JUPITER ENVIRONMENTAL SERVICES, INC. VS. WALLACE BROS. INC. (L-0413-17, OCEAN COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided April 9, 2020·No. A-3981-18T3·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-3981-18T3

JUPITER ENVIRONMENTAL SERVICES, INC.,

Plaintiff-Respondent/

Cross-Appellant,

v.

WALLACE BROS., INC., and LIBERTY MUTUAL INSURANCE COMPANY,

Defendants-Appellants/

Cross-Respondents.

Argued telephonically March 18, 2020 – Decided April 9, 2020

Before Judges Fuentes, Haas and Enright.

On appeal from the Superior Court of New Jersey, Law Division, Ocean County, Docket No. L-0413-17.

Patrick Thomas Murray, III, argued the cause for appellants/cross-respondents (Peckar & Abramson, PC, attorneys; Patrick Thomas Murray, III, on the briefs).

Matthew David Lakind argued the cause for respondent/cross-appellant (Tesser & Cohen, attorneys;

Matthew David Lakind, on the briefs).

PER CURIAM In this breach of contract case involving the installation of windows at eight public schools, defendants Wallace Bros., Inc. (Wallace) and its insurer Liberty Mutual Insurance Company appeal from the Law Division's April 2, 2019 order entering judgment in favor of plaintiff Jupiter Environmental Services, Inc. (Jupiter). Wallace contends that the court erred by finding that it breached its contract with Jupiter, and requiring Wallace to pay Jupiter its lost profits and overhead, plus interest, on two school projects for which Jupiter performed no work after Wallace deleted these schools from the contract pursuant to one of its provisions. Wallace also argues that the court erred by imposing interest upon a different portion of the judgment under the Prompt Payment Act (PPA), N.J.S.A. 2A:30A-1 to -2.

Jupiter has filed a cross-appeal from the same judgment, and argues that the court should have awarded it additional damages for a third school that was deleted from the contract, together with attorney's fees under the PPA. Jupiter also asserts that the court miscalculated the amount of lost profits and overhead

A-3981-18T3

due it, as well as the amount Wallace owed Jupiter for the completion of a fourth project.

Having reviewed the parties' contentions in light of the record and applicable law, we affirm the judgment in part, reverse it in part, and remand for the entry of a new judgment.

I.

The parties are fully familiar with the lengthy procedural history and facts of this matter. Therefore, we need only recite the most salient facts here.1 Wallace was the general contractor on a construction project to renovate eight public schools for the Brick Township Board of Education (Brick). As part of its duties as the general contractor, Wallace was responsible for removing and replacing windows at each of the schools. Brick and Wallace believed there was asbestos in all of the windows and, therefore, Wallace was required to safely remove this hazardous material from the schools.

Because Wallace was not qualified to remove asbestos, it subcontracted with Jupiter, an environmental/asbestos removal contractor, to perform the

1 These facts were developed at a three-day bench trial. The only witnesses at the trial were Jupiter's vice-president, Pane Repic, and Wallace's president, Steven Wallace. To avoid confusion between Wallace, the company, and its president, we hereafter refer to Mr. Wallace as Steven. In doing so, we intend no disrespect.

A-3981-18T3

asbestos abatement aspect of the project. The parties agreed that after Wallace and its other subcontractors took out the windows, Jupiter would take them from the schools, and later remove the asbestos at its shop.

Jupiter's bid on the subcontract was broken out with separate prices for each of the schools. There were eight sets of plans, eight sets of drawings, eight scheduled start and completion dates, and eight abatement management plans. After some preliminary negotiations, Wallace accepted Jupiter's offer to complete all the asbestos removal work for $425,000. During the negotiations, the parties learned that the windows in two of the schools, Lake Riviera Middle School (Lake Riviera) and Midstream Elementary School (Midstream) , might not contain any asbestos. Thus, they agreed that if asbestos was found and needed to be abated, Jupiter would be entitled to an additional $35,000 for this work.

Of particular importance to the issues involved in these appeals, Section 5.2 of the subcontract allowed Wallace to reduce or add to Jupiter's scope of work in any manner and for any reason. Section 5.2 stated:

The Subcontractor may be ordered in writing by the Contractor, without invalidating this Subcontract, to make changes in the Work within the general scope of this Subcontract consisting of additions, deletions or other revisions, including those required by Modifications to the Prime Contract issued subsequent

A-3981-18T3

to the execution of this Agreement, the Subcontract Sum and the Subcontract Time being adjusted accordingly. The Subcontractor, prior to the commencement of such changed or revised Work, shall submit promptly to the Contractor written copies of a claim for adjustment to the Subcontract Sum and Subcontract Time for such revised Work in a manner consistent with requirements of the Subcontract Documents.

