Kat Construction Management, LLC v. Safeco Insurance Company of America

CourtDistrict Court, D. Colorado
DecidedJanuary 14, 2022
Docket1:19-cv-02981
StatusUnknown

This text of Kat Construction Management, LLC v. Safeco Insurance Company of America (Kat Construction Management, LLC v. Safeco Insurance Company of America) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kat Construction Management, LLC v. Safeco Insurance Company of America, (D. Colo. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLORADO Judge Raymond P. Moore

Civil Action No. 19-cv-02981-RM-KLM

KAT CONSTRUCTION MANAGEMENT LLC, a Colorado limited liability company,

Plaintiff, v.

SAFECO INSURANCE COMPANY OF AMERICA, a New Hampshire corporation

Defendant. _______________________________________________________________________________ ORDER _______________________________________________________________________________ This is a property insurance dispute arising from hail damage to the home and property of Huntington Brown, who held an insurance policy (the “Policy”) with the Defendant, Safeco Insurance Company of America (the “Defendant” or “Safeco”). Brown hired the Plaintiff, KAT Construction Management, LLC (the “Plaintiff” or “KAT”) to make repairs to his home, including to his roof and to other structures on his property. Brown later assigned any remaining claims under the Policy to KAT, and KAT filed this action. At issue is Safeco’s Motion for Summary Judgment (ECF No. 34). KAT filed a response (ECF No. 43) and Safeco filed a Reply (ECF No. 45). The Motion is now ripe for resolution. Upon review of the Motion and responses, relevant parts of the court record, and the applicable statutes and case law, and being otherwise fully advised, the Court finds and orders as follows. I. BACKGROUND Safeco insured Brown’s property at the time the property suffered damage from a hailstorm in 2017. (ECF No. 35-10.) Pursuant to the Policy, Safeco would pay for covered losses at replacement cost, specifically, as pertinent here: (1) We will pay the full cost of repair or replacement, but not exceeding the smallest of the following amounts: (a) the limit of liability under the policy . . . ;

(b) the replacement cost of that part of the damaged building for equivalent construction and use on the same premises as determined shortly following the loss;

(c) the full amount actually and necessarily incurred to repair or replace the damaged building as determined shortly following the loss; [or]

(d) the direct financial loss you incur . . . .

(ECF No. 35-10, p.40, emphasis original.) Following the storm, Brown entered into a Work Management Contract with KAT and subsequently filed a claim under the Policy. (ECF No. 35-7.) Within three days of that claim, Safeco assigned Brian Sewald to adjust the claim and he inspected Brown’s property. Five days later, on November 21, 2017, Sewald sent Brown an estimate for covered repairs and replacements to his property. Sewald concluded that the total actual cash value, after accounting for Brown’s $2,500.00 deductible, would be $16,060.93 and that Brown could collect an additional $12,057.27 of recoverable depreciation after repairs were completed, for a total of $28,118.20. (ECF Nos. 35- 7, 35-9.) Safeco sent Brown a check for the initial $16,060.93 the same day. (ECF No. 35-12.) Apparently Brown and/or KAT decided that because of the impending winter weather, it would be sensible to wait until the Spring to begin repairs to Brown’s roof. (ECF No. 44-8). Therefore, the next recorded communication between the parties did not take place until April of 2018, when KAT emailed Sewald to let him know that KAT had discovered some “differences” between its estimate and Safeco’s estimate and setting them out for Sewald’s consideration. (ECF No. 44-11.) Among the concerns raised were that the Safeco estimate purportedly did not include money to (1) repair a damaged sculpture in Brown’s backyard; (2) assemble three replacement Rubbermaid sheds; (3) replace an Adirondack chair (it included replacement of one chair, but two were damaged); (4) replace two skylights that KAT had concluded could not be repaired; (5) sand windows prior to repainting; (6) replace two metal sheds; (7) repair plumbing as required to comply with the building code; (8) install ventilation for the attic/roof to comply with the building code; (9) purchase new roofing material; (10) upgrade guttering to meet the building code requirements; (11) repair damaged paint on patio posts; (12) pay for temporary repairs already made to the roof; (13) remove skylights and install new trim work; and (14) document the ongoing repairs. Sewald responded that Safeco would not be amending its estimates but informed KAT that it could submit any code upgrades that would be required by the city and Safeco would

review them. In mid-May, KAT emailed the code information, as well as invoices for completed work, and requested payment. (ECF No. 44-3.) At the end of May, Safeco informed KAT that Sewald was no longer handling the claim and in mid-June further informed KAT that Safeco had reassigned the claim to Alan Naas. (ECF Nos. 44-5, 44-6.) KAT emailed Naas on June 21, 2018 to inquire about the state of the claim and Naas responded the following morning, Friday, June 22, 2018, to let KAT know that he would review all the materials and get back to them by the close of business the following Monday. (ECF No. 44-7.) KAT sent its total estimate for the work to Safeco, reflecting a total for all of the work of $86,520.14. (ECF Nos. 35-2, 44-1.) On July 2, 2018, Naas sent Brown a revised calculation of the benefits it would pay on his

