Kasbo Construction Co. v. Minto School District

184 N.W. 1029, 48 N.D. 423, 1921 N.D. LEXIS 60
CourtNorth Dakota Supreme Court
DecidedOctober 20, 1921
StatusPublished
Cited by1 cases

This text of 184 N.W. 1029 (Kasbo Construction Co. v. Minto School District) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kasbo Construction Co. v. Minto School District, 184 N.W. 1029, 48 N.D. 423, 1921 N.D. LEXIS 60 (N.D. 1921).

Opinion

Grace, C. J.

This is an action to recover $3,486.40, the balance of the contract price about $9,241.40, and $877.68 for alleged extra work, [426]*426labor, and material for the construction of a certain schoolhouse for defendant. The defendant paid about $7,000 of the contract price.

The defendant admits that plaintiff erected and constructed such building, but denies that it was constructed and finished according to the plans and specifications, and by appropriate pleading sets up 'two separate counterclaims aggregating $9,000. The issues were submitted to a jury and' resulted in a verdict in favor of defendant for a dismissal of the action. Plaintiff made a motion for a new trial which was denied, and from the order denying new trial plaintiff appeals and assigns 7 errors based upon alleged erroneous instructions by the court and 28 specifications of the insufficiency of the evidence to sustain the verdict.

The material facts necessary to be stated are as follows: The defendants published notices for bids for the construction of a schoolhouse, according to plans and specifications, to be erected in Minto township in Cavalier county. On about April 1, 1918, at a meeting of the school board, it let the contract for the construction of the building to the plaintiff. At that time the terms of the contract were discussed between the parties and a written contract, Exhibit C, was entered into and; signed by both parties. It is of too great length to be set out in full and it is needless to do so.

Exhibits D and E, specifications and plans, are part of the contract. There is another alleged contract, Exhibit A, which plaintiff contends i? the contract under which the work was performed. It claims that though this contract is unilateral, having been signed by the plaintiff only, nevertheless it was sent to the defendant and retained by it. Plaintiff claims that the defendant agreed that the work should be done under the- latter contract. There is positive testimony, however, that Exhibit C was the contract agreed upon and signed by both parties. After its completion, Kasbo took it with him for the purpose of making copies of it and was to return it. At the trial plaintiff attempted to introduce Exhibit A in evidence. It was excluded, and properly so, as it never was accepted nor approved by the school board. It was a contract materially different from Exhibit C. Furthermore, the following stipulation was made in open court between the plaintiff and defendant which was dictated by Mr. Devaney, one of plaintiff’s attorneys:

.“It is stipulated by and between the plaintiff and defendant that Exhibit C is the original contract entered into by and between plaintiff and defendant on or about April 1, 1918, excepting therefrom the por[427]*427tions which are stricken out with a red pencil and including those portions contained in brackets and green ink which the plaintiff made in the contract after the contract was reduced to writing, and signed therein approved and consented to by the defendants. It is further stipulated that Exhibit F is a true copy of said original agreement and may be used upon the trial of this case for any purpose for which the original may be used. It is further stipulated that Exhibit D is the specifications referred to in said contract, and it should be admitted in evidence as such and as the specifications according to which the schoolhouse was to be built, and that Exhibit E may be admitted in ■evidence as the original plans of the schoolhouse to -be built by the plaintiff under this contract and according to which plans it was to be built.”

Certainly and especially in view of the above stipulation, there was no error in excluding Exhibit A. Exhibit C, as it originally existed before the changes inserted into it by Kasbo and which is represented by Exhibit F, is the contract and the only contract between the parties, and the trial was had on that theory, and the plaintiff cannot now change its position. The 28 assignments of error relative to the insufficiency of the evidence to sustain the verdict need no lengthy discussion. If there is competent evidence in the record which will support the verdict, then all errors based upon the insufficiency of the evidence must be considered of no merit. An examination of the evidence not only discloses that there is some competent evidence, to support the verdict, but that there is an abundance of it. It is entirely unnecessary to set it forth in detail. It is sufficient to state that there is an abundance of evidence to show that the foundation of the building was improperly and poorly constructed; that the cement and gravel used therein were not in proper proportion nor in compliance with the specifications, and as a result, according to the testimony of Mr. Shannon, an architect of 25 years’ experience, who examined the building, the foundation, and basement walls, it appears that the walls were soft; that they were very irregular and not straight . and out of plumb in places; that the concrete was soft. He found a crack in the northeast corner and one in the southwest corner, stating that these were ruptures in the wall. In explaining what he meant by the walls being soft, he stated, in substance, that they are not of the density that concrete usually is; that it would rub off by hand, or pieces could be taken out of it. He stated that the walls were not safe nor durable and that as an architect he would not allow such a wall, but [428]*428would condemn it, have it taken out and another put in. He stated further that the rafters, ceiling, and joists had sagged; that they were not properly braced; that the floor had sagged some; that the frame at the plate line was very roughly thrown together and not put in according to plans and as a result seems to let the building spread; that the cornices were open and let the daylight in; that some of the wainscoting was out of plumb; that the outside walls were not in plumb.

There is much' more evidence by the same witness largely to the same effect. He further testified as follows:

Q. What difference in money in your opinion would there be between the building as it stands now, as erected by Mr. Kasbo, and the building as it should have been erected under that contract? A. $4,500.

He testified further to the effect that the building could not be repaired and put in condition as required by the specifications for $4,500; that there was no way that the'wall could be repaired and made to stand up according to the plans and specifications; that it would have to be wrecked and rebuilt; and that in his opinion it would cost, to take out and rebuild a foundation for a new building, about $3,000. In substance his testimony shows that to make the building, aside from the foundation or basement walls, comply with the plans and specifications, it would have to be wrecked and rebuilt, and that this could not be done for $4,500.

The evidence of Shannon is substantiated by that of other competent witnesses. The evidence is abundant to sustain the verdict of the jury. If the verdict of the jury had been for a much larger amount, there is abundant evidence in the record to have sustained it.

The several assignments of error predicted upon alleged erroneous instructions have been carefully analyzed and are of no real substance, and are largely without merit. The parts of the instructions from which excerpts are taken are entirely too lengthy to be here set out and none of them merit discussion. It will, however, do no harm to briefly discuss the only one of importance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fargo Glass & Paint Co. v. Smith
266 N.W. 100 (North Dakota Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
184 N.W. 1029, 48 N.D. 423, 1921 N.D. LEXIS 60, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kasbo-construction-co-v-minto-school-district-nd-1921.