Kademenos v. Harbour Homeowners Ass'n

2011 Ohio 1266, 193 Ohio App. 3d 112
CourtOhio Court of Appeals
DecidedMarch 18, 2011
DocketNo. E-10-042
StatusPublished
Cited by1 cases

This text of 2011 Ohio 1266 (Kademenos v. Harbour Homeowners Ass'n) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kademenos v. Harbour Homeowners Ass'n, 2011 Ohio 1266, 193 Ohio App. 3d 112 (Ohio Ct. App. 2011).

Opinion

Yarbrough, Judge.

{¶ 1} This is an appeal and cross-appeal from a judgment of the Erie County Court of Common Pleas that granted summary judgment in favor of appellee and cross-appellant, Harbour Homeowners Association, and appellee, Harbour Lagoons Association, on claims for breach of contract and declaratory relief. The underlying dispute in this case is whether appellees are obligated to dredge a portion of the Pipe Creek waterway to provide appellants/cross-appellees boat access to Sandusky Bay and Lake Erie. Upon consideration of the assignments of error, we affirm.

{¶ 2} The undisputed facts of this case are as follows. On July 21, 2001, appellants/cross-appellees, Victor and Evon Nádemenos, purchased waterfront property in the Harbour Lagoons Subdivision (“subdivision”) located along Pipe Creek in Sandusky, Ohio. By virtue of this ownership, the Nademenoses became members of appellee, the Harbour Lagoons Association (“Lagoons Association”), a homeowners association.

{¶ 3} On May 30, 1992, the original developer of the subdivision, Admiral’s Harbour, Inc. (“AHI”), entered into an agreement (“AHI-HOA Agreement”) with a neighboring homeowners association, Harbour Homeowners Association (“HOA”), appellee and cross-appellant, that stated, “[HOA] shall dredge the [115]*115canals and waterways adjoining the Harbour and the Harbour Lagoons Subdivision, as it may from time to time be expanded, as needed.”

{¶ 4} Later, on July 31, 1996, AHI and the Lagoons Association entered into the Pipe Creek Channel Operating Agreement (“PCCO”), which created the Pipe Creek Channel Association, for the purpose of “maintaining, dredging, and preserving the channel constructed in Pipe Creek and a portion of East Sandusky Bay (‘Channel’).” In the PCCO, “Channel” is defined as “Sections A and G as shown in the ‘Master Dredging Plan’ ” — a document provided by the Army Corps of Engineers that was incorporated into the PCCO, and which provides a map of all of the relevant waterways. AHI and the Lagoons Association are the only members of the Pipe Creek Channel Association. HOA is a nonmember owner.

{¶ 5} This dispute is over the rights and duties created by paragraph 2(a) of the PCCO, which provides for contributions from nonmember owners, stating:

{¶ 6} “Under an agreement dated as of May 30, 1992 between AHI and HOA * * * HOA agreed to assume responsibility for dredging the canals and waterways adjoining the Harbour Properties and the Lagoons Subdivision as expanded, including Sections C and D as shown on the Master Dredging Plan (and Sections B and E if such sections are created as part of the Lagoons Subdivision) #$¿

{¶ 7} Further, paragraph 7 of the PCCO provides: “The Owners acknowledge that several of the Harbour Properties and other Properties contain separate canal systems that provide access to Pipe Creek but are not considered to be part of the Channel for purposes of this agreement. The Owners acknowledge and agree that * * * [iii] HOA is solely responsible for the maintenance, dredging, and preservation of Sections C and D of the Master Dredging Plan (and Sections B and E if such sections are created as part of the Lagoons Subdivision) as provided in the [AHI-HOA Agreement].”

