Kaucher, Hodges & Co. v. Buckeye Cotton Oil Co.

238 S.W. 1, 152 Ark. 249, 1922 Ark. LEXIS 29
CourtSupreme Court of Arkansas
DecidedFebruary 27, 1922
StatusPublished
Cited by2 cases

This text of 238 S.W. 1 (Kaucher, Hodges & Co. v. Buckeye Cotton Oil Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kaucher, Hodges & Co. v. Buckeye Cotton Oil Co., 238 S.W. 1, 152 Ark. 249, 1922 Ark. LEXIS 29 (Ark. 1922).

Opinion

McCulloch, C. J.

Appellants are building contractors, and in March, 1918, entered into a written contract with appellee for the -construction of a reinforced concrete building near the city of Little Rock. They agreed with appellee to “furnish the detailed plans, the building for a compensation equal to eight per cent, of the actual construction cost.” ■ Appellee was,, under the contract, to furnish and pay for all material anil labor. Appellants’ estimate of the cost of the building, including their own compensation, was the sum of $76,463, and in the contract appellants gave a 'guaranty that the cost would not exceed that sum, -but the guaranty was qualified by a clause in the contract as follows:

“It is further understood that this guaranty is made during existing conditions and does not apply should the work be interfered with or cost increased by any act of Government or any unforeseen elements or acts of God.”

Appellants gave a bond, executed by a surety company, which contained the following clause!:

“Fifth. It is hereby understood and agreed that this bond is executed by the surety and accepted by the obligee with the understanding that the contract which it guarantees is made in contemplation of the existing conditions as to the cost of labor, material, equipment, and supplies, and the cost of transportation, and the total cost of $76,463 named in said contract shall not apply, but shall be increased proportionately to the increased cost of completing the contract in the event of an increase in the cost of labor, material, equipment, supplies or transportation, or in the event of the work being interfered with or the cost increased by any act of the Government or any unforeseen elements, or act of God, or for any other reason for which the principal is not responsible.”

There was a provision in the contract for extra work as follows:

“Miscellaneous: In case additional excavation work and concrete is needed, unit prices on same to the owner to be as follows:
“Excavation at 75e per cubic yard.
“Concrete at 30'c per cubic yard.”

The building was completed in accordance with the terms of the contract, but the cost thereof was more than $20,000 in excess of the amount guaranteed by appellants, in addition to the cost of added work falling within the specification for extras. Appellee instituted this action against appellants and the surety on their bond to recover the additional cost of the building over the amount of the guaranteed cost, and appellants defend on the ground that the increased cost resulted from changed conditions with respect to prices of material and labor and inefficiency of labor.

There is also a disputed item in the account between the parties with respect to the cost of furnishing “forms” for extra concrete. This item amounted to $3,827.97, and it is the contention of appellants that this was not included within the unit price of 30 cents per cubic yard as specified in the contract. The contention of appellee is that the specified price for concrete was intended to include the cost of the “forms,” and that that clause of the specification should 'be construed to mean the price of concrete in place.

The action was instituted in the circuit court of Pulaski 'County, and by consent of parties was transferred to the chancery court, and proceeded there to a final decree. -After the testimony was introduced, the parties entered into a written stipulation in which it was agreed that the aggregate of the items of increase of cost of labor 'Claimed by appellants in the construction of the building amounted to $7,032.16, and that the cost, including labor and material, was the sum of $3,827.97, as stated in appellants’ account. Appellants claim that to the item of increased cost of labor there should be added the regular commission of 8 per cent, specified in the contract and also the 11.70 per cent, commission to cover overhead expenses, but appellee disputed the right of appellants to include these percentages in the increased estimate of cost. The stipulation was, further, that if the court allowed those claims of appellants, but disallowed their claim for increased cost alleged to be due on account of inefficiency of labor, the amount of the decree in favor of appellee should be $11,-076.38. The court in its final decree refused to charge appellants with the items of increased cost of labor as set forth in the stipulation, including the percentages referred to for compensation and overhead expenses, but charged appellants with the sum of $11,076.38, increased cost that appellants contend was caused by inefficiency of labor, and rendered a decree against appellants for that sum on its contract of guaranty. The court allowed appellants a credit for the sum claimed as the cost of furnishing “forms” for concrete. Appellants prosecuted their appeal from that part of the decree adverse to them, and appellee has cross-appealed.

There was evidence adduced which supports the finding of the court that the aggregate amount in the stipulation of counsel was expended for increased cost of labor.

The contract provides that the guaranty “is made during existing conditions and does not apply should the work be interfered with or costs increased by any act of Government or any unforeseen elements or acts of God.” Counsel for appellee contend that according to the proof the cost of labor was not increased by the act of Government in pursuing its war preparations in and about Little Roclc, but the answer to this contention is that the exception is not based entirely on interferences or increases by “act of Government,” but it provides that the guaranty does not apply to changed conditions “'from any unforeseen elements,” and the proof is abundant that there was a change of conditions with respect to the cost of labor, both skilled and unskilled, after the contract was entered into and before the build-, ing was completed. We are of the opinion also that the court was correct in adding to this increased cost the percentage specified for compensation to the contractors and overhead expenses. The contract provided for the payment of these percentages, and this applied to the percentages on such part of the increased cost as did not fall within the scope of appellant’s guaranty.

We are also of the opinion that the court was correct in allowing appellants credit for the cost of furnishing the “forms” for the extra concrete. This part of the contract appears in the specifications, which also contains a specification for the concrete work called for in the plans. There was a separate specification for “concrete work” and for “forms.” One specification provided how the concrete should be mixed, and the kind of cement to be used, and the kind of sand and rock.’ The other specification provided how the forms should be constructed, and where the lumber therefor should be delivered. The specification for extra concrete work must be read in the light of these separate specifications, and, when this is done, it seems clear that it was not intended to include the cost of making the “forms” in the specified unit price for extra concrete.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Rust
468 S.W.2d 205 (Supreme Court of Missouri, 1971)
Venters v. Bunnell
93 S.W.2d 70 (Missouri Court of Appeals, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
238 S.W. 1, 152 Ark. 249, 1922 Ark. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kaucher-hodges-co-v-buckeye-cotton-oil-co-ark-1922.