Karaha Bodas Co LLC v. Perusahaan Pertamban

Court of Appeals for the Fifth Circuit·Decided May 9, 2003·No. 02-20042·Unpublished

Opinion

United States Court of Appeals Fifth Circuit

IN THE UNITED STATES COURT OF APPEALS F I L E D March 5, 2003

FOR THE FIFTH CIRCUIT

____________________ Charles R. Fulbruge III Clerk

No. 02-20042

KARAHA BODAS COMPANY, L.L.C., Plaintiff-Appellee,

versus

PERUSAHAAN PERAMBANGAN MINYAK DAN GAS BUMI NEGARA, ET AL., Defendants,

PERUSAHAAN PERAMBANGAN MINYAK DAN GAS BUMI NEGARA, Defendant-Appellant.

Appeal from the United States District Court for the Southern District of Texas (H-01-CV-634)

Before KING, Chief Judge, DAVIS, Circuit Judge, and ROSENTHAL*, District Judge.

PER CURIAM:** Appellant, Perusahaan Perambangan Minyak Dan Gas Bumi Negara (“Pertamina”) contracted with appellee, Karaha Bodas Company,

*

District Judge of the Southern District of Texas, sitting by designation.

**

Pursuant to 5TH CIR. R. 47.5, the Court has determined that this opinion should be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4.

L.L.C. (“KBC”) to develop geothermal energy sources in Indonesia for electrical power generation. The parties executed two contracts. Both contained an arbitration clause. In 1998, financial crises in Indonesia led to the suspension of the project. KBC initiated arbitration proceedings, which were conducted in Switzerland. The Tribunal entered an award in favor of KBC for damages resulting from the cancellation of the project. KBC then filed suit in the federal district court in the Southern District of Texas to confirm that award. This appeal is from the district court’s grant of summary judgment confirming the award and rejecting Pertamina’s challenges to the arbitration procedures and result.

Months after briefing on this appeal concluded, Pertamina filed in the district court a motion to set aside judgment under Rule 60(b)(2), based on newly discovered evidence that Pertamina contended should have been disclosed during the arbitration, and under Rule 60(b)(5), based on the decision of an Indonesian court annulling the arbitration award. A few weeks later, Pertamina filed in this court a motion to supplement the record and for supplemental briefing, seeking to have this court include in the appellate record both the recently discovered evidence and the information as to the post-judgment decision of the Indonesian court annulling the award. The developments in the Indonesian court are the subject of a separate appeal now pending before a

different panel of this court; Pertamina urges this court to supplement the record on this appeal with the record of the separate pending appeal.

Pertamina urges this court to supplement the record and consider the additional evidence without the benefit of the district court’s ruling on the Rule 60 motion pending in that court. KBC urges this court simply to deny the motion to supplement the record and for supplemental briefing. The threshold questions presented in this case are how this court should address the request to supplement the record to add materials that the district court did not consider, and how the district court should treat the Rule 60(b) motion to vacate its judgment when the appeal from the judgment is pending. Because the motion to supplement raises the same questions that are before the district court in the Rule 60(b) motion, the district court should consider those questions first. The Rule 60(b) motion is still pending in the district court, and that court has not yet indicated whether it intends to grant or deny the motion. Accordingly, the appeal from the grant of summary judgment will be held in abeyance to permit a limited remand for the district court to consider the merits of the Rule 60(b) motion.

I. Background

Petitioner-appellee KBC explores and develops geothermal energy sources and builds electric generating stations using

geothermal sources. Respondent-appellant Pertamina is an oil, gas, and geothermal energy company owned by the Government of Indonesia.*** KBC signed two contracts to produce electricity from geothermal sources in Indonesia in November 1994. The Joint Operation Contact granted KBC the right to develop geothermal energy sources in the Karaha area of Indonesia; Pertamina was to manage the project and receive the electricity generated. (Final Award, ¶ 4). Under the Energy Sales Contract, PLN agreed to purchase from Pertamina the energy generated by KBC’s facilities. (Id. at ¶ 5). Both contracts contained arbitration clauses, calling for the application of the Arbitral Rules of the United Nations Commission on International Trade Law (“UNCITRAL”) and specifying Geneva, Switzerland as the place of any arbitration. On September 20, 1997, the Indonesian government suspended the project because of the government’s financial crisis. The project was indefinitely suspended on January 10, 1998. On February 10, 1998, KBC notified Pertamina and PLN that the government’s suspension constituted an event of force majeure under the contracts.

