Kato Corp. v. Roche

60 F. App'x 324
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 21, 2003
DocketNo. 02-1315
StatusPublished

This text of 60 F. App'x 324 (Kato Corp. v. Roche) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kato Corp. v. Roche, 60 F. App'x 324 (Fed. Cir. 2003).

Opinion

DYK, Circuit Judge.

Kato Corporation (“Kato”) appeals the decision of the Armed Services Board of Contract Appeals (“the Board”) denying Kato’s claim for additional compensation under a contract between Kato and the Air Force. Kato alleges that it is entitled to an equitable adjustment of the contract price to compensate it for expenses it incurred in excavating, stockpiling and replacing contaminated soil encountered while removing an underground storage tank. The Board held that Kato was not entitled to an equitable adjustment based on differing site conditions. In re Kato Corp., ASBCA No. 51513, 02-1 BCA ¶ 31,-669 at 156, 492, 2001 WL 1562270 (Nov. 30, 2001). We affirm.

BACKGROUND

The Air Force awarded Contract No. F45603-96-C-0004 (“Contract”) to Kato in November 1995, at a fixed price of $502,801.00. The contract required Kato to make improvements to the heating and ventilation system at McChord Air Force Base, Building 1305, and to excavate and remove an adjacent 2,000-gallon underground fuel oil storage tank. Id. at 1.

The contract provided an overview of the work required to remove the storage tank:

The work consists of removal, decontamination and disposal of one, 2000-gal-lon underground storage tank and associated piping and ancillary equipment. The tank is constructed of steel and is at the approximate location shown on the drawings. The 2000-gallon tank was used for storing fuel oil and has not been taken out of service. Residue remaining in the tank is considered a hazardous waste. Subsurface conditions are not known. The Contractor is re[325]*325sponsible for verifying the actual conditions prior to submitting a bid.

Id. at 156,498.

Various clauses in the contract related to the prospect of finding contaminated soil at the worksite. The contract contained a provision providing, “[it] is not anticipated that contaminated soil will be encountered. If found, contact the Contracting Officer or authorized representative for further direction.” Id. A variety of other provisions addressed the contractor’s responsibilities in the event contaminated soil was discovered. For example, the paragraph entitled “Tank Excavation” provided, in part:

Excavation around the perimeter of the tank shall be performed in a manner that will limit the amount of potentially contaminated soil that could be mixed with previously uncontaminated soil. Contaminated soil shall be segregated in separate stockpiles. Surface water shall be diverted to prevent direct entry into the excavation.

(J.A. at 23.) The contract paragraph entitled “Stockpiles” provided, in part:

Excavated material which is visibly stained and which has an obvious petroleum odor or as required by the State of Washington or implementing agency shall be considered contaminated and shall be stockpiled for sampling in accordance with Paragraph Stockpiled Material Sampling. Uncontaminated soil shall be stockpiled separately from the contaminated soil, a safe distance away from, but adjacent to, the excavation. Contaminated soil shall be placed on an impermeable geomembrane a minimum of 30 mils thick, and covered with a 10 mil sheet of geomembrane. The geomembrane shall be placed such that the stockpiled soil does not come into contact with surface water run-off. The 10 mil geomembrane cover shall prevent rain or surface water from coming into contact with the contaminated soil, as well as limit the escape of the volatile constituents in the stockpile.

Kato, 02-1 BCA at 156,493. In addition, the contract included a full paragraph devoted entirely to the subject of contaminated soil, entitled “Contaminated Soil”:

After the tank has been removed from the ground, the adjacent and underlying soil shall be examined for any evidence of leakage. The soil shall be visually inspected for staining and also screened for the presence of volatile and semi-volatile hydrocarbon contamination using a real time vapor monitoring instrument. Contaminated soil shall be stockpiled onsite per Paragraph Stockpiles. The State of Washington inspector shall determine the extent of the contaminated soil to be removed from each site but shall not exceed 20 cubic yards per site. Any evidence that contamination exceeds that indicated in the contract shall be reported to the Contracting Officer or authorized representative on the same day it is discovered. After the known contaminated soil is removed, the excavation shall be sampled and analyzed per Paragraph SOIL EXAMINATION, TESTING, AND ANALYSIS.

Id. There were various other provisions in the contract, too numerous and lengthy to quote in their entirety, addressing measures to be taken in the event contaminated soil was encountered.

The contract clause relating to payment for removal of the storage tank provided that payment, “shall be under the base bid for the tank removal and shall constitute full payment for all work defined in the contract documents including testing of the contents, excavation and disposal of the tank, and testing of the underlying soil.” Id.

[326]*326Kato began excavation of the storage tank on March 11,1996. After the excavation was complete, Kato discovered that soil underlying the tank was contaminated with petroleum residue. On March 14, 1996, Kato informed the Air Force that it had discovered contaminated soil and provided test results regarding the level of contamination in the soil. A dispute arose as to whether Kato was required to excavate and stockpile the contaminated soil within the original contract price. On July 31, 1996, the Air Force directed Kato to excavate and stockpile 20 cubic yards of contaminated soil and to replace it with clean fill dirt. Kato performed this work. Id. at 156,494.

On January 7, 1998, Kato submitted to the Air Force a claim for $7,594.07 in compensation for “stockpiling contaminated soil and related activities.” (J.A. at 47.) Kato claimed this compensation under the contract’s differing site conditions clause.

The contract incorporated by reference section 52.236-2 of the Federal Acquisition Regulations, entitled “Differing Site Conditions.” That section provides, in part:

(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract
í{í íjí $ # ^ ifc
(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

48 C.F.R. § 52-236-2 (2002).

Kato claimed that “[t]he Contract documents clearly indicated that no contaminated soil was anticipated to be encountered ... the fact that the Contract documents provided a method for handling unexpected contaminated soil does not explicitly or implicitly resolve the question of who is to pay for handling the contaminated soil.” (J.A. at 52-53.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
60 F. App'x 324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kato-corp-v-roche-cafc-2003.