Kanda Construction, LLC v. Gebre

197 So. 3d 791, 2015 La.App. 4 Cir. 1307, 2016 La. App. LEXIS 1408, 2016 WL 3939592
CourtLouisiana Court of Appeal
DecidedJuly 20, 2016
DocketNo. 2015-CA-1307
StatusPublished
Cited by2 cases

This text of 197 So. 3d 791 (Kanda Construction, LLC v. Gebre) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kanda Construction, LLC v. Gebre, 197 So. 3d 791, 2015 La.App. 4 Cir. 1307, 2016 La. App. LEXIS 1408, 2016 WL 3939592 (La. Ct. App. 2016).

Opinion

ROLAND L. BELSOME, Judge.

| -¡This appeal is taken from a trial court judgment rendered in favor of Mansour Kavin Zahiri. For the following reasons, we affirm.

FACTS AND PROCEDURAL HISTORY

Appellant, Amare Gebre (“Mr. Gebre”)1 is the owner of real property and improvements (the “Property”) at 1544 Gentilly Boulevard in New Orleans, Louisiana. In 2012, Hurricane Isaac damaged the Property and the City of New Orleans (the “City”) determined the Property was in imminent danger of collapse and thereafter demolished the existing structure.2

[793]*793By contract dated February 17, 2013 Appellee, Randa Construction, L.L.C. (“Randa”), agreed to construct a new building on the Property for the sum of $130,000. The contract called for periodic payments based on percentage of completion. Ultimately, Mr. Gebre withheld a final payment of $13,000 from Randa, a fact which Mr. Gebre readily admits. On June 5, 2014, Randa filed suit to | aenforce final payment on the building contract alleging that all work required under the contract was completed. Additionally, Randa sought an additional $6,000 for work done at the request of Mr. Gebre, which fell outside the scope of the contract.

Shortly .thereafter, on July 2, 2015, Mr. Gebre answered and .reconvened for damages alleging that Randa failed to.follow the architect’s.plans and specifications and that the work was done poorly and incompletely. Mr. Gebre alleged that, as a result of these failures, he is unable to obtain a final inspection permit from the City and that his property remains out of commerce. Accordingly, Mr. Gebre sought the cancellation of a lien filed by Randa, damages for Randa’s poor and incomplete work, and lost rents.

Prior to trial, Mr. Gebre filed a Motion for Summary Judgment which was denied by the district court. Mr. Gebre then filed a Motion in Limine to preclude Mansour Ravin Zahiri (“Mr. Zahiri”), owner of Ran-da, from testifying as his own expert on the ground of lack of reliability.3 The motion to prevent Mr. Zahiri from testifying as an expert was denied, and the matter was tried on February 11-12, 2015, and taken under advisement. On September 22, 2015, a Judgment and Reasons for Judgment were issued in favor of Randa in the amount of $13,000, thereby dismissing Mr. Gebre’,s reconventional demand. for damages. It; is this Judgment from which Mr. Gebre appeals.

m\¡fiSSIGNMENTS OF ERROR 4
1. The district court erred in finding ■ that Randa carried the applicable burden-of proof in its contract enforcement claim, and in determining that Mr. Gebre 'failed to meet the burden in his reconventional demand for damages.
-2. The district’court abused its discretion and committed reversible error in overruling Mr. Gebre’s Motion in Limine to strike Mr. Zahiri from testifying as an expert, thereby permitting Mr. Zahiri to offer his own expert testimony. ■ .

STANDARD OF REVIEW

In Rosell v. ESCO, 549 So,2d 840 (La.1989), the Louisiana Supreme Court discussed the well settled rule that an appellate court may. only set aside a factual finding of a trial court where .the finding was based on a “manifest error” or was “clearly wrong.” Where there is conflict in the testimony, a trial court’s reasonable evaluations of credibility and reasonable inferences of fact should not be disturbed on appeal. Id. at 844. Thus, where there are two permissible views of the evidence, the trial court’s choice between them cannot be manifestly erroneous or clearly wrong. Id. Further, if a trial court has [794]*794based its findings of fact on a determination regarding the credibility of the witnesses, the manifest error standard of review requires even more deference to the findings of the trier of fact, due to the fact finder’s unique position to discern variations in the witnesses’ demeanor and tone of voice. Id.

| ¿However, where the decision of the trial court is based on an erroneous application of law rather than a valid exercise of discretion, the trial court’s decision is not entitled to deference from the reviewing court. Kem Search, Inc. v. Sheffield, 434 So.2d 1067, 1071-72 (La.1983). In this situation, reviewing courts should apply a de novo standard of review. Kevin Associates, L.L.C. v. Crawford, 2003-0211, p. 15 (La.1/30/04), 865 So.2d 34, 43.

DISCUSSSION

Assignment of Error 1

Mr. Gebre first asserts that the district court erred in determining that Kanda met the burden of proof applicable in contract enforcement proceedings and, in turn, in determining that Mr. Gebre did not meet his burden in his reconventional demand for damages. It is not refuted that Mr. Gebre has not paid the final $13,000 owed under the contract; however, the parties differ as to whether all work required under the contract was completed according to the specifications.

Notably, there is a dispute as to whether some of the documents submitted to the City prior to the demolition of the previous structure on the property were confused with documents submitted for the new construction over which the parties had contracted. Based on the testimony elicited at trial regarding the plans, the trial court determined that the parties were operating under a “revised” plan and specifications, which replaced the original plan contained in the contract.5

[BThe heart of the testimony elicited at trial was that of the parties’ experts, whose opinions conflicted regarding the sufficiency of Kanda’s work. This Court has recognized that it is the responsibility of the trier of fact to determine which evidence is most credible when testimony of expert witnesses differs. Schlesinger v. Herzog, 1995-1127, p. 12 (La.App. 4 Cir. 4/3/96), 672 So.2d 701, 710. Tommie Johnson (“Mr. Johnson”), Mr. Gebre’s construction expert, testified that there were twenty-seven discrepancies between the plans and what was actually built by Kanda. However, as noted by the trial court in its reasons for judgment, Mr. Johnson admitted on cross-examination that he had never seen the “revised” plans, nor had he been informed about any oral changes to the plans. After comparing the discrepancies with the “revised” plans, Mr. Johnson conceded that many of the discrepancies on his list could be explained by the revisions. Accordingly, the weight of Mr. Johnson’s testimony as a whole did not fully dispute Mr. Zahiri’s assertions.

On the other hand, the trial court credited Mr. Zahiri’s testimony concerning numerous oral change orders that accounted for the deficiencies complained of by Mr. Gebre.6 For example, Mr. Gebre complains, inter alia, that Kanda failed to install the appropriate number of windows, incorrectly located doors, and failed to install walls called for in the plans. The record reflects that these departures from the architectural plans were by agreement [795]*795of the parties due to Mr. Gebre’s desire to create more floor space and shelving in the store.

| (¡Additionally, Mr. Gebre conceded that it was contractually his responsibility to purchase various pieces of equipment, i.e. the handicap lift and kitchen appliances. Mr. Gebre avers that the kitchen door was left uninstalled, but the court attributed this discrepancy to Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cibilic v. Cox Operating, L.L.C.
249 So. 3d 323 (Louisiana Court of Appeal, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
197 So. 3d 791, 2015 La.App. 4 Cir. 1307, 2016 La. App. LEXIS 1408, 2016 WL 3939592, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kanda-construction-llc-v-gebre-lactapp-2016.