KD Oak Grove, LLC v. Warren & Warren Asphalt Paving, LLC
Opinion
IN THE SUPREME COURT OF MISSISSIPPI NO. 2020-IA-00810-SCT
KD OAK GROVE, LLC v. WARREN & WARREN ASPHALT PAVING, LLC
DATE OF JUDGMENT: 07/22/2020 TRIAL JUDGE: HON. SUSAN RHEA SHELDON TRIAL COURT ATTORNEYS: NED ANDREW NELSON MARK A. NELSON
RON A. YARBROUGH
COURT FROM WHICH APPEALED: LAMAR COUNTY CHANCERY COURT ATTORNEY FOR APPELLANT: RON A. YARBROUGH ATTORNEYS FOR APPELLEE: NED ANDREW NELSON SAMUEL DENON NEWMAN
MARK A. NELSON
NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: REVERSED AND RENDERED - 09/16/2021 MOTION FOR REHEARING FILED: MANDATE ISSUED:
CONSOLIDATED WITH
NO. 2020-IA-00840-SCT
KP WESTWOOD, LLC v.
WARREN & WARREN ASPHALT PAVING, LLC, WARREN PAVING, INC., AND ADS, LLC
DATE OF JUDGMENT: 07/29/2020 TRIAL JUDGE: HON. SUSAN RHEA SHELDON COURT FROM WHICH APPEALED: LAMAR COUNTY CHANCERY COURT ATTORNEY FOR APPELLANT: RON A. YARBROUGH
ATTORNEYS FOR APPELLEES: MARK A. NELSON NED ANDREW NELSON
SAMUEL DENON NEWMAN
RODERICK MARK ALEXANDER, JR.
NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: REVERSED AND RENDERED - 09/16/2021 MOTION FOR REHEARING FILED: MANDATE ISSUED:
BEFORE KING, P.J., COLEMAN AND CHAMBERLIN, JJ.
COLEMAN, JUSTICE, FOR THE COURT:
¶1. The instant case is a consolidated interlocutory appeal stemming from a dispute over construction liens. KD Oak Grove and KP Westwood entered into two separate contracts with Coumanis Allen, a general contractor. Subsequently, Coumanis did not pay subcontractors for their work, and Warren & Warren, one of Coumanis’s subcontractors, filed construction liens on Oak Grove’s and Westwood’s separate real property. Notably, in both payment actions, Warren admitted to failing to file its lis pendens notice along with its construction liens, waiting 110 days to file it. The two separate legal actions were brought before the Chancery Court of Lamar County, Mississippi, and were assigned to separate chancellors. ¶2. Oak Grove and Westwood filed separate motions for summary judgment, which were denied by the chancellors; they timely appealed. The crux of the instant appeals is one of statutory interpretation: whether the failure to comply with Mississippi Code Section 85-7- 405(1)(c)(i) (Supp. 2020), which requires the simultaneous filing of a lis pendens notice with the commencement of the payment action, renders Warren’s liens unenforceable and ineffective.
FACTS AND PROCEDURAL HISTORY KD Oak Grove ¶3. Warren filed its notice of claim of subcontractor’s lien pursuant to Mississippi Code Section 85-7-405 (Supp. 2020) against Oak Grove on November 20, 2018. On March 14, 2019, Warren filed a complaint against Oak Grove in the Chancery Court of Lamar County, commencing its payment action. Warren stated that its “payment action was commenced to recover outstanding and owed invoices for work performed under its subcontract with Coumanis.” On March 25, 2019, Oak Grove filed its answer and defenses to Warren’s complaint. ¶4. On July 2, 2019, 111 days from the commencement of the payment action, Warren filed its notice of lis pendens against Oak Grove’s property. Subsequently, Oak Grove filed a motion for summary judgment on August 30, 2019, asserting contract defenses and the failure to comply with the strict requirements of Section 85-7-405. Oak Grove filed another motion for summary judgment on March 6, 2020. After a response from Warren and a rebuttal by Oak Grove, a hearing was held on June 22, 2020, on the consolidated motions for summary judgment. Afterwards, the chancellor entered an order denying both of Oak Grove’s motions for summary judgment. Oak Grove appealed. KP Westwood ¶5. A similar set of facts are relevant to the action between Westwood and Warren. Warren filed a subcontractor’s lien claim on November 27, 2018. A day later, Westwood filed its complaint for interpleader in the claim. Warren was added as an interpleader
defendant, and on January 30, 2019, Warren filed its answer, affirmative defenses, and counterclaim, “commencing its payment action as defined by Miss. Code Ann. § 85-7-401 . . . .” Then, Warren filed its amended complaint on March 13, 2019. On July 2, 2019, Warren filed its notice of lis pendens against the property of Westwood. Westwood filed a motion to dissolve the liens, which was ultimately denied by the chancellor. Westwood appealed, and the cases were later consolidated.
DISCUSSION
¶6. The Court applies a de novo review to the grant or denial of summary judgment. Venture, Inc. v. Harris, 307 So. 3d 427, 431 (¶ 14) (Miss. 2020) (quoting Double Quick, Inc. v. Moore, 73 So. 3d 1162, 1165 (¶ 7) (Miss. 2011)). “Summary judgment is appropriate when ‘the pleadings, depositions, answers to interrogatories and admissions on file, together with the affidavits, if any, show that there is no genuine issue [as to] any material fact and that the moving party is entitled to a judgment as a matter of law.’” Id. (quoting Miss. R. Civ. P. 56(c)). ¶7. The parties do not dispute the above facts and that Warren’s claims are governed by Mississippi Code Sections 85-7-403 and 85-7-405. Rather, the statutory issue is whether Warren’s liens are unenforceable and ineffective because, in both cases, Warren failed to timely and contemporaneously file its lis pendens notices. Beyond that, Oak Grove asserts that Warren’s liens should be dissolved, because Oak Grove “relied in good faith on sworn statements in making payment to Coumanis Allen, LLC.” We will first address the statutory issue surrounding the lis pendens notice, because it is dispositive.
I. Whether Warren’s failure to file the lis pendens notice with the commencement of its payment action pursuant to Mississippi Code Section 85-7-405(1) renders its liens unenforceable and ineffective.
Free access — add to your briefcase to read the full text and ask questions with AI
KD Oak Grove, LLC v. Warren & Warren Asphalt Paving, LLC (KD Oak Grove, LLC v. Warren & Warren Asphalt Paving, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.