Justin Cornett v. Collectable Sports Assets, LLC

Court of Chancery of Delaware·Decided December 29, 2025·No. C.A. No. 2024-1130-SEM·Published

Opinion

COURT OF CHANCERY OF THE STATE OF DELAWARE SELENA E. MOLINA LEONARD L. WILLIAMS JUSTICE CENTER SENIOR MAGISTRATE IN CHANCERY 500 NORTH KING STREET, SUITE 11400 WILMINGTON, DE 19801-3734

December 29, 2025

Arthur G. Connolly, III, Esquire John A. Sensing, Esquire Jarrett W. Horowitz, Esquire Potter Anderson & Corroon LLP Connolly Gallagher LLP 1313 North Market Street 1201 North Market Street, 20th Floor Wilmington, DE 19801 Wilmington, DE 19801

Brian Gottesman, Esquire Gabel Beaver LLC 5811 Kennett Pike Wilmington, DE 19807

Re: Justin Cornett v. Collectable Sports Assets, LLC, C.A. No. 2024-1130-SEM

Dear Counsel:

I write regarding Collectable Sports Assets, LLC (the “Defendant”)’s motion

for relief (the “Motion”) and the receiver’s interim report (the “Report”). The Motion

is denied and, herein, I answer the questions posed in the Report.

I. Background

For purposes of this letter decision, I provide only a brief background. Justin

Cornett (the “Plaintiff”) initiated this action on November 1, 2024, seeking a court-

ordered production of certain demanded books and records of the Defendant, a

Delaware LLC of which the Plaintiff is a member. Early in this action, the parties C.A. No. 2024-1130-SEM December 29, 2025 Page 2 of 10

stipulated to present this matter to me for a “final decision[,]” such that the parties

“waive[d] the right to seek further judicial review of [my] decision at the trial

level[,]” agreeing that my decision would be “subject to direct appeal to the

Delaware Supreme Court[.]”1

This action was tried in April 2025 and I issued my post-trial decision in May

2025, holding that the Plaintiff was entitled to a court-ordered production of

documents responsive to Requests 1 through 7, and 9, as defined and further

explained in that report.2 Notably, I found the Defendant had agreed to voluntarily

produce records responsive to Requests 1-2 and 5-7 (the “Phase One Production”)

and I held the Defendant to that agreement. For Requests 3-4 and 9 (the “Phase Two

Production”), I overruled the Defendant’s objections and ordered production.

At my direction, the parties drafted and submitted a proposed final

implementing order. In pertinent part, the proposed order set forth two stages for

production. First, the Phase One Production would be completed with 10 days of the

final order. Second, the Phase Two Production would be completed within 30 days

of the final order. That second step was expressly subject to an appeal and the parties

1 Docket Item (“D.I.”) 35. 2 D.I. 56. C.A. No. 2024-1130-SEM December 29, 2025 Page 3 of 10

agreed that the Phase Two Production deadline would be stayed pending resolution

of any appeal. I granted the proposed order on June 11, 2025 (the “Final Order”).

The Final Order triggered a few deadlines. The first was for the Phase One

Production, which was due within 10 days, or by June 25, 2025. 3 The Defendant did

not make the Phase One Production by that deadline. Then, within the same 30-day

window, any party could appeal my decision, and the Defendant (absent timely

appeal) was required to complete the Phase Two Production. On July 11, 2025, the

final day within that 30-day window, the Defendant timely noticed an appeal, staying

the Phase Two Production.

After that appeal, the Defendant’s counsel moved to withdraw at this and the

appellate level. Those motions were granted, and both courts warned the Defendant

that it could not represent itself pro se and that there were serious consequences if it

failed to secure successor counsel. The Defendant did not heed those warnings; the

Supreme Court thus dismissed its appeal, and I ultimately held the Defendant in

contempt, sanctioned it, and appointed the Receiver to take over production efforts.

That contempt and appointment are at issue in the Motion. Briefly, and as

reflected on the docket, when the Defendant missed the June 25 deadline for the

3 See Ct. Ch. R. 6 (a)(1)(B) (“Exclude intermediate Saturdays, Sundays, and legal holidays when the period is less than 11 days.”). C.A. No. 2024-1130-SEM December 29, 2025 Page 4 of 10

Phase One Production, the Plaintiff moved for contempt and sanctions. I granted that

motion on September 5, 2025. To coerce compliance, I began with a daily fine of

$1,000.00, accruing from September 6, 2025 until production was complete or

September 12, at the latest. In doing so, I effectively gave the Defendant an extended

deadline, explaining: “This extended one-week deadline balances the Plaintiff’s

genuine interest in prompt production against the risk of imposing unnecessarily

severe monetary sanctions or jumping too quickly to the extreme remedy of a

receiver.”

I went on to explain, however, “[i]f the Defendant does not rectify its

contempt and produce the records by September 12, 2025, . . . I will be left with no

other option.” If the Phase One Production was still outstanding by that date (more

than 2 months after the original deadline), I warned that I would appoint a receiver

to take over the Defendant’s production efforts. The Defendant did not complete the

Phase One Production by September 12, and I appointed the Receiver on September

18, disregarding attempted filings from the Defendant’s non-attorney controller.

II. The Motion

More than three months after its original counsel was permitted to withdraw,

new counsel entered an appearance for the Defendant and has moved for relief. In

the Motion, filed on October 27, 2025, the Defendant argues that my September 18 C.A. No. 2024-1130-SEM December 29, 2025 Page 5 of 10

appointment of the Receiver was premised on a mistake of fact and should be

rescinded because there was no need for a receiver to take over the Defendant’s

production efforts. Even accepting the Defendant’s factual record, I disagree that

relief is warranted. The Motion is denied.

The Defendant moves for relief under Court of Chancery Rule 60(b), which

states in relevant part: “On motion and upon such terms as are just, the Court may

relieve a party . . . from a final judgment, order, or proceeding for the following

reasons: (1) Mistake, inadvertence, surprise, or excusable neglect; … or (6) any other

reason justifying relief from operation of the judgment.” Ct. Ch. R. 60(b)(1), (6).

“There are two significant values implicated by Rule 60(b). The first is

ensuring the integrity of the judicial process and the second, countervailing,

consideration is the finality of judgments. Because of the significant interest in

preserving the finality of judgments, Rule 60(b) motions are not to be taken lightly

or easily granted. A proper standard must strike a balance between the interest in

bringing litigation to an end and the countervailing concern that justice is carried

out.”4 I attempt to strike that balance as I review both prongs of the Defendant’s

argument.

4 MCA, Inc. v. Matsushita Elec. Indus. Co., Ltd., 785 A.2d 625, 634–35 (Del. 2001). C.A. No. 2024-1130-SEM December 29, 2025 Page 6 of 10

First, the Defendant argues I made an “erroneous conclusion of fact” when I

concluded the Phase One Production was not completed, and relying thereon,

appointed the Receiver. In so arguing, the Defendant makes much of my decision to

Free access — add to your briefcase to read the full text and ask questions with AI

Justin Cornett v. Collectable Sports Assets, LLC, (Del. Ct. App. 2025).

Justin Cornett v. Collectable Sports Assets, LLC (Justin Cornett v. Collectable Sports Assets, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

MCA, Inc. v. Matsushita Electric Industrial Co.
785 A.2d 625 (Supreme Court of Delaware, 2001)