Kanza Construction, Inc. v. Kansas City Southern Railways Company

CourtCourt of Appeals of Mississippi
DecidedFebruary 22, 2021
Docket2019-CA-00904-COA
StatusPublished

This text of Kanza Construction, Inc. v. Kansas City Southern Railways Company (Kanza Construction, Inc. v. Kansas City Southern Railways Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kanza Construction, Inc. v. Kansas City Southern Railways Company, (Mich. Ct. App. 2021).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI

NO. 2019-CA-00904-COA

KANZA CONSTRUCTION, INC. APPELLANT

v.

KANSAS CITY SOUTHERN RAILWAYS APPELLEE COMPANY

DATE OF JUDGMENT: 05/01/2019 TRIAL JUDGES: HON. ISADORE W. PATRICK JR. HON. TONI DEMETRESSE TERRETT COURT FROM WHICH APPEALED: WARREN COUNTY CIRCUIT COURT ATTORNEY FOR APPELLANT: STEVEN CRAIG PANTER ATTORNEYS FOR APPELLEE: CHARLES EDWIN ROSS JAMES EARL GRAVES III LINDA FAYE COOPER NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: AFFIRMED - 02/22/2021 MOTION FOR REHEARING FILED: MANDATE ISSUED:

BEFORE WILSON, P.J., LAWRENCE AND McCARTY, JJ.

WILSON, P.J., FOR THE COURT:

¶1. Kansas City Southern Railway Company (KCS) contracted with Kanza Construction

Inc. to demolish and replace a bridge on Washington Street in Vicksburg. Kanza did not

complete the project on time, and the new bridge had numerous defects. KCS had to hire

another contractor to complete the bridge, and KCS refused to make payments to Kanza that

Kanza claimed were due under the parties’ contract. Kanza sued for breach of contract, and

KCS filed a counterclaim for breach of contract.

¶2. Prior to trial, the trial judge granted partial summary judgment in favor of KCS, ruling that KCS was entitled to judgment as a matter of law on Kanza’s claim for “acceleration

damages.” After a bench trial, the trial judge found that Kanza’s work was defective, that

KCS had to hire another contractor to finish the project, and that Kanza had materially

breached the parties’ contract. The trial judge entered a final judgment in favor of KCS and

awarded damages of $3,476,544.83. Kanza does not appeal or contest the findings or

damages awarded in the final judgment.1 Rather, Kanza argues that the trial judge erred by

granting KCS’s pretrial motion for partial summary judgment on Kanza’s claim for

“acceleration damages.”

¶3. We conclude that the trial judge’s finding that Kanza materially breached the parties’

contract—a finding that Kanza does not challenge on appeal—defeats Kanza’s claim for

acceleration damages. Therefore, even if the trial judge erred by granting partial summary

judgment prior to trial, the claim for acceleration damages fails based on the unchallenged

findings in the final judgment. Accordingly, any error in the pretrial ruling was harmless,

and we affirm in full the final judgment in favor of KCS.

FACTS AND PROCEDURAL HISTORY

¶4. The Washington Street Bridge in Vicksburg passes over two parallel railroad tracks

operated by KCS. In 2009, the City of Vicksburg closed the bridge due to safety concerns

and discussed repairs to the bridge with KCS. The City contracted with KCS to demolish the

old bridge, construct a new bridge, and build retaining walls around the tunnel under the

1 Kanza’s surety, Hanover Insurance Company, was a party in the trial court, and the final judgment held Kanza and Hanover jointly and severally liable for the judgment. Hanover paid the full amount of the judgment and is not a party on appeal.

2 bridge. KCS then accepted bids from contractors to perform the demolition and construction.

KCS accepted Kanza’s bid to perform the work for a lump sum of $6,796,000, which was

the amount that KCS received from the City for the project. KCS and Kanza then entered

into a contract, referred to as the Master Agreement (hereinafter, “the Agreement”), that

incorporated the City’s engineer’s design plans for the bridge and retaining walls. Kanza had

inspected the design plans and the property prior to submitting its bid.

