Kansas Gas & Electric Co. v. City of McPherson

72 P.2d 985, 146 Kan. 614, 1937 Kan. LEXIS 32
CourtSupreme Court of Kansas
DecidedNovember 6, 1937
DocketNo. 33,477
StatusPublished
Cited by10 cases

This text of 72 P.2d 985 (Kansas Gas & Electric Co. v. City of McPherson) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas Gas & Electric Co. v. City of McPherson, 72 P.2d 985, 146 Kan. 614, 1937 Kan. LEXIS 32 (kan 1937).

Opinion

The opinion of the court was delivered by

Harvey, J.:

This action was brought to enjoin defendant from extending its electric transmission lines to the city of Moundridge and supplying electric energy to that city and vicinity. After a hearing on the merits the trial court enjoined the defendant from extending its transmission lines to and supplying electric energy to the city of Moundridge and vicinity “unless and until” defendant “shall obtain [615]*615a certificate of public convenience and necessity from the corporation commission of the state.” Defendant has appealed, contending it is not required by statute to obtain such a certificate. Plaintiff has cross-appealed, contending the injunction should have been granted without qualification.

The facts may be summarized briefly as follows: Plaintiff is incorporated under the laws of West Virginia and is authorized to do business in Kansas. Its business consists of producing, transmitting and selling electric energy. To conduct that business it has a large investment in this state. It had obtained from the state corporation commission a certificate of convenience and necessity so as to enable it to supply Moundridge and vicinity, and many other places, with electric energy. In January, 1922, it entered into a contract with the governing body of the city of Moundridge, which had its own electric distribution system, to supply electricity at the city gates to the city, for it to distribute oyer its distribution system, most of which was within the city. Provisions of the contract authorized plaintiff to supply electricity directly to consumers in the city using more than a stated quantity, and also to supply consumers in the vicinity of Moundridge. By its terms this contract was to continue in force until July 1, 1936, and thereafter from year to year until canceled by either party, which could be done by giving 60 days’ notice in writing. The city of Moundridge served this notice, terminating the contract July 1,1936; but pending the outcome of this action plaintiff is supplying the city of Moundridge with electricity under the terms of the contract and orders of the court. Moundridge has a population of 875, is using 325 meters in its distribution system, and during 1935 used 366,540 K.W.H. from plaintiff, and paid therefor the sum of $6,444.40. Plaintiff has a transmission line approximately seventeen miles in length, extending from Newton in Harvey county to Moundridge, with which it supplies that city and one additional customer therein, and the towns of Hesston in Harvey county and Goessel in Marion county, an oil field east of Mound-ridge, and nine rural customers in McPherson county, south and east of Moundridge.

The city of McPherson, in McPherson county, is a city of the second class, with a commission form of government. It has owned and operated a municipal electric plant since 1909, and has had rural transmission lines extending into the surrounding trade territory since 1918, northeast, southwest and southeast of the city. The [616]*616line extending southeast toward Moundridge, about seventeen miles, has been serving rural customers north and west of Moundridge since 1921, and in that year defendant had a substation within the corporate limits of Moundridge, but furnished no current to customers within the corporate limits. In 1934 and 1935, at an expense of about $245,000, defendant rebuilt and enlarged its generating plant in order to take care of the growing demands of its customers, both within and without the city. Plans were prepared for the reconstruction of many of its existing lines and the construction of new lines. One of these was a 12,000-volt, three-phase line along U. S. highway 81 from the town of Elyria to within about a mile and a half of Moundridge, which line, except for the stringing of wires on eight poles about midway between the two towns, had been completed at the time of the hearing. This was a reconstruction and extension of a previously existing line, and is the same type as other lines extending in other directions from the city of McPherson. Plaintiff makes no claim that defendant is planning to supply current to any of plaintiff’s customers other than Mound-ridge, which has canceled its contract with plaintiff, as it had a right to do. The total cost of this rural electrification program is between $120,000 and $135,000 and involves the construction and reconstruction of about 198 miles of transmission lines to serve about 493 customers, none of whom is served by plaintiff. This was financed by a bond issue, a PWA grant, and current revenues.

In February, 1936, the city of McPherson obtained from the corporation commission an order approving the location and type of construction of- the lines. N;o certificate of convenience and necessity was obtained from the corporation commission, or applied for. In April, 1936, a contract was entered into by the governing bodies of the cities of McPherson and Moundridge by which the city of Moundridge was to buy its electric energy from the city of McPherson for a term beginning July 1, 1936. Soon thereafter, and on May 8, 1936, this action was filed. Plaintiff is not a taxpayer of the city of McPherson and does not rely upon its status as such for its right or authority to maintain this action, but does rely upon the theory that it is threatened with unfair competition by acts of the city of McPherson unauthorized by law. Defendant questions the right of plaintiff to maintain this action, but we pass that question, for the reason that in an effort to eliminate it at the time of the argument in this court it was suggested the question [617]*617might be eliminated if the state, through its attorney general, would then intervene in the action; and this was done. Without:determining the effect of this upon all of the details argued by counsel it seems clear the case is before us for our determination of the principal questions presented.

We turn now to the legal questions argued. Is the city of McPherson required by law to obtain a certificate of convenience and necessity from the corporation commission of the state before it can extend its electric transmission lines into territory outside of the corporate limits of the city? The first statute we had requiring any public utility to procure such a certificate was enacted in 1911 (Laws 1911, ch. 238). Prior to that time utility companies, such as plaintiff, extended lines into, territory or not as their managing officers determined it was advisable to do so for business reasons. The general purpose of this statute was to place public utilities not municipally owned and operated under the supervision of the state, acting through its corporation commission, or similar regulatory bodies, in a manner similar, to the supervision which the state previously had exercised over railroads. In some respects it was framed after the Interstate Commerce Commission Act of Congress. This act of 1911, with some amendments or modifications not here important, continues to be the law of this state. (G. S. 1935, 66-101, et seq.) It contained within it (§ 3) the provision:

“Nothing in this act shall apply to any public utility in this state owned and operated by any municipality.” (G. S. 1935, 66-104.)

Section 31 of the act provided that no public utility governed by the provisions of the act could transact business in the state until it had obtained a certificate of convenience from the Public Utilities Commission. Soon after this statute was enacted these provisions came before the court for consideration in Humphrey v. City of Pratt, 93 Kan. 413 (1914), 144 Pac. 197.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kansas Public Service Co. v. State Corporation Comm.
433 P.2d 572 (Supreme Court of Kansas, 1967)
State Ex Rel. Fatzer v. Sinclair Pipe Line Co.
304 P.2d 930 (Supreme Court of Kansas, 1956)
State Ex Rel. Steere v. Franklin County Farm Bureau
239 P.2d 570 (Supreme Court of Kansas, 1951)
State Ex Rel. P.U.D. Etc. v. Wylie
182 P.2d 706 (Washington Supreme Court, 1947)
Central Lincoln Peoples' Utility District v. Smith
133 P.2d 702 (Oregon Supreme Court, 1943)
City of North Newton v. Regier
103 P.2d 873 (Supreme Court of Kansas, 1940)
State ex rel. Parker v. City of Kansas City
98 P.2d 101 (Supreme Court of Kansas, 1940)
City of Curtis v. Maywood Light Co.
288 N.W. 503 (Nebraska Supreme Court, 1939)
Hunt v. Eddy
90 P.2d 747 (Supreme Court of Kansas, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
72 P.2d 985, 146 Kan. 614, 1937 Kan. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-gas-electric-co-v-city-of-mcpherson-kan-1937.