Kansas City Southern Railway Co. v. Mabry, 165 S.W. 279, 112 Ark. 110, 1914 Ark. LEXIS 216 (Ark. 1914).

Opinion

McCulloch, C. J.

The plaintiff shipped a carload of holly, in boxes and crates, from Horatio, Arkansas, over defendant’s railroad, to Kansas City, Missouri, consigned to his own order but intended for delivery to a dealer in that commodity with whom the plaintiff had a contract of sale at. the price of $2 per box, the purchaser to pay the freight. The car was loaded at Horatio during the afternoon of December 12, 1912, and left that point the next day. It was shipped as first-class freight, and, according to plaintiff’s proof, conld have reached Kansas City on December 15. It did not reach there until the morning of December 17, and there is a conflict as to when the purchaser, who, by stipulation in the bill of lading was to be notified, received notice of the arrival of the oar. Defendant’s agents testified that notice was given at 3 o’clock on the afternoon of the 17th and that the notice was renewed on the morning of the 18th. The agent of the purchaser testified that the notice was not received until the morning of the 18th. The purchaser refused to accept the holly on account of the delay in reaching Kansas City, and it was subsequently sold by defendant’s agent for the freight charges, bringing an amount $3.67 in excess of those charges. The evidence tended to show that there was no market for holly on the 18th and that there was a total loss on account of the delay.

Plaintiff instituted this action to recover the full price of the holly according to his contract with the Kansas City'dealer. He recovered a judgment below for the full amount of the contract price, and defendant has appealed to this court.

It is insisted that the verdict is not supported by the evidence. It is said, first, that there is not sufficient proof of the delay.

We are of the opinion, however, that the proof is sufficient, and that that question was properly submitted to the jury. The holly was shipped as first-class freight, the same as live stock, and witnesses who were accustomed to shipping live stock or who had shipped over that line, testified concerning the time required for a car of freight to go from De Queen, Arkansas, which is eight miles from Horatio, to Kansas City. The proof was sufficient to show that forty-eight hours was enough time to take in transporting the car to Kansas City and that any excess constituted unreasonable delay.

Sunday intervened between the date of shipment and the time the consignment should have arrived in Kansas City, and the point is made that the company was not. hound to transport the goods on that day.

There is no proof that the company refrained from forwarding freight on Sunday, and even though it had. the right to stop its trains on Sunday, if it failed to do-so, and undertook to forward the freight, it was held to-proper diligence in doing so. Western Union Telegraph Co. v. Hearn, 110 Ark. 176, 161 S. W. 1025. But if Sunday be eliminated from the time chargeable against, the defendant in transporting the freight, still there is enough to show an unreasonable delay, for even then, according to the proof, the car should have reached Kansas, City on December 16, and the proof shows that if the car had arrived on that day the damage would have been averted. The price of holly was declining very rapidly day by day and the market went to pieces thereafter.

The burden of proof was on the plaintiff to show that there was an unreasonable delay. Kansas City Southern Ry. Co. v. Morrison, 103 Ark. 522. Plaintiff has discharged that burden and adduced sufficient evidence to warrant the jury in finding that there was an. unreasonable delay.

It is next contended that the proof fails to show any damage, in that the holly could have been disposed of -at a price sufficient to save plaintiff harmless.

There was a conflict in the testimony on this point,, that adduced by the defendant tending to show that on. December 17 or 18, the holly could have been sold at a price sufficient to save the plaintiff from damage. The freight charges amounted to sixty cents per box, and it was, therefore, necessary to find a market at $2.60 per-box in order to prevent any damage. J. H. Dengel, a witness introduced by plaintiff, testified that on Decern-, her 16 the price of holly began to decline but that there were some sales at $3.50 per box; that after that day the market was demoralized because it would be impossible-to make shipments from that point in time to reach other-points in the territory for Christmas sales. He testified further that after the 16th “it was a question to get whatever price you could for whatever was held over after that day. The market on the 17th was $2.50 per crate, and from that to $1, and some was dumped without any sale.” Holly is perishable, and this testimony was sufficient to show that at the time it reached Kansas City there was no market for it and that it was a total loss. The testimony warranted the jury in finding that the dealer had no opportunity to place it on the market before December 18, when the proof is clear enough that there was practically no sale for it. Even accepting the statement of defendant’s agents that notice was given at 3 o’clock on the afternoon of the 17th, the jury could have drawn the inference that it was too near the close of business hours for the dealer to receive and put it on the market before the next day.

The testimony was, therefore, sufficient to sustain the verdict that there was a total loss of the price of the holly.

Objections were made to some of plaintiff’s testimony bearing on the question of delay. But we think the testimony was competent, and not of sufficient importance to call for discussion.

It is contended that the court erred in fixing the measure of damages according to the price of the article at the place of delivery instead of according to the price at the place of shipment, as stipulated in the bill of lading.

The evidence warranted the finding that there was no market at Horatio, or, rather, that the market there was dependent upon prices at Kansas City and other distant markets. It was proper to consider the prices at Kansas City in order -to determine the market at Horatio (St. Louis Southwestern Ry. Co. v. Kilberry, 83 Ark. 87), and there is no contention from either side that the Kansas City market was not the proper criterion in fixing the market price at Horatio, transportation charges being deducted.

The instruction was not technically correct, but in view of-the undisputed evidence no prejudice resulted.

The testimony does not show that notice to the company was given so as to warrant the recovery of special damages. But there was no error in submitting to the jury the question of special damages, which was the difference between the contract price and the market price in Kansas City on the date that the shipment reached Kansas City and notice was given to the dealer. The undisputed evidence is that the market price in Kansas City on the day that the shipment should have reached that place was considerably in excess of plaintiff’s contract price with the dealer. Learned counsel for defendant insist even that the market was in excess of the contract price on the day that the car reached Kansas City. Therefore, the restriction to the contract price really resulted in a benefit to the defendant, and it can not complain.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Central Coloso, Inc. v. Domenech
48 P.R. 330 (Supreme Court of Puerto Rico, 1935)
St. Louis-San Francisco Railway Co. v. Greig
31 S.W.2d 290 (Supreme Court of Arkansas, 1930)
H. Rouw Co. v. Kansas City Southern Railway Co.
288 S.W. 900 (Supreme Court of Arkansas, 1926)
Clear Creek Oil & Gas Co. v. Bushmaier
165 Ark. 303 (Supreme Court of Arkansas, 1924)
Barrett v. St. Louis Southwestern Railway Co.
235 S.W. 800 (Supreme Court of Arkansas, 1921)
Missouri Pacific Railroad v. Martindale
213 S.W. 777 (Supreme Court of Arkansas, 1919)
Allen v. Nothern
180 S.W. 465 (Supreme Court of Arkansas, 1915)
St. Louis, Iron Mountain & Southern Railway Co. v. Tilby
174 S.W. 1167 (Supreme Court of Arkansas, 1915)
Kansas City & Memphis Railway Co. v. Oakley
170 S.W. 565 (Supreme Court of Arkansas, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
165 S.W. 279, 112 Ark. 110, 1914 Ark. LEXIS 216, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-city-southern-railway-co-v-mabry-ark-1914.