J.W. Garrett & Sons, Inc. D/B/A G & G Enterprises, Inc. v. Wyatt D. Snider, Jack Koch, and John Thomasson

CourtCourt of Appeals of Texas
DecidedOctober 1, 2015
Docket09-14-00306-CV
StatusPublished

This text of J.W. Garrett & Sons, Inc. D/B/A G & G Enterprises, Inc. v. Wyatt D. Snider, Jack Koch, and John Thomasson (J.W. Garrett & Sons, Inc. D/B/A G & G Enterprises, Inc. v. Wyatt D. Snider, Jack Koch, and John Thomasson) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.W. Garrett & Sons, Inc. D/B/A G & G Enterprises, Inc. v. Wyatt D. Snider, Jack Koch, and John Thomasson, (Tex. Ct. App. 2015).

Opinion

In The

Court of Appeals Ninth District of Texas at Beaumont ____________________ NO. 09-14-00306-CV ____________________

J.W. GARRETT & SONS, INC. D/B/A G&G ENTERPRISES, INC., Appellant

V.

WYATT D. SNIDER, JACK KOCH, AND JOHN THOMASSON, Appellees

_______________________________________________________ ______________

On Appeal from the 60th District Court Jefferson County, Texas Trial Cause No. B-187,307 ________________________________________________________ _____________

MEMORANDUM OPINION

In this appeal, we consider whether the trial court properly granted a take-

nothing summary judgment on a builder’s claims alleging negligence, fraud,

misrepresentation, theft of services, and misapplication of trust funds against three

board members of the Young Men’s Christian Association of Beaumont, Texas

(BYMCA). The claims of the builder, J.W. Garrett & Sons, Inc. (G&G), arose after

1 the BYMCA defaulted on its obligation to make progress payments toward

completing a new building, which was intended to be the BYMCA’s principal

location. In four issues, G&G argues that the final judgment should be reversed,

and that its claims should be remanded for trial. We conclude the issues that G&G

raises in the appeal do not require the judgment to be reversed, and the trial court’s

judgment is affirmed.

Background

The background facts are provided in light of the summary judgment

standard of review, which requires that we view the summary judgment evidence

in the light most favorable to G&G as the party that opposed the motion for

summary judgment. See Henkel v. Norman, 441 S.W.3d 249, 250 (Tex. 2014). In

2008, the BYMCA hired G&G on a cost-not-to-exceed basis to manage the

construction of a new facility to house the BYMCA. At a meeting in January 2009,

prior to the date that G&G agreed to manage the project, Wyatt D. Snider told

G&G’s president, Colin Garrett, that “the [BYMCA] had designated $4,500,000.00

to complete the project.” When the meeting occurred, Snider was a member of the

BYMCA’s board, and in 2009, he became the board’s chair. Jack Koch, the

BYMCA’s Chief Executive Officer, was present during the meeting.

2 At another meeting in February 2009, Garrett presented G&G’s suggestions

that were designed to reduce the cost of completing the proposed project to Koch

and John Thomasson, who was at the time the meeting occurred serving as the

BYMCA’s chair. During this meeting, G&G agreed to reduce various costs for the

proposed project, reducing the maximum projected cost to build the facility to

$4,008,862.

Between February 2009 and February 2010, G&G performed a substantial

amount of work to construct the facility, but on February 11, 2010, Snider

informed G&G that the BYMCA did not have sufficient funds to complete the

project. When G&G sued the defendants, G&G had been paid $3,229,755 for its

work on the project; G&G claimed that the BYMCA owed an additional $728,325

for the work that had been completed. In addition to its claims for unpaid work,

G&G claimed in its suit that it would have earned an additional $437,410 under its

contract with the BYMCA had the project been completed.

According to an affidavit that Garrett filed to oppose the motion for

summary judgment, G&G would not have started the job had Garrett known that

the BYMCA “did not have the money to complete the construction, or that a

capital campaign or fundraising campaign would be required to raise the money to

complete the construction.” According to Garrett’s affidavit, G&G acted

3 reasonably in relying on Snider’s statement that the BYMCA had designated

$4,500,000 to pay for the project, and he asserted that in deciding whether to agree

to the BYMCA’s proposal that G&G build the new facility, G&G relied on

Snider’s statements. In his affidavit, Garrett stated that before Snider told him to

stop work, “I was not aware of how the [BYMCA] had arranged to pay for the

construction.”

In July 2010, G&G sued the BYMCA, Snider, Koch, and Thomasson on

claims that relate to the BYMCA’s failure to fully pay for the work G&G

completed and the profit it would have earned if the project had been completed.

