KB Weygand & Assoc. v. DEERWOOD LAND CO.

812 So. 2d 1165, 2001 WL 410496
CourtSupreme Court of Alabama
DecidedApril 20, 2001
Docket1991216 and 1991344
StatusPublished
Cited by1 cases

This text of 812 So. 2d 1165 (KB Weygand & Assoc. v. DEERWOOD LAND CO.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KB Weygand & Assoc. v. DEERWOOD LAND CO., 812 So. 2d 1165, 2001 WL 410496 (Ala. 2001).

Opinion

812 So.2d 1165 (2001)

K.B. WEYGAND & ASSOCIATES, P.C.
v.
DEERWOOD LAKE LAND COMPANY.
Deerwood Lake Land Company
v.
K.B. Weygand & Associates, P.C.

1991216 and 1991344.

Supreme Court of Alabama.

April 20, 2001.
Rehearing Denied July 6, 2001.

*1166 Jesse P. Evans III and Michael B. Odom of Najjar Denaburg, P.C., Birmingham, for appellant/cross appellee K.B. Weygand & Associates, P.C.

Scott A. Powell, Bruce J. McKee, and Nolan E. Awbrey of Hare, Wynn, Newell & Newton, Birmingham, for appellee/cross appellant Deerwood Land Company.

WOODALL, Justice.

The trial court entered judgment in favor of the plaintiff, Deerwood Lake Land Company ("Deerwood"), and against the defendant, K.B. Weygand & Associates, P.C. ("Weygand"). Weygand appeals from that judgment. (Case No. 1991216.) Deerwood cross-appeals from the trial court's refusal to include pre-judgment interest in its award. (Case No. 1991344.)

Deerwood is a private subdivision in Shelby County. Weygand is a civil engineering firm. In 1995, Deerwood hired Weygand to plan and execute the expansion of its lake and subdivision, including a necessary road. The road was designed and built in accordance with Shelby County's requirements for what is commonly referred to as a "6-2-1" road. The subdivision road contained a six-inch base, consisting of crushed rock, stone particles, or slag, placed on top of the subgrade. Two inches of plant-mix asphalt, or binder, was placed on top of the six-inch base. A one-inch seal coat of asphalt was required to be placed on top of the binder, but Shelby County will not allow the seal coat to be applied for one year or until ninety percent of the houses in the subdivision are constructed. The binder allows water to pass *1167 into the base, but the seal coat helps keep the water from passing through the binder into the base.

Shortly after the binder was applied, and long before the seal coat could have been applied, the road failed. Weygand hired Alain Gallet, a geotechnical engineer, to assess the failure. Gallet found that excessive water trapped below the base stone had caused the pavement to "float" and the asphalt to crack. It was Gallet's opinion that the water had infiltrated the binder layer and had become trapped below the base stone because the roadbed, also referred to as the subgrade, was impervious and, therefore, the water did not pass through it. Gallet recommended the installation of lateral drains to expedite the flow of water from beneath the base stone into existing ditches. Deerwood followed Gallet's recommendation and incurred expenses totalling $58,187.84 in repairing and repaving the road.

On April 23, 1998, Deerwood sued Weygand in the Shelby Circuit Court, seeking damages allegedly caused by the failure of the road. The complaint stated claims for negligence, breach of warranty and breach of contract. Weygand answered, denying any negligence, denying any breach of contract, and denying the existence of any warranty, express or implied.

The case was tried by the trial court without a jury. On November 2, 1999, the trial court found in favor of Deerwood and against Weygand and entered a judgment in the amount of $72,146.27 which included an award of pre-judgment interest. In basing the judgment upon a finding that Weygand had breached an implied warranty, the trial court stated as follows:

"1. The contract between the parties included an implied warranty whereby defendants `impliedly warranted the sufficiency and adequacy of the plans and specifications to reasonably accomplish the purpose for which they were intended.' Broyles v. Brown Engineering Co., 275 Ala. 35, 38, 151 So.2d 767 (1963). `[W]here one party furnishes plans and specifications for a contractor to follow in a construction job, he thereby impliedly warrants their sufficiency for the purpose in view.' Id. at 39 [, 151 So.2d 767].
"2. Because defendants' plans were inadequate, defendants are liable for breach of warranty.
"3. Because plaintiff will be compensated under the breach of warranty count, it is unnecessary to consider the breach of contract and negligence counts, and those two counts are dismissed."

(Clerk's Record at 32, 33.)

Weygand filed a post-trial motion on December 2, 1999. On February 17, 2000, the trial court amended the November 2, 1999 order, entering judgment in favor of Weygand on both the breach of contract and negligence claims. The judgment against Weygand continued to be based only on the trial court's finding that Weygand's "plans did not sufficiently provide for water drainage from the roadbed." (Clerk's Record at 50.) In its amended order, the trial court reduced the damages to $58,187.84 and found that Deerwood was not entitled to pre-judgment interest. Weygand filed a timely notice of appeal from the judgment against it. Deerwood cross-appealed only from the trial court's failure to include pre-judgment interest in its final judgment.

The following issue is dispositive: Did the trial court err in concluding that the agreement between Deerwood and Weygand included an implied warranty whereby Weygand guaranteed the sufficiency and adequacy of the plans and specifications for the road to reasonably accomplish the purpose for which they were intended? *1168 In reaching that conclusion, the trial court was required to apply the law to undisputed facts and, therefore, the ore tenus presumption of correctness does not apply. DeWitt v. Stevens, 598 So.2d 849, 850 (Ala. 1992). We conclude that the trial court incorrectly applied the law to the facts and, therefore, erred to reversal.

Deerwood and Weygand agree that the resolution of the dispositive issue must begin with an analysis of Broyles v. Brown Engineering Co., 275 Ala. 35, 151 So.2d 767 (1963). In Broyles, civil engineers agreed to submit plans and specifications to the plaintiffs for drainage of a proposed subdivision. The complaint was summarized:

"The complaint further charges that the drainage areas depicted on the plans submitted by the defendant were incorrect and did not show adequate storm drainage easements where necessary; that the drainage plans were inadequate for the purpose for which they were to be used; and that the drainage of the subdivision, due to the incorrectness of the plans and specifications submitted by defendant pursuant to its employment by plaintiffs, was (and is) subject to periodic floodings."

Id. at 37, 151 So.2d at 769. The parties' positions were stated:

"The defendant contends that in the absence of an express contract, there is no liability for the alleged insufficiency or inadequacy of the plans except as may be attributable to its negligence or its failure to use reasonable skill and diligence in their preparation. Neither negligence nor the want of reasonable skill and diligence in the preparation of the plans was charged in the complaint. A breach of implied warranty of adequate results is the gravamen of each count. Plaintiffs take the position that an implied warranty exists and it casts upon the defendant the obligation of a guarantor or insurer of the plans for the purpose in view and of which defendant had knowledge when it accepted employment."

Id. at 37, 151 So.2d at 769-770.

This Court stated in Broyles

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Electric Corp. v. Utilities Board of Foley
643 F. Supp. 2d 1302 (S.D. Alabama, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
812 So. 2d 1165, 2001 WL 410496, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kb-weygand-assoc-v-deerwood-land-co-ala-2001.