Keene v. Mugford (In re Mugford)

346 B.R. 284, 2006 Bankr. LEXIS 1531
CourtUnited States Bankruptcy Court, D. Massachusetts
DecidedJuly 28, 2006
DocketBankruptcy No. 04-14261-RS; Adversary No. 04-1265
StatusPublished
Cited by1 cases

This text of 346 B.R. 284 (Keene v. Mugford (In re Mugford)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keene v. Mugford (In re Mugford), 346 B.R. 284, 2006 Bankr. LEXIS 1531 (Mass. 2006).

Opinion

MEMORANDUM OF DECISION REGARDING DEBT DIS-CHARGEABILITY

ROBERT SOMMA, Bankruptcy Judge.

By their complaint, Douglas Keene and Mary Beth Sidorowicz ask the Court to determine that their claim for damages against the Debtor arising from his alleged breach of a home improvement contract is excepted from discharge under 11 U.S.C. Section 523(a)(2)(A) and Section 523(a)(2)(B). More particularly, the Plaintiffs contend that the Debtor knowingly made a false representation when he portrayed himself to them as a skilled and experienced home improvement contractor capable of performing, and intending to perform, the work contemplated under the subject contract. The Debtor denies this contention.

I

Procedural History

On May 19, 2004, the Debtor filed a voluntary Chapter 7 petition, commencing the within case. On December 30, 2004, the Court entered an order of discharge in favor of the Debtor pursuant to § 727(a) of the Bankruptcy Code.

On August 23, 2004, the Plaintiffs commenced the within adversary proceeding. Their complaint seeks an order under 11 U.S.C. §§ 523(a)(2)(A) and 523(a)(2)(B) excepting from discharge their claim against the Debtor for damages in excess of $100,000 from his breach of a home improvement contract for renovation and addition to their home (“Residence”). Their claim for damages has not yet been adjudicated. In this proceeding, the Court determines the dischargeability of the claim, not the Debtor’s liability or the damages therefor. On July 19, 2006, the Court held a trial of the complaint and now states its findings of fact and conclusions of law in the matter so tried. For the reasons set forth below, the Court will dismiss the Plaintiffs’ complaint for determination of dischargeability.

II

Findings of Fact

On April 7, 2003, the Plaintiffs and the Debtor entered into a contract for certain modifications, renovations and improvements at the Residence (“Contract”) (“Project”). The Contract did not specify a payment or performance schedule.1 It did provide for a Project cost of $204,685 and for a $12,500 deposit which the Plaintiffs paid to the Debtor on or about the Contract date. The Plaintiffs made two further payments to the Debtor: $35,000 on [287]*287May 10, 2003 and $20,000 on August 24, 2003.2 The Project comprised a new garage, laundry, bath and mud room; an addition to the kitchen; and various other items.

Before hiring the Debtor, the Plaintiffs conducted due diligence, checking the Debtor’s references and inspecting the Debtor’s prior projects. They concluded that he had the skill and experience to complete the Project in a timely manner. At that time, the Debtor had approximately twenty years experience as a carpenter and approximately five years experience as a licensed general contractor with numerous completed projects.

At the outset, the Debtor encountered two unanticipated and previously undisclosed construction tasks not contemplated in the Contract: the need for an environmentally compliant fence at or bordering on a wetlands area adjacent to the Residence and the need to re-route the utility connections to the Residence (i.e., water and electricity lines). In addition, despite his urging otherwise, the Plaintiffs suspended his work shortly after he started to permit the construction (by another contractor) of a pool at the Residence. Hence, he did not begin actual Project construction for at least a month after the Contract, having interrupted his work schedule to accommodate the pool installation. The pool was completed in mid-July 2003.

During the period after completion of the pool and especially during September through December 2003, the Debtor appeared only intermittently at the Residence, ultimately completing the fence installation, the utilities relocation and three separate foundations (one of which sustained a crack and was apparently replaced by a successor contractor) but nothing more. During that same period, the Plaintiffs tried, without success, to communicate effectively and regularly with the Debtor regarding his sporadic and unsatisfactory performance on the Project.

The Debtor deposited the monies paid to him by the Plaintiffs into his operating account and neither escrowed nor earmarked these funds for the Project. The Contract did not require such escrow or earmarking and the Plaintiffs did not request it. The Debtor values his work on the Project at $40,000-$45,000.

The Debtor could only remember one or two names of the subcontractors he employed on the Project. He never purchased any materials for the Project other than the foundation concrete. He failed to introduce any supporting documentary evidence at trial regarding his performance.

In January 2004, the Debtor acknowledged to the Plaintiffs in writing his poor performance, attributing it to his overcommitment to multiple jobs and unspecified personal problems. Despite the Debt- or’s assurances to the Plaintiffs that he could resume the Project on a better-managed basis, the Plaintiffs had lost confidence in the Project and in the Debtor. In February 2004, concerned about the construction disarray at the Residence, the onset of a particularly cold winter, the Debtor’s unsatisfactory performance and their payment of $67,500 with little to show for their money but a fence, a utilities relocation and three foundations (one defective), they elected not to proceed under the Contract and hired another contractor.

[288]*288Thereafter,3 the Plaintiffs brought a complaint against the Debtor regarding the Project with the regulatory agency charged with oversight of home improvement contractors, the Board of Building Regulations and Standards of the Massachusetts Department of Public Safety (“Board”). On June 29, 2005, after notice and hearing, the Board issue its decision, finding that the Debtor failed to complete the Project and failed to include a Project payment or performance schedule in the Contract as required by law. M.G.L. c. 142A, §§ 17(2) and 2(a). For those violations, the Board suspended his contractor’s license for 30 days, levied a $500 fine and issued a formal reprimand. The Board’s factual findings are comparable to the allegations made in the complaint before this Court.

Ill

Discussion

a. Section 523(a)(2)(A)

In order to establish that a debt is non-dischargeable under Section 523(a)(2)(A) of the Bankruptcy Code, the Plaintiffs must prove that, in obtaining money from them, (1) the Debtor made a knowingly false representation or made a representation in reckless disregard of the truth; (2) the Debtor intended to deceive the Plaintiffs; (3) the Debtor intended the Plaintiffs to rely upon the false representation; (4) the Plaintiffs actually relied on the false representation; (5) the Plaintiffs’ reliance on the false representation was justified; and (6) the Plaintiffs’ reliance on the false representation caused damage to them. In re Spigel, 260 F.3d 27, 32 (1st Cir.2001), citing Palmacci v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ott v. Somogye
N.D. Ohio, 2020

Cite This Page — Counsel Stack

Bluebook (online)
346 B.R. 284, 2006 Bankr. LEXIS 1531, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keene-v-mugford-in-re-mugford-mab-2006.