Kaplan v. Hammond

2024 Ohio 2492, 246 N.E.3d 1072
CourtOhio Court of Appeals
DecidedJune 28, 2024
DocketOT-23-003
StatusPublished
Cited by1 cases

This text of 2024 Ohio 2492 (Kaplan v. Hammond) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kaplan v. Hammond, 2024 Ohio 2492, 246 N.E.3d 1072 (Ohio Ct. App. 2024).

Opinion

[Cite as Kaplan v. Hammond, 2024-Ohio-2492.]

IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT OTTAWA COUNTY

Gabriela Kaplan Court of Appeals No. OT-23-003

Appellant Trial Court No. 18 CVH 180

v.

Ricky Hammond, et al. DECISION AND JUDGMENT

Defendants Decided: June 28, 2024

[John A. Feick and Feick Design Group, LLC – Appellees]

*****

Bryan S. Choka, for appellant.

Justin D. Harris and Hannah R. Duschl, for appellees.

ZMUDA, J.

I. Introduction

{¶ 1} Appellant, Gabriela Kaplan, appeals the February 3, 2021, judgment of the

Ottawa County Court of Common Pleas granting summary judgment in favor of

appellees John A. Feick and Feick Design Group, LLC.1 For the following reasons, we

1 Because the claims against them, and our resolution of this appeal does not require distinction between appellees, we refer to appellees collectively as “Feick” or “he” for ease of reading. reverse the trial court’s judgment and remand this matter to the trial court for further

proceedings.

II. Facts and Procedural Background

{¶ 2} The factual background underlying this appeal, based on the parties’ motions

and affidavits, is largely undisputed. Kaplan has owned a residence in Put-in-Bay,

Ottawa County, Ohio, since 1991. Put-in-Bay is located on an island and required all

parties to take ferries to access the residence. During the time Kaplan has owned the

property, she has had multiple instances of water intrusion into the residence, resulting in

damages to the residence and her personal property. The facts relevant to the water

intrusion giving rise to the present case began in 2012 when Kaplan entered into an

agreement with North Coast Roofing, LLC, for the replacement of her roof. That work

was performed in 2012.

{¶ 3} Three years later, Kaplan again discovered water intrusion into her

residence. Believing that the issue related to a first-floor window, Kaplan contacted

Hammond Construction, LLC (“Hammond”), to determine what work would be

necessary to repair any damages and to replace the window. To determine the scope of

work necessary, Hammond removed the exterior coverings from the residence and

discovered that the water damage extended beyond the window it was inspecting.

Hammond instead found that the window directly above the one it had been asked to

inspect had also suffered from water intrusion and that the wood underneath the

protective exterior coverings around both windows was damaged and needed to be

2. replaced. Hammond recommended to Kaplan that all of the rotting wood underneath the

coverings be replaced along with all windows, exterior doors, and the siding. Kaplan

agreed and the parties entered into a contract for the suggested repairs on October 9,

2015.

{¶ 4} Having had multiple issues with water intrusion into the residence in the

past, Kaplan sought an architect to perform four periodic inspections of Hammond’s

work as it progressed to ensure that no further water intrusion would occur. Kaplan

ultimately entered into an agreement with Feick on November 13, 2015, to perform this

oversight function. The agreement provided that Feick would provide Kaplan with

sealed drawings for the door and window installations, conduct the requested inspections

of Hammond’s work, and to advise on any issues uncovered during the inspections. The

scope of the inspections to be performed were outlined in the agreement and included the

following:

1. Feick to meet [Hammond] the first day of demolition to review the

installation procedures.

2. Feick to inspect the completed installation of the first 2 windows.

3. Feick to inspect upon completion of all windows and doors, prior to any

siding being installed.

4. Feick to inspect after siding is completed.2

2 We note that the record contains two different copies of the written agreement. The first, included as an exhibit to Kaplan’s First Amended Complaint, contains these identical terms with additional terms hand-written into the agreement by Kaplan

3. The agreement obligated Kaplan to reimburse Feick a flat fee of $2,700 for the four

inspection trips in addition to paying a specified hourly rate for the work performed by

any Feick representative in furtherance of the agreement.

{¶ 5} In addition to the terms outlining the scope of work and the fees due, the

agreement also contained two terms related to the cessation of work/termination of the

agreement and the amount of damages that could be recovered from Feick arising from

any claims related to the agreement. The cessation/termination clause stated:

This agreement may be terminated by either party upon not less than thirty

days written notice should the other party fail substantially to perform in

accordance with the terms of this agreement through no fault of the party

initiating the termination. [Feick] reserves the right to cease all work

production at such time that accounts remain unpaid thirty days after the

invoice date. [Feick] shall be compensated for all services prior to

termination or work stoppage for reasons stated above plus reimbursable

expenses.

The limitation of liability clause stated:

regarding the scope of the inspections. The second copy, provided by Feick as an exhibit to his motion for summary judgment, does not include Kaplan’s hand-written revisions. Despite this, Feick does not dispute that the parties entered into the written agreement. As described below, the basis for Kaplan’s breach of contract claim is that Feick breached the agreement by failing to conduct the fourth inspection, regardless of its scope. As a result, we only review whether the trial court properly granted summary judgment in Feick’s favor on Kaplan’s breach of contract claim as to whether the inspection occurred and we make no judgment as to the proper scope of that inspection.

4. Neither [Feick], nor its officers, directors, partners, employees, agents or

consultants will be jointly, severally, individually or otherwise liable to the

client or anyone claiming by, through or under the client, in excess of the

compensation paid pursuant to this agreement, by reason of any act or

omission (including breach of contract or negligence) not amounting to a

willful or intentional wrong.

Neither party disputes the language of those basic terms or that those terms were included

in the parties’ November 13, 2015 written agreement.

{¶ 6} Hammond began its work on the residence on November 17, 2015. It is

undisputed that Feick performed the first two scheduled inspections on November 18,

2015, and November 20, 2015, respectively. The record also shows that Feick performed

an inspection of the completed window and door installation on December 24, 2015.

From that inspection, Feick developed a “punch list” of items that needed to be addressed

prior to the installation of the siding. Kaplan paid Feick $3,217.50 for the first three

inspections and his work performed during those inspections pursuant to the agreement.

{¶ 7} The parties agree that the fourth inspection was scheduled to occur on April

25, 2016. The parties also agree that the inspection did not occur. Kaplan contends that

the inspection was scheduled to occur in the afternoon. This, she argues, was to

accommodate Hammond completing installation of the siding and addressing the punch

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin v. Toledo Clinic, Inc.
2025 Ohio 2619 (Ohio Court of Appeals, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2024 Ohio 2492, 246 N.E.3d 1072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kaplan-v-hammond-ohioctapp-2024.