Jutte Elec., Ltd. v. Ohio Facilities Constr. Comm.

2017 Ohio 2697
CourtOhio Court of Claims
DecidedApril 3, 2017
Docket2014-00318
StatusPublished

This text of 2017 Ohio 2697 (Jutte Elec., Ltd. v. Ohio Facilities Constr. Comm.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jutte Elec., Ltd. v. Ohio Facilities Constr. Comm., 2017 Ohio 2697 (Ohio Super. Ct. 2017).

Opinion

[Cite as Jutte Elec., Ltd. v. Ohio Facilities Constr. Comm., 2017-Ohio-2697.]

JUTTE ELECTRIC, LTD., et al. Case No. 2014-00318

Plaintiffs/Counter Defendants Judge Patrick M. McGrath Referee Dale A. Crawford v. JUDGMENT ENTRY OHIO FACILITIES CONSTRUCTION COMMISSION

Defendant/Counter Plaintiff/Third-Party Plaintiff

v.

STEED HAMMOND PAUL, INC., etc.

Third-Party Defendant/Fourth Party Plaintiff

BERARDI PARTNERS, INC.

Fourth-Party Defendant

{¶1} On December 13, 2016, the referee issued a decision recommending judgment in favor of defendant, Ohio School Facilities Commission (OSFC). Additionally, as the third-party claims and counterclaims were based solely on indemnity, the other claims, damages, and costs were denied as not supported by the greater weight of the evidence. Civ.R. 53(D)(3)(b)(i) states, in part: “A party may file written objections to a magistrate’s decision within fourteen days of the filing of the decision, whether or not the court has adopted the decision during that fourteen-day period as permitted by Civ.R. 53(D)(4)(e)(i).” After receiving two extensions of time, plaintiffs, Jutte Electric, LTD. (Jutte) and Southwest Marine and General Insurance Case No. 2014-00318 -2- JUDGMENT ENTRY

Company (Surety), filed their objections on January 17, 2017. All defendants filed responses or memorandum contra in opposition to plaintiffs’ objections on February 2, 2017. Plaintiffs raise the following five objections:

a. Objection 1: The referee’s determination that plaintiffs failed to prove that their damages resulted from the acts and omissions of the OSFC is erroneous.

{¶2} Plaintiffs assert that the referee misapplied the concept of “reasonable certainty” as it applies to damages. The referee determined that plaintiffs “failed to prove by a preponderance of the evidence within a reasonable degree of certainty that their damages were proximately caused by the OSFC.” (Objections, p. 2). Plaintiffs argue that pursuant to the holding in Tri-State Asphalt Corp. v. Ohio Dept. of Transp., 10th Dist. Franklin No. 94API07-987, 1995 Ohio App. LEXIS 1554 (April 11, 1995), it is the amount of damages that needs to be proved within a reasonable degree of certainty. Therefore, according to plaintiffs, under Ohio law a plaintiff need not prove within a reasonable degree of certainty that its damages were proximately caused by defendant. {¶3} Plaintiffs also contend that their expert, Timothy Calvey, testified that plaintiffs’ damages were caused by OSFC. Specifically, plaintiffs state that Mr. Calvey testified that plaintiffs’ damages resulted from: 1) design delays, late drawings, and an incomplete and erroneous design; 2) delayed and incomplete responses to Requests for Information (RFI); 3) dimensional issues; 4) design changes; 5) issues with schedules; and 6) late award of campus-wide bid packages for casework, technology, security, and fire alarm systems. {¶4} The court finds that the referee accurately applied the law as it pertains to plaintiffs’ burden of proof and the court does not agree with plaintiffs’ interpretation of the law. Assuming plaintiffs’ representation of the law is true, it does not change the Case No. 2014-00318 -3- JUDGMENT ENTRY

referee’s decision since he clearly held that plaintiffs failed to meet their burden of proving that OSFC proximately caused plaintiffs’ damages. {¶5} In determining the proximate cause of alleged damages to a prime contractor on a multi-million dollar construction project that spans a substantial amount of time, a trial court must rely heavily on expert testimony. The types of claims alleged by plaintiffs involve complex scheduling issues, and is therefore outside the purview of a lay person’s knowledge. Therefore, the testimony of an expert is particularly crucial in determining proximate causation. {¶6} The referee found that plaintiffs’ expert testimony lacked credibility. The credibility of witnesses and the weight attributable to their testimony are primarily matters for the trier of fact. State v. DeHass, 10 Ohio St. 2d 230, 227 N.E. 2d 212 (1967), paragraph one of the syllabus. The court is free to believe or disbelieve, all or any part of each witness’s testimony. State v. Antill, 176 Ohio St. 61, 197 N.E. 2d 548 (1964). While the court’s review of the referee’s decision is de novo, it gives great deference to the referee’s opinion regarding the credibility of trial testimony. {¶7} Accordingly, plaintiffs’ first objection is OVERRULED.

b. Objection 2: The referee erred in determining that “all claims before August 31, 2011 were settled and should not have been included as damages.”

{¶8} Plaintiffs contend that the referee erred in concluding that issues arising prior to the execution of the Memorandum of Understanding (MOU) were settled and should not have been included as damages. They argue that the August 31, 2011 MOU does not reference a settlement of any or all claims existing as of the date of its execution. In fact, plaintiffs assert that the MOU contains specific language expressly reserving their rights with respect to any and all claims. Paragraph six of the MOU states: Case No. 2014-00318 -4- JUDGMENT ENTRY

In the event that the Obligee [the OFSC] fails to perform the obligation set out in this agreement or in the Contract, the Principal [Jutte] and the Surety [Southwest] by execution of this Agreement do not waive or in any way forfeit or relinquish any legal rights they may have to assert claims against the Obligee under the Contract or Bond or waive any defenses which may have which are inconsistent with the terms of this Agreement.

{¶9} Upon review, the court finds the referee’s analysis of the effect of the MOU on plaintiffs’ claims to be an accurate interpretation. By executing the MOU, plaintiffs agreed to remedy several workmanship and scheduling issues. By agreeing to resolve these issues, thereby admitting that there were issues that needed to be addressed and remedied by plaintiffs, and not by OSFC or a supplementary contractor, plaintiffs effectively waived the right for claims related to that unresolved work. The referee did not state that plaintiffs agreed to waive their rights to pursue claims. If he had done so, the claims would not have survived summary judgment and proceed to a full trial on the merits. Specifically, the referee stated that all of the claims before August 31, 2011 should not have been included in plaintiffs’ damages. Plaintiffs had every right to bring a claim for something that occurred before August 31, 2011, but not as it pertains to the specific enumerated items in the MOU. Considering this was very early in the construction of the project and buildings were not yet out of the ground, the court is dealing with a relatively small amount of plaintiffs’ alleged damages; damages which were not proved to be caused by OSFC. {¶10} Accordingly, plaintiffs’ second objection is OVERRULED.

c. Objection 3: The referee incorrectly analyzed the bases for Southwest’s rights to assert claims against the OSFC.

{¶11} Upon thorough review, the court finds that the referee’s analysis of the Surety’s rights is consistent with the law. Even if the referee was mistaken, his opinion on pages 18-22 regarding the relationship between the Surety, OSFC, and Jutte is Case No. 2014-00318 -5- JUDGMENT ENTRY

essentially dicta. In no way does the referee’s analysis of the Surety’s rights affect the outcome of this case. {¶12} Accordingly, plaintiffs’ third objection is OVERRULED.

d. Objection 4: The referee incorrectly analyzed the sufficiency and legal ramifications of Southwest’s investigation and decision regarding how to complete Jutte’s work on the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related