Kay Construction Co. v. Control Point Associates, Inc.

15 Mass. L. Rptr. 203
CourtMassachusetts Superior Court
DecidedAugust 16, 2002
DocketNo. 012426
StatusPublished
Cited by5 cases

This text of 15 Mass. L. Rptr. 203 (Kay Construction Co. v. Control Point Associates, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kay Construction Co. v. Control Point Associates, Inc., 15 Mass. L. Rptr. 203 (Mass. Ct. App. 2002).

Opinion

Agnes, A.J.

BACKGROUND

This is a civil action in which the plaintiff, Kay Construction Company (“plaintiff’) has brought suit against defendant, Control Point Associates, Inc. (“Control Point”) for breach of contract, negligence, indemnity for losses, and unfair practices under G.L.c. 93A, §11. Also, the plaintiff brought suit against defendant, Bohler Engineering, PC and defendant, Ludwig C. Bohler for indemnity for losses, as well as unfair practices under G.L.c. 93A, §11. Furthermore, the plaintiff brought suit against defendant, Security Insurance Company of Hartford (“Security”) for unfair practices under G.L.c. 93A, §§9, 11. The defendants deny all the allegations set forth in the plaintiffs complaint.

At this phase of the case, the plaintiff is seeking partial summary judgment for the issue of liability against Control Point for Count I, breach of contract, and Count II, negligence. Conversely, Security is seeking dismissal of Count V, unfair practices under G.L.c. 93A, §9, in addition to a stay of the proceeding for Count VI, unfair practices under G.L.c. 93A, §11.

FACTS

The plaintiff is a general contractor that had a contract with ESA Services, Inc. to build an Extended Stay America Hotel on Andover Street in Tewksbury, Massachusetts. The contract was effective April 17, 2000, and contained various “milestones” where a specific amount of the work was to be completed. Two of these “milestones” were deemed “substantial completion phases.” The first phase was to be completed 180 days from the date of commencement, while the second phase was to be completed 210 days from the date of commencement. Plaintiffs Exhibit, Tab 1 Page 4. The contract also contained a liquidated damages clause that would impose a daily $2,000 tine for each day final completion of the project was delayed. Plaintiffs Exhibit, Tab 1 Page 3.

It is hereby ORDERED pursuant to Mass.R.Civ.P. 53 and Superior Court Rule 49 an Order of Reference shall issue appointing a master to be paid by the parties to perform the accounting. If the parties are unable to agree upon a master within fifteen (15) days of receipt of this order, I shall appoint one. The master shall determine: (1) the gross profit to NAIS from the sale of Shimadzu equipment to York Hospital and deduct the reasonable expenses to arrive at the net income to the joint venture; (2) the salvage value of the loaner Alpha Review Station; (3) the additional expense, if any, incurred because Ray Tek was not on site during some of the installation of the cardiac cath lab; and, (4) the value of the service contract for the eight years of the contract excluding the two years under warranty less the expense or projected expense incurred by NAIS in the actual servicing of the equipment. Equipment listed on the sales contract but paid directly to the supplier or manufacturer by the Hospital shall not be included in the calculations.

The plaintiff hired subcontractor Control Point to provide professional land surveying services in conjunction with the ESA project. On August 21, 2000, Michael Collentro, the plaintiffs project manager, signed Control Point’s proposal (dated August 17, 2000) to provide land surveying for the plaintiff. Plaintiffs Exhibit, Tab 2A. Shortly thereafter, Paul Jurkowski of Control Point performed the requested surveying at the project site. He set the “survey points” for where the foundation was to be built, and provided the plaintiffs site supervisor, Raymond DeVita, with a field plan of the site. Plaintiffs Exhibit, Tab 6, Tab 6A. DeVita specifically requested that the “survey points” be off-set by 50 feet from where the foundation was to actually be located. This was requested so the plaintiff could adequately excavate the site and build the foun[204]*204dation in accordance with the zoning by-laws of the Town of Tewksbury. Plaintiffs Exhibit, Tab 6, Tab 11. The plaintiff requested that Control Point return to the site post-excavation in order to restore and adjust “survey points” that may have been disturbed during the excavation process, which Control Point did on August 29, 2000. Upon Control Point’s resurvey of the site, the plaintiff commenced construction of the foundation on September 15, 2000. Shortly thereafter, Control Point returned to the site in order to perform the “as-built survey.” Collentro and DeVita both noticed after reviewing the “as-built” plan that the foundation encroached on the “front and left side zoning set-backs.” Plaintiffs Exhibit, Tab 6, Tab 10. An independent survey conducted by Kevin Hinds of the Engineering Design Consultants, Inc. confirmed that the foundation was in violation of the zoning by-laws, and in his estimation the violations were a result of miscalculations made by Control Point in the formulation of the field plan. Plaintiffs Exhibit, Tab 9.