claim. (ECF No. 35-17.) Based on the additional information provided by KAT, Naas now calculated a claim total of $65,082.54. Safeco made the payment of $12,057.27 for recovered depreciation and then a final additional payment of $34,464.34. (ECF No. 35-12.) Safeco sent the final payment to Brown’s mortgage company which, in turn, released that payment to Brown and KAT upon receipt of certain documentation. (ECF No. 35-21.) Included in that documentation was an Addendum to Work Agreement between Brown and KAT, dated July 20, 2018. It set out the “Total Contract Price” as $65,082.54 and was signed by both parties. Also included was an invoice reflecting prior payments of $28,118.20 plus $2,500.00 for the deductible, and a total due of $34,464.34. And it included a Contractor’s Waiver of Lien, which stated that, conditional upon payment of the total $65,082.54, “all claim(s) of lien for labor and/or materials will be waived.” (ECF Nos. 35-21, 46-3.) KAT and Naas exchanged several additional emails regarding the estimate, KAT arguing for the higher total and Naas informing KAT that Safeco would not be increasing payments for overhead and profit beyond that already included in the estimate. (ECF No. 44-13.) Naas then

emailed Brown to inform him that Safeco and KAT had “been unable to reach an agreed cost” and noting that “[t]here is a policy provision for an Appraisal process,” and suggesting that an appraisal would be the next step in attempting to reach such an agreement. (ECF No. 35-19.) Apparently, Brown never requested an appraisal. Instead, over a year later, Brown signed an “Assignment of Remaining Insurance Claims,” giving KAT the right to pursue any benefits related to this claim that might remain under Brown’s insurance Policy. (ECF No. 44-2.) In return, KAT again agreed that it would not file any lien or assert any claim against Brown or his home. KAT submitted an affidavit with its Response to the Motion for Summary Judgment in which it asserted that “[t]he purpose of executing the Assignment was to ensure that instead of invoicing the homeowner/policy holder, [Brown], for additional amounts owed for the work on his

residence . . . [KAT] would seek reimbursement for the remaining amount owed directly from [Safeco].” (ECF No. 44-14.) A few days after executing the Assignment, KAT filed this suit. (ECF No. 1.) It asserts claims for breach of contract and for unreasonable delay or denial of insurance benefits pursuant to sections 10-3-1115 and -1116 of the Colorado Revised Statutes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Stone v. Autoliv ASP, Inc.
210 F.3d 1132 (Tenth Circuit, 2000)
United States v. Dawes (In Re Dawes)
652 F.3d 1236 (Tenth Circuit, 2011)
McCormick v. DIAMOND SHAMROCK CORPORATION
487 P.2d 1333 (Supreme Court of Colorado, 1971)
Empire Cas. v. ST. PAUL FIRE AND MARINE
764 P.2d 1191 (Supreme Court of Colorado, 1988)
Western Distributing Co. v. Diodosio
841 P.2d 1053 (Supreme Court of Colorado, 1992)
Tivoli Ventures, Inc. v. Bumann
870 P.2d 1244 (Supreme Court of Colorado, 1994)
Union Insurance Co. v. Houtz
883 P.2d 1057 (Supreme Court of Colorado, 1994)
Regency Realty Investors, LLC v. Cleary Fire Protection, Inc.
260 P.3d 1 (Colorado Court of Appeals, 2010)
Bankruptcy Estate of Morris Ex Rel. Goodwin v. COPIC Insurance Co.
192 P.3d 519 (Colorado Court of Appeals, 2008)
Cyprus Amax Minerals Co. v. Lexington Insurance Co.
74 P.3d 294 (Supreme Court of Colorado, 2003)
Williams v. Owners Insurance Company
621 F. App'x 914 (Tenth Circuit, 2015)
Allstate Insurance Co. v. Medical Lien Management, Inc.
2015 CO 32 (Supreme Court of Colorado, 2015)
Gutteridge v. State of Oklahoma
878 F.3d 1233 (Tenth Circuit, 2018)
v. GEICO Casualty Company
2018 CO 87 (Supreme Court of Colorado, 2018)
Soicher v. State Farm Mutual Automobile Insurance Co.
2015 COA 46 (Colorado Court of Appeals, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Kat Construction Management, LLC v. Safeco Insurance Company of America, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kat-construction-management-llc-v-safeco-insurance-company-of-america-cod-2022.