K BAR A RANCH

CourtUnited States Bankruptcy Court, D. Montana
DecidedJune 7, 2024
Docket1:22-bk-10004
StatusUnknown

This text of K BAR A RANCH (K BAR A RANCH) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K BAR A RANCH, (Mont. 2024).

Opinion

UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF MONTANA

In re

K BAR A RANCH, Case No. 1:22-bk-10004-BPH Debtor.

MEMORANDUM OF DECISION

I. Introduction.

In this chapter 12 bankruptcy,1 this Court is tasked with parsing through an oversecured creditor’s legal fees and Debtor’s objection to those fees because the fees are allegedly unreasonable. It is a tedious task, made more tedious by the application’s lack of detail or explanation for the necessity of the fees in a case that was neither complex nor novel. Despite the fatiguing nature of the task, it is particularly important because any fees approved as reasonable will in essence be reimbursed by Debtor through its confirmed plan. For the reasons stated below, this Court approves $12,500, in fees and denies the remainder as unreasonable for purposes of § 506(b). This Court approves reimbursement for costs.

II. Procedural Background. First Pioneer National Bank (“Creditor”) filed an “Application for Professional Fees and Costs” requesting approval of fees and costs for its attorneys (collectively, Creditor and its counsel are “Applicant”).2 The Application requests an award of fees in the amount of $49,767 and reimbursement for costs in the amount of $6.70. In total, Applicant requested $49,773.70. In response, Debtor filed an Objection to the Application.3

1 Unless specified otherwise, all chapter and section references are to the Bankruptcy Code, 11 U.S.C. §§ 101-1532, all “Rule” references are to the Federal Rules of Bankruptcy Procedure, and all “Civil Rule” references are to the Federal Rules of Civil Procedure.

2 ECF No. 114 (“Application”). Applicant subsequently submitted a “Supplemental Table in Support of Application for Professional Fees and Costs” at ECF No. 166 (“Supplemental Table”), indicating that Applicant had applied “additional discounts/reductions” bringing the amount requested to $45,510.20 (“Total Amount”). However, this Court cannot ascertain Applicant’s method of reduction. As a result, certain elements of this Court’s analysis of the Application may overlap with reductions already applied by Applicant.

3 ECF No. 127 (“Objection”). A hearing on the Application was held and the parties argued their respective positions.4 No exhibits or testimony were introduced. At the end of the hearing, this Court informed the parties it would take the matter under advisement. III. Factual Background. Debtor filed its chapter 12 petition on January 18, 2022. Creditor filed a proof of claim in the amount of $3,970,421.45 which was later amended by a stipulation with Debtor to $4,085,158.56 (“Claim”).5 According to the Claim, the value of the real property securing the debt has a market value of $9,520,000. Creditor’s Claim is protected by a 233% equity cushion. Debtor’s initial chapter 12 plan proposed to pay Creditor’s Claim with an interest rate of 4%.6 Under the Plan, Debtor would provide annual installments of $234,727 over a term of 30 years commencing on plan confirmation. Creditor objected to the Plan.7 In its Plan Objection, Creditor argued that the proposed interest rate did not include an upward adjustment for risk, resulting in a possible windfall for Debtor at the expense of Creditor. Creditor additionally argued that the proposed 30-year payment term in the Plan greatly exceeded Debtor’s original obligation. Confirmation of the Plan was denied.8 In the intervening time between filing the Plan and the Plan Objection, the chapter 12 Trustee held a preliminary plan conference on May 23, 2022.9 Although it appeared all issues were resolved at the conference, the Debtor and Creditor quibbled over the language included in a stipulation documenting their agreement. As a result, the Trustee held another preliminary plan conference on June 28, 2022. At this conference, the parties reached an agreement in principle a second time, but once again could not agree on the language for purposes of a stipulation. Specifically, Creditor wanted to include a “status quo” provision that explicitly provided that each covenant, term, and obligation in the prepetition agreements between the parties would not be changed absent express modification in the Plan.10

