Justice v. Booten

110 S.W.2d 1094, 270 Ky. 812, 1937 Ky. LEXIS 169
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedDecember 3, 1937
StatusPublished

This text of 110 S.W.2d 1094 (Justice v. Booten) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Justice v. Booten, 110 S.W.2d 1094, 270 Ky. 812, 1937 Ky. LEXIS 169 (Ky. 1937).

Opinion

Opinion op the Court by

Judge Perry

Affirming.

In January, 1932, Pike county, acting through its duly appointed building commission, composed of the county judge and other officials, contracted with the appellants, Joe H. Justice and A. S. Johnson, partners, doing business under the name of Joe H. Justice Building Company, hereinafter, for the sake of brevity, referred to as the appellant company, to remodel and enlarge the Pike county courthouse, according to certain plans and specifications, for an agreed price of $87,300, subject, however, to the commission’s right to alter same by its later making changes therein, or additions thereto, and paying the compensation therefor which might be agreed upon between the contractors and the building commission.

Pursuant to such understanding and working plan, including the changes and additions thereunder made, the contracted remodeling and enlargement of the courthouse was finally completed in June, 1933, when the de *813 fendants (here appellants) claim they were paid on final settlement had with the county therefor the sum of $100,633.21 or $13,333.21 more than the original price, which was found due and allowed them for the various changes and additions made to the original plans and specifications, which required both extra work and materials for carrying them out.

After the appellant company had secured this building contract, they advertised for bids of subcontractors to do certain portions of the work.

For the roofing and sheet metal work required on the cornice and tower of the courthouse the appellee was awarded the subcontract at an agreed price, under the original plans and specifications, of $3,000, by the terms of which he was to furnish both the materials and labor required therefor.

The record discloses that, after the making of this subcontract by the appellee (plaintiff below), various alterations and additions were made to the original plans by the building commission, as to this roofing work, which called for much additional work and more expensive goofing material to be done and furnished by the appellee, embracing (among other minor changes) a change in the character of roofing, from slate to the more expensive type of tile roofing, on a portion of the roof; the heightening of the tower on the courthouse by an additional 15 foot section; also the reroofing of an old portion of the courthouse with material composed of different layers not called for by the original plan.

Plaintiff claims that, because of these changes made in the original plans, he was required to furnish much additional and costly material of such character that its installation was very complicated, and required his employment of very expensive and highly skilled labor; also that the clock tower called for by the original plans was to be of similar dimensions with those of the old one then on the courthouse, but only changed in being differently located, and that the framework of such a tower he was to cover had already been erected when the building' commission decided that so small a tower would not harmonize with the dignity and size of the new building, and that its height should be raised by adding an entirely new section, approximately 15 feet high, and its base dimensions also increased.

On account of the extra materials and extra *814 amount and class of labor called for by reason of these innovations and changes made in the original plans and ¡specifications, this controversy over the extra compensation owing therefor by the contractors to the appellee, subcontractor, has arisen.

The latter claims that he has by these changes, been called upon to furnish extra material and labor to the amount of $3,046.10, over and above the contract price of $3,000 agreed upon with the appellant company for furnishing the materials and doing the roofing work called for by the original plans and specifications, and that there was due him for his labor and materials furnished by him in performing both agreements a total of $6,046.10, upon which total amount he had been paid or received from the appellant only $3,755.48, leaving a balance owing him thereon of $2,290.62. The appellant company having failed to pay or settle with him therefor, he brought this action for recovery of this amount, allegedly owing, with interest, and asked that the cause be referred to the master commissioner for an accounting between him, the plaintiff, and the defendant company and that he have judgment against the defendants, Justice and Johnson, and each of them for the sum stated and interest.

To the petition, asking such relief, the defendants filed answer and counterclaim, whereby they first denied each of the several itemized claims therein, allegedly owing for extra work and material furnished on the building by appellee, as subcontractor, and further affirmatively pleaded, by way of counterclaim, that the appellee had breached the terms of the roofing contract, in that he had therein agreed to complete the same within 60 days after its making, but had failed to do so; that he had quit the job entirely in January, 1933, and refused to proceed any further with carrying it out; that his needless delay and inattention to the performance of his contract had resulted in both delaying and ■damaging their work and that of the other subcontractors, and by reason of which things they counterclaimed for damages thereby caused them in a total sum of $3,000, and, 'further, they denied'that they had paid plaintiff upon his claim of $6,046.10 for extra work and materials furnished and for those furnished under his original contract only the amount of $3,755.48, but had, .in fact, paid him thereon the sum of $4,442.48.

*815 A reply, denying these matters of counterclaim, completed the issues, when the case was referred to the master commissioner for the hearing of proof upon them, who thereafter made a report of his findings based upon the pleadings and evidence so heard, wherein he found there remained owing and unpaid plaintiff on the amount earned the sum of $1,595.38, and that the defendants’ counterclaim for damages was not supported by the proof, and recommended that the plaintiff recover judgment against the appellant company for $1,595.38, with interest.

Exceptions to the report were filed by both parties. Upon the later submission and hearing of these exceptions by the court, those filed by plaintiff were withdrawn and the cause heard only upon the exceptions of the defendants, when it was adjudged that the report of the commissioner be sustained as to each of its findings, and that the plaintiff recover the sum recommended, of $1,595.38, with interest from January 20, 1933, until paid.

From this judgment this appeal is prosecuted.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
110 S.W.2d 1094, 270 Ky. 812, 1937 Ky. LEXIS 169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/justice-v-booten-kyctapphigh-1937.