Keber v. Stellato

77 Pa. D. & C. 314, 1951 Pa. Dist. & Cnty. Dec. LEXIS 424
CourtPennsylvania Court of Common Pleas, Beaver County
DecidedMarch 24, 1951
Docketno. 2
StatusPublished

This text of 77 Pa. D. & C. 314 (Keber v. Stellato) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Beaver County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keber v. Stellato, 77 Pa. D. & C. 314, 1951 Pa. Dist. & Cnty. Dec. LEXIS 424 (Pa. Super. Ct. 1951).

Opinion

McCreary, P. J.,

On December 23, 1949, plaintiffs filed a mechanics’ lien against defendants for the price and value of materials fur[315]*315nished and for work and labor done for and about the alteration and repair of a certain building owned by defendants and located on lot no. 708 in the Am-bridge Land Company’s Plan, situate in the Borough of Ambridge, Pa.

On February 3, 1950, defendants filed a petition and issued a rule on plaintiffs to show cause why the claim filed should not be stricken from the record. Defendants set forth in separate numbered paragraphs six reasons why the rule should be made absolute, but these six reasons may be combined into three. Briefly stated they are as follows:

1. The lien itself does not show that the last work was performed prior to December 15, 1949, notice of intention to file a lien having been given by plaintiffs to defendants on December 15, 1949. Defendant alleges that while the lien statement shows that the last work done by plaintiffs was performed on December 16, 1949, the lien shows on its face that whatever work was done on December 16th was merely an attempt to remedy the defective work completed previous to December 15th, and for the purpose of extending the time for filing the lien.

2. The second reason assigned for striking off the claim is that since the lien undertakes to state the manner in which notice was given it is defective in that it shows oh its face that no formal notice was given, within 45 days of the date of filing the lien, of an intention to file a lien as required by the provisions of section 8 of the Mechanic’s Lien Law.

3. The third reason assigned for striking off the claim is that the lien is defective in that it appears from the face of the lien and the record that the lien was filed less than 30 days after the notice of intention to file a lien was served.

We will consider these reasons in the order named.

[316]*316We agree with plaintiff that the first reason assigned for striking off the claim has no merit. We are of the opinion that the question as to whether the work done or attempted to be done on December 16th, 1949, was actually the last work done on the job, or whether it was merely a matter of correcting or replacing defective work for the ostensible purpose of extending the time for filing the lien, is a question of fact to be decided by a jury and is not one properly to be decided by the court as a matter of law from the face of the record. In his brief of argument counsel for plaintiff says:

“It is the position of the plaintiff that the Notice of Intention to file a claim must be given by the subcontractor to the owner on or before the day the claimant completed his work or furnished the last of his materials. This is provided in Section 2 of the Act of June 4, 1901, P. L. 431 (49 P. S. 23). In the plaintiff’s claim filed in this case it is set forth that in connection with the brick work, it was substantially completed but there was still an item to do of removing, straightening and re-laying a row of bricks which the owners had complained had not been properly done. The defendant argues that this on its face shows that the work was defective and therefore the completion of the defective work on December 16 cannot be counted. However, the plaintiff takes a position that the question that whether the claimant had ‘completed his work’ on or before December 16 is a matter of fact to be decided by a jury under all the evidence. The claimant came back to complete certain brick work at the request of the owner and whether this interpreted the completion of the work or not only a jury can decide. There is no admission or anything clear on the record to show that the work completed was defective. The only statement is that the owner had complained concerning the work. The [317]*317true status of whether the work was completed or not would be for a jury. In connection with the contract of October 24, 1949 dealing with the pouring of concrete on the porch floor, etc., the fact that the claimant came back on December 16 to complete the job of leveling the porch floor is a clear statement that the work was not yet completed. The testimony will show that the concrete had been poured on the porch floor in a rough state and that the final smoothing and leveling job with finer cement and concrete had yet to be completed which was to be done on December 16. The fact that the claim states that the concrete floor was to be ‘leveled’ means that the finishing coat was to be placed on it and cannot be held to be an admission that the prior work was defective as the defendant argues. Whether the concrete work was finished would again be a question for the jury to determine under the testimony as to the facts.”

With this statement we are in full accord and therefore dismiss the reason first assigned for striking off the claim as being without merit.

However, we are of the opinion that the second and third reasons assigned for striking off the claim do have merit, and that since the defects set out in the second and third reasons assigned do appear from the face of the record the court is obliged to strike the lien from the record.

Sections 2 and 8 of the Act of June 4, 1901, P. L. 431, as amended, 49 PS §§23, 101, being sections of what is known as the Mechanic’s Lien Law of Pennsylvania, make it clear that the lien as filed is defective. Section 2 reads in part as follows:

“Every structure or other improvement, and the curtilage appurtenant thereto, shall be subject to a lien for the payment of all debts due to the contractor or sub-contractor in the erection and construction or [318]*318removal thereof, in the addition thereto, and in the alteration and repair thereof, ...

“Nor shall any claim for alterations or repairs . . . be valid, unless it be for a sum exceeding one hundred; and, in the case of a sub-contrator, unless, also, written notice of an intention to file a claim therefor, if the amount due be not paid, shall have been given to the owners or some one of them, ... on or before the day the claimant completed his work or furnished the last of his materials.”

Section 8 of the Mechanic’s Lien Law reads in part as follows:

“Any sub-contractor, intending to file a claim, must give to the owner written notice to that effect, verified by affidavit, setting forth the name of the party with whom he contracted, the amount alleged to be still due, the nature of the labor or materials furnished, and the date when the last work was done or last materials furnished. Such notice must be served at least one month before the claim is filed, and within three months after the last of his work was done or materials furnished, if he has six months within which to file his claim, and within forty-five days thereafter, if he has but three months within which to file it.” (Italics supplied.)

It is clear from a reading of these two sections of the Mechanic’s Lien Law that when a subcontractor mechanic files a lien for alterations or repairs there are two notices that must be given, one an informal notice under the provisions of section 2 of the act, and the other a formal notice, under oath, setting forth details as required by section 8 of the act. Cushman in his treatise on The Law of Mechanics’ Liens in Pennsylvania makes this clear, if there ever were any doubt about it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Higgins Lumber Co. v. Marucca
48 A.2d 48 (Superior Court of Pennsylvania, 1946)
Westmoreland Guarantee Building & Loan Ass'n v. Connor
65 A. 1089 (Supreme Court of Pennsylvania, 1907)
Tenth National Bank v. Smith Construction Co.
67 A. 872 (Supreme Court of Pennsylvania, 1907)
Keely v. Jones
35 Pa. Super. 642 (Superior Court of Pennsylvania, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
77 Pa. D. & C. 314, 1951 Pa. Dist. & Cnty. Dec. LEXIS 424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keber-v-stellato-pactcomplbeaver-1951.