4 ECF No. 161.

5 Claim No. 3-1 on the Claim Register; ECF No. 74 (“Stipulation”).

6 ECF No. 40 (“Plan”).

7 ECF No. 50 (“Plan Objection”).

8 ECF No. 57.

9 Preliminary plan conferences are organized by chapter 12 trustees and reflect an effort by the chapter 12 trustee to resolve objections. These efforts are undertaken in part because the timeline for confirmation in chapter 12 cases is very short. 11 U.S.C. § 1221; 11 U.S.C. § 1224.

10 A status quo provision expressly preserves terms in prepetition contracts. See, e.g., United States v. Goff, 2005 U.S. Dist. 49884, at *26 (D. Idaho 2005). Such provisions provide that certain terms contained within the underlying loan agreement, such as remedies for default and acceleration of debt payments, are preserved post-confirmation. Id. Absent a status quo provision, a court may interpret the confirmed plan to override the prepetition provisions. See Navistar Fin. Corp. v. Jim Having reached an agreement twice, only to have the parties’ efforts scuttled when drafting a stipulation, Debtor filed a “Motion to Enforce Settlement.”11 Creditor objected to the Motion to Enforce.12 Debtor responded by filing an Objection to Creditor’s Claim.13 Debtor filed an amended plan on August 12, 2022.14 The Amended Plan increased the interest rate and provided for annual payment of $271,756 over a term of 30 years commencing on plan confirmation. Creditor again objected to the Amended Plan.15 The Amended Plan Objection highlighted multiple issues, but its primary focus involved the Amended Plan’s failure to include a status quo provision. Debtor and Creditor ultimately reached an agreement on the outstanding issues. Remarkably, this time the parties agreed on the language and form of the Stipulation.16 Pursuant to the Stipulation, Debtor agreed to include a status quo provision in the Amended Plan and withdrew its Motion to Enforce and Claim Objection.17 In return, Creditor withdrew its Amended Plan Objection. Debtor’s Amended Plan was confirmed.18 Creditor filed the present Application pursuant to § 506(b). No contested hearings were held on any of the above matters, except the Application. Notably, counsel for Debtor filed an “Interim Application for Compensation” roughly a month prior to the Application.19 Debtor’s Application, which includes Debtor’s disputes with Creditor along with the additional tasks and duties required of Debtor’s counsel, requested $22,655.50 in fees compared to the approximately $50,000 in fees requested by Applicant. Notably, Debtor’s counsel billed approximately 60 hours less than Applicant. Following the hearing, at this Court’s request, Applicant submitted an itemized table that

Palmer Trucking, 2012 U.S. Dist. 20510, at *12-13 (D. Mont. 2012) (holding that a creditor could not accelerate maturity of debt owed to it by the debtor because plan did not expressly contain acceleration clause). Creditor relied on this case in its objections to confirmation.

11 ECF No. 54 (“Motion to Enforce”).

12 ECF No. 67.

13 ECF No. 68, Claim No. 3-1 on the Claim’s Register (“Claim Objection”).

14 ECF No. 69 (“Amended Plan”).

15 ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Ron Pair Enterprises, Inc.
489 U.S. 235 (Supreme Court, 1989)
Hoopai v. Hoopai
581 F.3d 1090 (Ninth Circuit, 2009)
Dalessio v. Pauchon (In Re Dalessio)
74 B.R. 721 (Ninth Circuit, 1987)
Meritor Mortgage Corp. v. Salazar (In Re Salazar)
82 B.R. 538 (Ninth Circuit, 1987)
In re Heath
483 B.R. 708 (E.D. Arkansas, 2012)
Ursic v. Bethlehem Mines
719 F.2d 670 (Third Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
K BAR A RANCH, Counsel Stack Legal Research, https://law.counselstack.com/opinion/k-bar-a-ranch-mtb-2024.