Kansas Electric Utilities Co. v. Bowersock

202 P. 92, 109 Kan. 718, 1921 Kan. LEXIS 353
CourtSupreme Court of Kansas
DecidedNovember 12, 1921
DocketNo. 23,064
StatusPublished
Cited by17 cases

This text of 202 P. 92 (Kansas Electric Utilities Co. v. Bowersock) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas Electric Utilities Co. v. Bowersock, 202 P. 92, 109 Kan. 718, 1921 Kan. LEXIS 353 (kan 1921).

Opinion

The opinion of the court was delivered by

Porter, J.:

Since 1909 the defendants, under a written contract with the Lawrence Railway and Light Company (since acquired by the plaintiff), have been furnishing electrical power to the plaintiff, and the sole question in this case is one involving defendants’ right to terminate the contract. ' The plaintiff, and its predecessor in interest, will be referred to as the plaintiff. Sometime in 1915 defendants notified plaintiff that they had reached their capacity in furnishing electric energy. On various occasions thereafter the parties discussed the matter until 1918, when the defendants gave plaintiff formal notice that they would' be compelled to terminate the contract because of the insufficiency of water power. Notice of termination was again given in 1919, when plaintiff brought this action to enjoin defendants from terminating the' contract.

On the trial the court made findings of fact and conclusions of law, finding the issues in favor of the plaintiff, and granted the injunction. The defendants appeal.

The defendants are the owners of the Bowersoek mills at Lawrence and the Bowersoek power dam in the Kaw river at Lawrence. At the time the contract was made, April 24, 1909, both parties believed the water power sufficient to cover the demands of both under ordinary conditions and to allow for normal growth of the business of both. Doubtless for that [720]*720reason there was no express limit placed in the contract as to the amount of energy which was to be used by the plaintiff or furnished by the defendants. It was stated in the contract that defendants proposed to furnish, and plaintiff proposed to take, the energy required by the plaintiff.' There was, however, a conditional limit mentioned in the contract which was, the extent of the water power supplemented, in case of extraordinary occasions, accidents and emergencies, with steam power. In 1909 the amount of power demanded by plaintiff was 643,000 kilowatts per year. By 1914 plaintiff’s demand had increased to 1,686,000 kilowatts; in 10 years it had increased to 2,164,000. The increase was occasioned largely by the demand for electric light which usually comes during the hours from 6:00lo 12:00 p. m. This demand is spoken of in the evidence as the “peak load,” and from 1909 to 1919 the peak load had increased more than three times. During these years the demand of the defendants likewise increased. They constructed a second flour mill, doubling their demand for that purpose, and took on a contract with the city of Lawrence for pumping water, which required additional power. The second mill, however, was shut down during the peak load, and the contract with the city contained a provision that it should receive only such amount of power as might be absolutely necessary between 6 o’clock pi m. and midnight. In 1915 defendants put flushboards two feet high on top of the dam, increasing the head of water by an equal amount. The boards were washed away séveral times a year but were replaced and maintained, and they added about one-third to the capacity of the water-power plant. In 1916, plaintiff required 260,000 kilowatts more than in 1915, and it was found necessary to operate the auxiliary steam plant on more than five-sixths of the days of that year. After the defendants, in the fall of 1918, notified plaintiff that they would be obliged to terminate the contract in accordance with its terms and urged plaintiff to make other arrangements to obtain power, defendants renewed their storage batteries and made a number of changes in an attempt to increase the water power. Use of the auxiliary steam plant was required on more than four-fifths of the days during 1918, and in 1919 on more than two-thirds of the days.

There is no claim by either party of deceit or fraud in the [721]*721wording of the contract, and no claim that either party misunderstood its terms. There is no question concerning its validity, and both parties insist upon its enforcement.

The first paragraph of the contract provides that defendants shall sell and deliver to plaintiff electric energy, and that plaintiff shall purchase and pay for the same for a term of twenty-one years unless sooner terminated as provided in the contract.

The next paragraph provides that when there is not ample or sufficient water power to operate the railway and electric lighting system of plaintiff, the defendants shall supply sufficient power from the auxiliary steam plant, and provides for certain installations of water power, steam and electrical equipment. The''plaintiff also agreed to install certain electrical storage batteries, “to be charged and paid for to the- extent of $45,000 in cash,” and also to install an auxiliary steam turbine or gas engine plant.

The third paragraph provides:

“The party of the first part proposes to furnish all the power that may be necessary and required by the party of the second part. It is not the understanding nor agreement that The Bowersock Mills and Power Company will operate the steam or gas plant continuously, or the water power plant and steam plants together continuously. It is the understanding that the water power under ordinary conditions will supply the power to be required, and the steam or gas plant is for extraordinary occasions, accidents or emergencies. In case the party of the first part has not sufficient water power at any time to supply sufficient current for the party of the second part, it shall immediately and so that there will be no unreasonable interruption in the operation of its railway or lighting system, put in operation the auxiliary steam of gas engine plants as the case may be, in order to supply sufficient power for the party of the second part, and to exercise due diligence in operating its plants to provide the party of the second part with a continuous supply of energy or power to meet the requirements of the party of the second part.”

The same clause provides in substance that if all the power generated from the auxiliary plants shall be temporarily necessary for the interest of the plaintiff, it shall have the exclusive use of the same.

In the fifth paragraph it is agreed that the defendants do not guarantee to maintain the dam and power, and will only be entitled to pay when they furnish a merchantable electric current and that—

[722]*722“In case of the failure, however, of the party of the first part to maintain its dam and water power, or in case this contract for any reason is abrogated or annulled, then the party of the second part shall have the right to acquire the auxiliary steam turbine or gas engine plant to be erected by the party of the first part in the manner as hereinafter provided.”

The main controversy between the parties arises over the terms of paragraph six, which reads as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. Chipman
510 P.2d 1257 (Supreme Court of Kansas, 1973)
Darby v. Keeran
505 P.2d 710 (Supreme Court of Kansas, 1973)
Smith v. Russ
339 P.2d 286 (Supreme Court of Kansas, 1959)
Kelly v. Grimshaw
167 P.2d 627 (Supreme Court of Kansas, 1946)
Shell v. Strong
151 F.2d 909 (Tenth Circuit, 1945)
Skelly Oil Co. v. Cities Service Oil Co.
160 P.2d 246 (Supreme Court of Kansas, 1945)
Movitz v. New York Life Insurance
133 P.2d 89 (Supreme Court of Kansas, 1943)
Dyal v. Brunt
123 P.2d 307 (Supreme Court of Kansas, 1942)
Southern v. Chase State Bank
61 P.2d 1340 (Supreme Court of Kansas, 1936)
Wood v. Ozark Pipe Line Co.
46 P.2d 614 (Supreme Court of Kansas, 1935)
Topeka State Bank v. Little
274 P. 1118 (Supreme Court of Kansas, 1929)
Boyd v. Colgan
268 P. 794 (Supreme Court of Kansas, 1928)
Hinshaw v. Wright
262 P. 601 (Supreme Court of Kansas, 1928)
Jackman v. Kansas Electric Power Co.
251 P. 431 (Supreme Court of Kansas, 1926)
Mansfield v. Crane
225 P. 1087 (Supreme Court of Kansas, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
202 P. 92, 109 Kan. 718, 1921 Kan. LEXIS 353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-electric-utilities-co-v-bowersock-kan-1921.