While G&G later voluntarily dismissed BYMCA 1 from the suit, it did not dismiss

its claims against Snider, Koch, and Thomasson. In its First Amended Petition, its

1 In May 2013, Snider, Koch, and Thomasson filed a motion for partial summary judgment on all of G&G’s claims against them, but the BYMCA never filed a motion seeking summary judgment on G&G’s claims against it. Therefore, because the motion did not dispose of all of the issues in the case against all parties, the trial court’s June 2013 order granting summary judgment was interlocutory. Tex. R. Civ. P. 301 (“Only one final judgment shall be rendered in any cause except where it is otherwise specially provided by law.”). In June 2014, G&G filed a motion to dismiss the claims that it was pursuing against the BYMCA without prejudice; its motion was granted on June 4, 2014. Subsequently, G&G filed a motion for new trial, followed by a timely-filed notice of appeal. See Tex. R. App. P. 26.1 (providing that a party must file a notice of appeal within 90 days of the date a judgment becomes final if any party timely files a motion for new trial). The dismissal made the June 2013 order operate as a final judgment, effective as of the day the trial court dismissed G&G’s claims against the BYMCA. 4 live pleading for the purpose of our review, G&G claimed that Snider, Koch, and

Thomasson were liable to it for misusing construction trust funds under chapter

162 of the Texas Property Code, alleged they were negligent, that they committed

fraud, and that they had stolen G&G’s services in violation of chapter 134 of the

Texas Civil Practice and Remedies Code and section 31.04 of the Texas Penal

Code. See Act of May 26, 1983, 68th Leg., R.S., ch. 576, § 1, sec. 162.001(a), (b),

1983 Tex. Gen. Laws 3269, 3720-721, Act of May 28, 1997, 75th Leg., R.S., ch.

1018, § 1, sec. 162.001(c), 1997 Tex. Gen. Laws 3721, 3721 (amended 2009)

(current version at Tex. Prop. Code Ann. § 162.001 (West 2014)), Tex. Prop. Code

Ann. §§ 162.002-.033 (West 2014); Tex. Civ. Prac. & Rem. Code Ann. §§

134.001-.005 (West 2011 & Supp. 2014); Tex. Penal Code Ann. § 31.04 (West

Supp. 2014). 2

On May 17, 2013, Snider, Koch, and Thomasson filed their traditional

motion for summary judgment. In the motion, they asked the trial court to enter a

take-nothing judgment on G&G’s four claims. The motion is supported by Snider’s

affidavit; the parties’ contract (signed by Koch, for the BYMCA, and Garrett, for

2 For purposes of this appeal, we cite to the current version of this statute, as the statute’s subsequent amendment is not relevant to the issues raised on appeal. 5 G&G); and a copy of G&G’s unsecured proof of claim, which G&G filed in

connection with the BYMCA’s Chapter 7 bankruptcy. 3

G&G filed a response, which includes Garrett’s affidavit, copies of several

electronic messages between Garrett and Snider about the proposed project, copies

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joe v. Two Thirty Nine Joint Venture
145 S.W.3d 150 (Texas Supreme Court, 2004)
Chon Tri v. J.T.T.
162 S.W.3d 552 (Texas Supreme Court, 2005)
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
Frost National Bank v. Fernandez
315 S.W.3d 494 (Texas Supreme Court, 2010)
Van Horn v. Chambers
970 S.W.2d 542 (Texas Supreme Court, 1998)
Randall's Food Markets, Inc. v. Johnson
891 S.W.2d 640 (Texas Supreme Court, 1995)
Centeq Realty, Inc. v. Siegler
899 S.W.2d 195 (Texas Supreme Court, 1995)
Science Spectrum, Inc. v. Martinez
941 S.W.2d 910 (Texas Supreme Court, 1997)
Trevino v. Trevino
64 S.W.3d 166 (Court of Appeals of Texas, 2001)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Bradford v. Vento
48 S.W.3d 749 (Texas Supreme Court, 2001)
Ocean Transport, Inc. v. Greycas, Inc.
878 S.W.2d 256 (Court of Appeals of Texas, 1994)
Christopher Henkel and Lisa Henkel v. Christopher Norman
441 S.W.3d 249 (Texas Supreme Court, 2014)
May v. May
589 S.W.2d 8 (Supreme Court of Arkansas, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
J.W. Garrett & Sons, Inc. D/B/A G & G Enterprises, Inc. v. Wyatt D. Snider, Jack Koch, and John Thomasson, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jw-garrett-sons-inc-dba-g-g-enterprises-inc-v-wyatt-d-snider-texapp-2015.