet of the 1,482-foot strip previously platted, before stopping the work and leaving the land on orders of Anthony D. Keeven, and that this work was done without the utility company first having obtained a signed easement document from landowners. The parties agreed that conversations and negotiations over a period of many months were had between Mr. Keeven and his attorney, and Mr. Patty, president of the utility company, respecting the installation of a sewer line across this tract; that the utility entered the property, surveyed and set stakes a number of times, and at various stages of the negotiations proffered to landowners three easement forms for their signatures; that landowners declined to sign any of these documents.

Landowners introduced evidence that in these negotiations no final agreement had been reached; that no permission or con[351]*351sent had been given by them to the utility company to enter the land and install the sewer line. The utility company, contra, introduced evidence that the entries of survey parties, for staking, etc., were understood by Mr. Patty to have been with the consent and permission of landowners; that Mr. Patty understood that a final agreement on an easement contract was reached in July, 1973 at the office of landowners’ attorney, at which landowners were present, by the terms of which the utility would straighten two “dog legs” in the creek area, restore the land as adequately as possible by clearing debris, trash, rubbish and brush, remove rock, provide free connection fees for existing buildings on the land, assist in procuring an easement over adjacent land for better drainage of Keev-ens’ land, and that the route of the line should be according to drawings the parties went over in the lawyer’s office. After that meeting Mr. Patty asked for inspections of the property by and bids and estimates from two contractors reference re-channeling the creek, and in August or September, 1973 the utility restaked the route without objection of landowners. Mr. Patty understood that the work could proceed without an executed easement — that the utility had the consent and permission of landowners to go ahead — and that upon completion of the work to the satisfaction of landowners the latter would then execute a formal easement document. The utility company contracted for the work to be done. Mr. Keeven had told Mr. Ruff, former owner of the utility, “No problem. Come on through any time you want.”

Landowners introduced extensive evidence of trespass; of damage to the land and the area adjacent to the trench, extending at places 100 feet on either side of the trench; strewing of thousands of rocks up to one foot in size on the land, whereby a total of four acres of the 100-acre tract was wasted for agricultural purposes or for use as a sod farm (Mr. Keeven’s principal business). The utility company sought to minimize these damages and introduced evidence that it would have removed the rocks if its contractor had not been run off the job. Evidence of $10,000 economic loss accruing to Mr. Keeven’s sod business from the depredation of the land was introduced and later stricken, after which Mr. Keeven testified that the difference between the reasonable market value of the land before and after the trespass was the sum of $10,-000. The utility, joining issue on the difference between the market value of the land before and after the taking, introduced expert testimony that the difference, not counting special benefits, was $850, but that special benefits to the land enhanced its value by $10,000.

In support of an award for punitive damages landowners introduced evidence that Anthony D. Keeven went on a hunting trip to Idaho, leaving his brother Frank in charge; that when Frank ascertained that the work had begun, and when the trenching machinery had progressed only about 100 feet into the tract, he requested of Mr. Patty that he stop construction, claiming no final agreement had been worked out, stating there was no easement right and that the contractor should get off the property; that Mr. Patty promised to go to the site and notify the contractor immediately to stop construction and get off the premises, but Mr. Patty did not do so; that three days later the line had progressed at least halfway across the land; that Frank Keeven again called Mr. Patty, who promised to go to the site and tell them to get off; that nevertheless construction continued, until Anthony D. Keeven returned and ordered the contractor off the premises. At this time only about 20 or 30 feet of pipe remained to be laid. There was evidence that at no time did Mr. Patty or Frank Keeven tell the contractor to shut down the job.

On the same day the jury returned its verdict the court entered an order of condemnation of a permanent easement over the land for the construction, operation and maintenance of the sewer line, and the right to possession upon payment of the “amount, if any, which may be assessed by the jury, this date, as actual damages.”

Landowners offered Instruction No. 3 (MAI 9.02) directing the jury to award [352]*352landowners the difference between the fair market value of the whole property immediately before the taking and the value of landowner’s remaining property immediately thereafter; Instruction No. 4 (MAI 16.02) defining “fair market value,” and Instruction No. 6 (MAI 34.03) directing the jury, in determining the value of the remaining property, not to consider any general benefit conferred upon all property within useable range of the sewer system. Landowners also offered Instruction No. 5 (MAI 10.01 modified and MAI 16.01 combined) as follows:

“If you find the issues in favor of plaintiffs, and if you believe the conduct of defendant in appropriating plaintiffs’ property was willful, wanton, or malicious, then in addition to any damages to which you find plaintiffs entitled under Instruction No. 3 you may award plaintiffs an additional amount as punitive damages in such sum as you believe will serve to punish defendant and to deter it and others from like conduct.

“The word ‘malicious’ as used in this instruction does not mean with hatred, spite or ill will, as commonly understood, but means the doing of a wrongful act intentionally without just cause or excuse.”

No instructions were offered or given on the subject of trespass. The utility company offered no instructions.

Notwithstanding the lack of instructions on trespass, that subject was thoroughly argued to the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sterbenz v. Kansas City Power and Light Co.
333 S.W.3d 1 (Missouri Court of Appeals, 2010)
Barr v. Kamo Elec. Corp., Inc.
648 S.W.2d 616 (Missouri Court of Appeals, 1983)
Cacioppo v. Southwestern Bell Telephone Co.
550 S.W.2d 919 (Missouri Court of Appeals, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
542 S.W.2d 349, 1976 Mo. App. LEXIS 2199, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keeven-v-st-charles-county-utilities-co-moctapp-1976.