JWP Zack, Inc. v. Hoosier Energy Rural Electric Cooperative, Inc.

709 N.E.2d 336, 1999 Ind. App. LEXIS 557, 1999 WL 203721
CourtIndiana Court of Appeals
DecidedApril 13, 1999
Docket42A01-9710-CV-339
StatusPublished
Cited by3 cases

This text of 709 N.E.2d 336 (JWP Zack, Inc. v. Hoosier Energy Rural Electric Cooperative, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JWP Zack, Inc. v. Hoosier Energy Rural Electric Cooperative, Inc., 709 N.E.2d 336, 1999 Ind. App. LEXIS 557, 1999 WL 203721 (Ind. Ct. App. 1999).

Opinion

OPINION

SHARPNACK, Chief Judge

JWP Zack, Inc. (“Zack”) appeals the trial court’s denial of its motion for partial summary judgment and its motion to compel the production of certain evidence. Zack raises two issues which we restate as:

(1) is there a genuine issue of material fact as to whether the limitation of liability clause contained in a 1990 agreement (“Mother Agreement”) limits any liability Zack might have to Hoosier Energy Rural Electric Cooperative, Inc. (“Hoosier”) for the loss that is the basis of this lawsuit; and,
(2) did the inadvertent disclosure of documents privileged as attorney-client communications during discovery waive Hoosier’s right to invoke thereafter the privilege as to those documents.

We affirm.

This case arises from a 1992 fire which occurred at Hoosier’s Merom Generating Station (“Station”). At the time of the fire, Zack was performing work, pursuant to a contract, at the Station for Hoosier. Hoosier sued Zack claiming that Zack’s negligence caused the fire and resultant damages to the Station. Zack denied liability and further *338 claimed that any liability it might have was limited by the Mother Agreement. 1

I.

The first issue is whether there is a genuine issue of material fact as to whether the limitation of liability clause contained in the Mother Agreement applies to Hoosier’s loss. Zack claims that the Mother Agreement is the contract that establishes the basic relationship between the parties and that its limitation of liability clause limits any liability Zack may have to Hoosier. To the contrary, Hoosier contends that the Mother Agreement was not in effect at the time of the fire and that the relationship between the parties is governed by an agreement entered into in 1992 (“1992 Agreement”) which contains no limitation of Zack’s liability.

The trial court denied Zack’s motion for partial summary judgment refusing to hold that Zack’s liability was limited by the Mother Agreement. The trial court found that there was no dispute as to the material facts; however, it held:

“Both parties ... throughout their motions and briefs, ask the Court to draw inferences and subjective conclusions from these facts which the law of this State prohibits at this stage of the proceedings. Therefore, both Motions for Partial Summary Judgment are denied.”

Record, pp. 1240. Hoosier does not appeal the denial of its motion for partial summary judgment.

Summary judgment is appropriate only when there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Ind. Trial Rule 56(C). The moving party has the initial burden to make a prima facie showing of these requirements. Shumate v. Lycan, 675 N.E.2d 749, 752 (Ind.Ct.App.1997), trans. denied, 683 N.E.2d 595. Once the movant has made such a showing, the opponent must respond by setting forth specific facts showing a genuine issue for trial; the opponent may not simply rest on the allegations of the pleadings. Stephenson v. Ledbetter, 596 N.E.2d 1369, 1371 (Ind.1992). On appeal, we are bound by the same standard as the trial court and may consider only those matters which were designated at the summary judgment stage of the proceedings. Shumate, 675 N.E.2d at 752. We do not weigh evidence, but will consider the facts in the light most favorable to the nonmoving party. Reed v. Luzny, 627 N.E.2d 1362, 1363 (Ind.Ct.App.1994), reh’g denied, trans. denied. Although the facts may be undisputed, summary judgment is inappropriate where “there are conflicting inferences which may be drawn from undisputed facts.” National City Bank, Indiana v. Shortridge, 689 N.E.2d 1248, 1251 (Ind.1997), opinion supplemented by, 691 N.E.2d 1210.

The record contains five agreements for the provision of maintenance and repair work at Hoosier’s Station. Hoosier is designated as the “owner” in all five. In two of them, the “contractor” is designated as Westerfield Company, Inc. The first of these two agreements was executed as of February 1, 1988, and provided that the contractor would provide repair and maintenance at the Station as separately authorized by owner’s purchase orders. It contained a clause that limited the contractor’s liability to “in no case exceed the contract price.” Record, pp. 591-592. The term of the agreement was from January 1, 1988 through December 31, 1988, unless either party terminated on thirty days notice. The second agreement, in which the contractor was designated as Westerfield Company, Inc., was executed as of March 1, 1990 (“Mother Agreement”). The Mother Agreement also provided that the contractor would perform maintenance and repairs as requested by the owner by the issuance of owner’s purchase orders. It also contained a limitation of liability clause, which again provided that the contractor’s liability should “in no case exceed the contract price.” Record, p. 637. The parties dispute the meaning of this clause and differ as to whether the clause refers to the sum total of all work *339 orders issued under the agreement, or whether the contract price refers to the amount of a particular work order. The Mother Agreement also provided for the provision of maintenance and repair for the calendar years 1990 and 1991 with an owner’s “option to renew for an additional two years.” Record, p. 633.

In a Hoosier interoffice memo dated January 8, 1988, from D.D. Winter to V.E. Peterson, Winter reported that during the fall of 1987, Hoosier had solicited bids from a number of contractors regarding maintenance at Merom. He wrote, “Attached is our evaluation which has Westerfield Company, Inc.,'a subsidiary of Zack Company, as the lowest evaluated bidder.” Record, p. 576. He concluded, “Thus, we are recommending that Zack Company be awarded this contract for 1988.” Record, p. 576. On January 11,1988, the Hoosier Board of Directors adopted a resolution that, “This corporation enter into an agreement with Westerfield Company, Inc., ... to perform such maintenance and repair services at Merom Generating Station as this corporation shall from time to time designate during the calendar year of 1988.” In a Hoosier purchase order dated March 15, 1988, addressed to Zack Company, reference was made, “As per Hoosier Energy contract number 1278 signed by the Zack Company, Feb. 1, 1988.” Record, p. 615. The record indicates that contract number 1278 is a number by which Hoosier referred to the agreement with Westerfield dated as of the 1st day of February, 1988.

In a Hoosier interoffice memo dated February 27, 1990, from D.D. Winter to V.E. Peterson, Winter wrote, “The annual maintenance contract with Zack expired at the end of 1989 ....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Marriage of Amich and Adiutori
192 P.3d 422 (Colorado Court of Appeals, 2007)
Simon Property Group L.P. v. mySimon, Inc.
194 F.R.D. 644 (S.D. Indiana, 2000)
PT BUNTIN, MD, PC v. Becker
727 N.E.2d 734 (Indiana Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
709 N.E.2d 336, 1999 Ind. App. LEXIS 557, 1999 WL 203721, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jwp-zack-inc-v-hoosier-energy-rural-electric-cooperative-inc-indctapp-1999.