¶5. Kanza was given notice to proceed on June 10, 2010. The Agreement required Kanza

to complete the project by June 10, 2011. Although the Agreement incorporated design plans

for the bridge and retaining walls, Kanza had discretion to make changes to the plans as long

as the changes were sound from an engineering standpoint and would not delay completion

of the project beyond its deadline. Kanza changed the design of the retaining walls, which

resulted in significant delays. Actual construction did not begin until April 2011, only three

months before the deadline. On May 20, 2011, Kanza requested an extension, and KCS and

the City agreed to extend the deadline to September 30, 2011. However, additional problems

arose, and the deadline was extended again to December 3, 2011.

¶6. On September 1, 2011, KCS’s senior vice president and chief engineer, John

Jacobsen, sent Kanza’s president, Steve Hutchinson, a letter regarding the delays and

extensions. Jacobsen insisted that Kanza add manpower and equipment in order to meet the

extended deadline of December 3. Jacobsen cited a provision of the Agreement that stated:

If in the opinion of [KCS], [Kanza] falls behind schedule at any time, [Kanza] will add additional manpower and equipment immediately and keep them on the job until the work is back on schedule without any additional cost to [KCS]. If overtime work is required to maintain the schedule, [Kanza] will

3 direct its work force to do so without any additional cost to [KCS].

¶7. Hutchinson responded by letter on September 7. He denied that Kanza was behind

schedule and asserted that Kanza was entitled to additional time for delays that were not

Kanza’s fault. Hutchinson argued that taking those delays into account, a new deadline of

March 13, 2012, would be appropriate. He stated that Kanza was willing to add manpower

and equipment and complete the project by December 2011, as requested by KCS. However,

he stated that this would be an “Acceleration of the Project” and that Kanza would be

“entitled to compensation for the acceleration effort.”

¶8. Hutchinson subsequently met with Jacobsen and KCS’s assistant general counsel,

David Reeves. The parties apparently agreed to a new completion schedule and a new

deadline of February 28, 2012. In an affidavit, Hutchinson claimed that after the meeting,

“Reeves took [him] aside and requested that Kanza proceed with the acceleration without a

prior change order.” Hutchinson claimed that Reeves said that an approved change order

would be provided at a later time. Hutchinson understood Reeves’s statements to mean that

“Kanza would be paid for its additional costs associated with the acceleration.” Hutchinson

stated that Kanza agreed to accelerate construction on that basis.

¶9. Kanza tendered the bridge to KCS by the February deadline, but KCS later identified

several defects in Kanza’s work. The defects required KCS to hire additional engineers to

evaluate the work and then hire a new contractor to repair and finish the project. Based on

the defects in Kanza’s work, KCS refused to pay Kanza the remainder of the lump sum

specified in the Agreement. KCS also refused to pay Kanza’s claimed “acceleration” costs.

4 ¶10. Kanza filed a complaint against KCS for breach of contract and damages, including

the remainder of the lump sum specified in the Agreement, KCS’s alleged acceleration costs,

and other alleged extra-contractual damages. KCS answered, denied that it had breached the

Agreement, and asserted a counterclaim for breach of contract. KCS sought damages for the

costs it had incurred to repair and complete the defective bridge and retaining walls.

¶11. KCS subsequently filed a motion for partial summary judgment addressing Kanza’s

claim for acceleration damages. KCS argued that Kanza was not entitled to acceleration

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brent v. Corbin
173 So. 2d 430 (Mississippi Supreme Court, 1965)
Eastline Corp. v. Marion Apartments, Ltd.
524 So. 2d 582 (Mississippi Supreme Court, 1988)
UHS-Qualicare, Inc. v. GULF COAST COM. HOSP., INC.
525 So. 2d 746 (Mississippi Supreme Court, 1987)
FAVRE PROP. MANAGEMENT, LLC v. Cinque Bambini
863 So. 2d 1037 (Court of Appeals of Mississippi, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Kanza Construction, Inc. v. Kansas City Southern Railways Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kanza-construction-inc-v-kansas-city-southern-railways-company-missctapp-2021.