Karen Mayo v. MODS International, Inc.

CourtCourt of Appeals of Wisconsin
DecidedApril 21, 2020
Docket2019AP000621
StatusUnpublished

This text of Karen Mayo v. MODS International, Inc. (Karen Mayo v. MODS International, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Karen Mayo v. MODS International, Inc., (Wis. Ct. App. 2020).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. April 21, 2020 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2019AP621 Cir. Ct. No. 2018SC3760

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT III

KAREN MAYO,

PLAINTIFF-RESPONDENT,

V.

MODS INTERNATIONAL, INC.,

DEFENDANT-APPELLANT.

APPEAL from a judgment of the circuit court for Outagamie County: JOHN A. DES JARDINS, Judge. Affirmed.

¶1 STARK, P.J.1 MODS International, Inc., appeals a small claims judgment awarding Karen Mayo $10,000, plus costs. MODS argues the circuit court erred by determining that MODS was not entitled to an equitable adjustment

1 This appeal is decided by one judge pursuant to WIS. STAT. § 752.31(2) (2017-18). All references to the Wisconsin Statutes are to the 2017-18 version unless otherwise noted. No. 2019AP621

of the time in which to complete its obligations under the parties’ contract. MODS also argues that Mayo did not terminate the contract for cause, and MODS is therefore entitled to costs incurred as a result of the termination, along with overhead and profit on work not executed. We reject MODS’ arguments and affirm.

BACKGROUND

¶2 MODS is located in Appleton, Wisconsin. It designs and builds modular structures using storage containers. Mayo entered into two contracts with MODS to build and install an Auxiliary Dwelling Unit (ADU)—i.e., a tiny house—consisting of two storage containers in the backyard of Mayo’s residence in Los Angeles, California.

¶3 Mayo signed the first contract—hereinafter, the design contract—on December 15, 2017. Under the design contract, which was labeled “Document No: OAB105,” Mayo retained MODS as an architect to design and engineer the ADU. Mayo agreed to pay MODS $4000 for its design services. The design contract provided that payment would be “deducted from the total agreed[-]to project cost, once a construction contract is signed by both parties.”

¶4 Mayo signed the second contract—hereinafter, the construction contract—on December 21, 2017. Under the construction contract, which was labeled “Document No. OCSP105,” Mayo retained MODS to act as a contractor to build the ADU and to install it on her property. The construction contract required MODS to install foundation piers for the ADU during the first week of January 2018 and to deliver and install the ADU on or before January 30, 2018. In addition, § 11.1 of the construction contract provided: “Time limits stated in the Contract Documents are of the essence of the Contract.” The “Total Price” set

2 No. 2019AP621

forth in the construction contract was $39,300. Mayo paid MODS $15,650 upon signing the construction contract, in addition to the $4000 she had already paid under the design contract.

¶5 MODS failed to install the piers for the ADU during the first week of January 2018 and failed to deliver and install the ADU on or before January 30, 2018. In fact, MODS had not yet completed those tasks as of August 2018. Consequently, on August 20, 2018, Mayo sent an email to MODS stating that effective August 24, she was “exercising [her] cancellation rights under Document OAB105 (MODS agreement dated December 13, 2017) Article 4” due to MODS’ “inability to complete the contract milestones and deliver the product as indicated in the attache [sic] agreement.” As a result of the termination, Mayo asked MODS to refund her $15,000 of the $19,650 she had already paid.

¶6 MODS refused to refund any money to Mayo. In November 2018, Mayo filed the instant small claims lawsuit against MODS in Outagamie County, seeking to recover the small claims judgment limit of $10,000. The matter was initially heard by a court commissioner, who found in favor of Mayo and awarded her $10,000, plus costs.

¶7 MODS then demanded a trial de novo before the circuit court. At the trial de novo, the evidence showed that MODS’ delay in installing the ADU was due at least in part to difficulties in obtaining a building permit. In particular, a MODS employee testified that he had worked “all over the United States,” and the process for obtaining a building permit for Mayo’s project in Los Angeles County was “one of the most difficult [he had] ever dealt with.” The employee further testified that he never stopped attempting to obtain a building permit for the project. The parties disputed, however, whether Mayo or MODS was

3 No. 2019AP621

ultimately responsible for obtaining the permit. MODS also argued at trial that the delay in completing Mayo’s project was partially caused by changes to the design. As such, MODS asserted the delay was caused by forces outside its control, and MODS was therefore entitled to an equitable adjustment of the deadline to complete the work under § 11.2 of the construction contract.

¶8 MODS also asserted at trial that Mayo’s email dated August 20, 2018, terminated only the design contract, which had already been completed as of that time, rather than the construction contract. Moreover, MODS contended that any termination of the construction contract was a termination for Mayo’s convenience under § 16.3 of that contract, rather than a termination for cause under § 16.2. MODS therefore argued that under § 16.3 of the construction contract, it was entitled to payment for “all the work executed and costs incurred by reason of [Mayo’s] termination, along with reasonable overhead and profit on the work not executed.”2

¶9 After considering the evidence presented at trial, the circuit court issued an oral ruling in favor of Mayo. The court concluded that under the construction contract, it was “clearly” MODS’ responsibility to obtain the necessary building permit. The court also found that: (1) when entering into the construction contract, Mayo relied on MODS’ representations that it was familiar with California law and had completed projects in California; (2) MODS did not exercise due diligence in investigating Mayo’s property to determine any

2 There is nothing in the record indicating that MODS filed a counterclaim against Mayo seeking to recover damages under § 16.3 of the construction contract. On appeal, MODS does not argue that the circuit court should have awarded it damages in a specific amount under § 16.3. Instead, it appears MODS’ position is that § 16.3 provided a basis for it to retain the money Mayo had already paid.

4 No. 2019AP621

difficulties that might exist; (3) the contract required the foundation piers for the ADU to be completed in the first week of January 2018 and the project to be completed by February 2018; (4) MODS failed to meet those deadlines; and (5) the delay was MODS’ fault and was within MODS’ control because MODS had represented to Mayo that it was familiar with California law, but it ultimately did not understand “the particulars of [obtaining a building permit] in L.A. County.”

¶10 Based on its findings, the circuit court concluded MODS was not entitled to an equitable adjustment of the time to complete its work under § 11.2 of the construction contract. The court also concluded that MODS had substantially breached the construction contract by failing to comply with the contractual time limits. Accordingly, the court concluded Mayo had terminated the construction contract for cause under § 16.2, rather than for her own convenience under § 16.3. It therefore awarded Mayo the $10,000 she sought, plus costs. MODS now appeals.

DISCUSSION

¶11 As an initial matter, we observe that Mayo did not timely file a response brief in this appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Pettit
492 N.W.2d 633 (Court of Appeals of Wisconsin, 1992)
Phelps v. Physicians Insurance
2009 WI 74 (Wisconsin Supreme Court, 2009)
Tang v. C.A.R.S. Protection Plus, Inc.
2007 WI App 134 (Court of Appeals of Wisconsin, 2007)
United Rentals, Inc. v. City of Madison
2007 WI App 131 (Court of Appeals of Wisconsin, 2007)
Waushara County v. Graf
480 N.W.2d 16 (Wisconsin Supreme Court, 1992)
Jezeski v. Jezeski
2009 WI App 8 (Court of Appeals of Wisconsin, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Karen Mayo v. MODS International, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/karen-mayo-v-mods-international-inc-wisctapp-2020.