In light of the liquidated damages clause the plaintiff determined that it would be in their best interests to raze the foundation, and reconstruct it at the correct location in accordance with the zoning by-laws of the Town of Tewksbury. Control Point admits that it requested the plaintiff to refrain from razing the foundation, and instead attempt to obtain a variance from the Tewksbury Zoning Board that would enable the foundation to remain in its improper location. Plaintiffs Exhibit, Tab 3 Pages 3-4; Defendant’s Answer. The plaintiff obliged Control Point’s request, but their application for a variance was ultimately denied. Plaintiffs Exhibit, Tab 13. The plaintiff was forced to suspend construction on the project, and rebuild the foundation. Thus, the plain tiff had difficulties fulfilling the time requirements in its contract with ESA, and suffered harm as a result. Plaintiffs Complaint, Factual Allegations.

DISCUSSION

“Summary judgment is a ‘device to make possible the prompt disposition of controversies on their merits without a trial, if in essence there is no real dispute as to the salient facts or if only a question of law is involved.’ ” Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983) (citations omitted). The function of a motion under Mass.R.Civ.P. 56, is to “pierce the boilerplate of the pleadings and assay the parties’ proof in an effort to determine whether trial is actually required.” Harris v. Harvard Pilgrim Health Care, Inc., 20 F.Supp.2d 143, 146-47 (D.Mass. 1998), citing McIntosh v. Antonino, 71 F.3d 29, 33 (1st Cir. 1995). Thus, summary judgment should be granted when there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991); Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983); Mass.R.Civ.P. 56(c). Also, summary judgment may be granted against the moving party, and may be granted as to certain issues but not others. See Community Bank v. Dawes, 369 Mass. 550, 553 (1976).

The moving party bears the burden of establishing the absence of a triable issue. Pederson v. Time, Inc., 404 Mass. 14, 17 (1989). Once this is satisfied, the burden shifts to the party opposing summary judgment to allege specific facts establishing the existence of a genuine issue or issues of material fact. Id. In assessing whether each party has met its burden, the court is not permitted to weigh the evidence, to determine the credibility of any witnesses or make any findings of fact. Kelly v. Rossi, 395 Mass. 659, 663 (1985). Moreover, “[t]he evidence is ‘considered with an indulgence in the [opposing party’s] favor.’ ” Anthony's Pier Four v. Crandall Dry Dock Engineering, Inc., 396 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Myford Touch Consumer Litig.
291 F. Supp. 3d 936 (N.D. California, 2018)
Gillis v. Peerless Insurance
31 Mass. L. Rptr. 539 (Massachusetts Superior Court, 2013)
DeJesus v. Milford Regional Medical Center, Inc.
30 Mass. L. Rptr. 653 (Massachusetts Superior Court, 2012)
Reardon v. Carter
23 Mass. L. Rptr. 229 (Massachusetts Superior Court, 2007)
Kay Construction Corp. v. Control Point Associates, Inc.
16 Mass. L. Rptr. 631 (Massachusetts Superior Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
15 Mass. L. Rptr. 203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kay-construction-co-v-control-point-associates-inc-masssuperct-2002.