KBC initiated arbitration proceedings on April 30, 1998.

Pertamina disputes the procedures used in the appointment of the arbitrators and the consolidation of the arbitrations under the two contracts. In its Preliminary Award, the Tribunal held that the

***

PLN, an electric utility owned by the Government of Indonesia, was a party to the arbitration but was dismissed from the district court action.

Tribunal was properly constituted, that consolidation was proper, and that the Government of Indonesia was not a proper party. KBC filed its Revised Statement of Claim on November 24, 1999. Pertamina received a number of extensions before it filed its reply brief on April 7, 2000, and KBC filed its rebuttal on May 8, 2000. In response to the rebuttal, Pertamina sought additional discovery and a continuance of the proceedings, scheduled to begin on June 19, 2000, claiming that KBC had raised new assertions and new elements of its case-in-chief not contained in the Revised Statement of Claims. The parties had vigorously disputed whether KBC could have obtained financing to build the project if the government had not issued the suspension decree. Pertamina asserted that KBC’s rebuttal introduced a new theory as to how it would have obtained financing, claiming that one of KBC’s direct investors, FPL Energy (“FPL”), would have provided project financing if no other source was available. Pertamina sought discovery of FPL documents relating to the claim that FPL was prepared to finance the KBC project. The Tribunal denied Pertamina’s requests for this discovery and for a continuance. The hearing on the merits was held in June 2000. The Tribunal stated in the final award that all parties had “waived their respective requests for discovery” at the conclusion of the hearing. (Final Award, ¶ 32). Pertamina disputes any waiver.

In the Final Award, issued in December 2000, the Tribunal found that Pertamina was liable for nonperformance of the contracts. The Tribunal interpreted the contractual provisions as “putting the consequences of a Governmental decision which prevents the performance of the contract at Pertamina’s . . . sole risk.” (Final Award, ¶ 57). The Tribunal awarded KBC $111.1 million to recoup its expenditures and $150 million in lost profits.

Free access — add to your briefcase to read the full text and ask questions with AI

Karaha Bodas Co LLC v. Perusahaan Pertamban, (5th Cir. 2003).

Karaha Bodas Co LLC v. Perusahaan Pertamban (Karaha Bodas Co LLC v. Perusahaan Pertamban) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Travelers Insurance v. Liljeberg Enterprises, Inc.
38 F.3d 1404 (Fifth Circuit, 1994)
Standard Oil Co. of Cal. v. United States
429 U.S. 17 (Supreme Court, 1976)
Maher v. Hyde
272 F.3d 83 (First Circuit, 2001)
Smith v. Pollin
194 F.2d 349 (D.C. Circuit, 1952)
Roy Ferrell v. Trailmobile, Inc.
223 F.2d 697 (Fifth Circuit, 1955)
United States v. Clayton R. Page, III
661 F.2d 1080 (Fifth Circuit, 1981)
Howard L. Dickerson v. State of Alabama
667 F.2d 1364 (Eleventh Circuit, 1982)
Freddie D. Gibson, Jr. v. Frank Blackburn, Warden
744 F.2d 403 (Fifth Circuit, 1984)
Willie X. Ross v. Ralph Kemp
785 F.2d 1467 (Eleventh Circuit, 1986)
United States v. Earl Hillsberg
812 F.2d 328 (Seventh Circuit, 1987)
United States v. Gene Allen Flores
887 F.2d 543 (Fifth Circuit, 1989)
Dakota Industries, Inc. v. Dakota Sportswear, Inc.
988 F.2d 61 (Eighth Circuit, 1993)
United States v. Marvin P. Jones
29 F.3d 1549 (Eleventh Circuit, 1994)