{¶ 8} The subdivision, as originally contemplated by AHI, would be comprised of lots located along four canals, referred to as Sections B, C, D, and E, respectively, which would feed into the main channel, referred to as Section A. Section A, which runs along Pipe Creek on the side opposite from the Kademenoses’ property, provides boat access to Sandusky Bay and Lake Erie. As identified in the Master Dredging Plan, only Sections C and D were existing canals; Sections B and E were “to be dry excavated.” In December 1996, AHI sold its remaining property in the subdivision to Harbour Lagoons Ltd., now known as 4920 Milan Investments, Ltd. (“Milan”). Milan redesigned the subdivision, and in so doing eliminated the plans to create Section B. The Kademenoses’ property is located on land that would have been excavated had Section B been created.

[116]*116{¶ 9} The events that led to this action involve a July 3, 2003 letter that Victor Hádemenos wrote, requesting that HOA dredge the waterway adjoining his property to provide access to Sandusky Bay and Lake Erie. HOA responded by a letter dated September 3, 2004, in which HOA refused to dredge the waterway, stating that it had no such obligation. Consequently, on October 29, 2008, the Kademenoses filed a complaint against HOA, Lagoons Association, Milan, Pipe Creek Channel Association, and John Does 1 through 5 containing claims for breach of contract for “failing to dredge and maintain [Section] B,” and for declaratory judgment that “[defendants are responsible to dredge [Section] B of the Pipe Creek Channel.”1

{¶ 10} After the initial pleadings were received, the trial court ordered that dispositive motions were to be filed by March 15, 2010. HOA, Lagoons Association, and Milan timely filed motions for summary judgment. The Kademenoses did not respond to these motions. On April 28, 2010, the trial court, in two separate judgment entries, granted summary judgment for HOA, Lagoons Association, and Milan, holding that Section B was never created and therefore no obligation to dredge or maintain Section B arose.

{¶ 11} Shortly thereafter, on April 30, 2010, the Kademenoses filed a “Motion for Reconsideration of the Court’s Decisions Entered April 28, 2010” and a “Motion for Leave to File Brief in Opposition and Cross Motion for Summary Judgment Instanter.” The trial court granted both motions on June 3, 2010, setting aside the April 28, 2010 judgments, and allowing the Kademenoses to file a brief in opposition and cross-motion for summary judgment. In addition, on August 2, 2010, the Kademenoses filed a “Motion for Relief from Judgment Entered April 28, 2010.” The trial court, in judgment orders dated August 17, 2010, August 19, 2010, and August 25, 2010, granted the Kademenoses’ “Motion for Relief from Judgment Entered April 28, 2010,” but at the same time granted HOA’s, Lagoon Association’s, and Milan’s motions for summary judgment.2 The trial court again based its decisions on the grounds that Section B was never created and therefore, under the clear and unambiguous terms of the contract, no obligation to dredge Section B arose.

{¶ 12} The Kademenoses now appeals these three summary-judgment orders. HOA cross-appeals the June 3, 2010 order granting the Kademenoses’ motion for [117]*117reconsideration and the August 17, 2010 order granting the Kademenoses’ motion for relief from judgment.

{¶ 13} The Kademenoses asserts the following single assignment of error:

{¶ 14} “The trial court erred in its interpretation of the Pipe Creek Channel Agreement wherein it found that the natural existing waterway portion of Channel B was not ‘created’ and therefore gave rise to no obligation on the part of the defendants to ‘dredge the waterways adjoining the harbour and the Harbour Lagoons Subdivision as expanded’ and thereby granting defendants’ motions for summary judgment.”

{¶ 15} We note at the outset that an appellate court reviews summary-judgment rulings de novo, applying the same standard as the trial court. Lorain Natl. Bank v. Saratoga Apts. (1989), 61 Ohio App.3d 127, 129, 572 N.E.2d 198; Grafton v. Ohio Edison Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joseph Bros. Co., L.L.C. v. Dunn Bros., Ltd.
2019 Ohio 4821 (Ohio Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2011 Ohio 1266, 193 Ohio App. 3d 112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kademenos-v-harbour-homeowners-assn-ohioctapp-2011.