[(emphasis added).]

Work on the project began in October 2015. A scheduling problem soon developed at the Osbornville Elementary School 2 (Osbornville). Brick wanted the work to be completed during the winter break so as not to interfere with the kindergarten to grade four students who attended the school. Jupiter notified Wallace that it could not meet this schedule.

Accordingly, Wallace invoked Section 5.2 of the subcontract and deleted Osbornville from the project. Wallace then made arrangements with Brick's design professionals permitting it to encapsulate the asbestos, rather than remove it, and Wallace was able to complete the Osbornville project on its own.

2 In their respective briefs, the parties provide different spellings of the name of this school. Wallace refers to it as the "Osborneville Elementary School," while Jupiter states it is the "Osberneville Elementary School." We refer to this institution by the name listed on Brick's website, which is the "Osbornville Elementary School." http://www.brickschools.org/Schools/Osbornville-ES (last visited Mar. 22, 2020).

A-3981-18T3

In February 2016, testing reports at Lake Riviera and Midstream confirmed there was no asbestos in the windows at either school. Because Wallace no longer needed an asbestos removal expert like Jupiter to remove the windows and asbestos at these schools, it removed them from the subcontract pursuant to Section 5.2.

Jupiter completed the asbestos removal work needed at the five remaining schools. At the end of the project, Wallace calculated that it owed Jupiter $54,184.50 for its work at the Lanes Mill Elementary School (Lanes Mill). However, Jupiter demanded that Wallace pay it approximately $190,000, which included payment for the Osbornville, Lake Riviera, and Midstream schools that had been deleted from the subcontract. Because the parties remained at loggerheads, they participated in mediation to attempt to resolve the dispute, but they were not successful. Jupiter subsequently commenced this breach of contract action.

Following the trial, the judge concluded that Wallace did not owe Jupiter anything on the Osbornville project because Wallace deleted this school from the subcontract pursuant to Section 5.2 and Jupiter performed no work on it. In so ruling, however, the judge determined that contrary to the clear language of Section 5.2 that permitted the contractor to modify the subcontract for any

A-3981-18T3

Free access — add to your briefcase to read the full text and ask questions with AI

JUPITER ENVIRONMENTAL SERVICES, INC. VS. WALLACE BROS. INC. (L-0413-17, OCEAN COUNTY AND STATEWIDE), (N.J. Ct. App. 2020).

JUPITER ENVIRONMENTAL SERVICES, INC. VS. WALLACE BROS. INC. (L-0413-17, OCEAN COUNTY AND STATEWIDE) (JUPITER ENVIRONMENTAL SERVICES, INC. VS. WALLACE BROS. INC. (L-0413-17, OCEAN COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brundage v. Estate of Carambio
951 A.2d 947 (Supreme Court of New Jersey, 2008)
Commercial Realty & Resources Corp. v. First Atlantic Properties Co.
585 A.2d 928 (Supreme Court of New Jersey, 1991)
State v. Dancyger
143 A.2d 753 (New Jersey Superior Court App Division, 1958)
First Atlantic Federal Credit Union v. Perez
918 A.2d 666 (New Jersey Superior Court App Division, 2007)
Cesare v. Cesare
713 A.2d 390 (Supreme Court of New Jersey, 1998)
Kampf v. Franklin Life Insurance
161 A.2d 717 (Supreme Court of New Jersey, 1960)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
Conway v. 287 Corporate Center Associates
901 A.2d 341 (Supreme Court of New Jersey, 2006)
In Re Malone
886 A.2d 181 (New Jersey Superior Court App Division, 2005)
State, Dept. of Environ. Protect. v. Ventron Corp.
468 A.2d 150 (Supreme Court of New Jersey, 1983)
Karl's Sales & Serv., Inc. v. Gimbel Bros., Inc.
592 A.2d 647 (New Jersey Superior Court App Division, 1991)
James v. Federal Insurance Co.
73 A.2d 720 (Supreme Court of New Jersey, 1950)
Van Horn v. City of Trenton
404 A.2d 615 (Supreme Court of New Jersey, 1979)
Kieffer v. Best Buy
14 A.3d 737 (Supreme Court of New Jersey, 2011)
Seidman v. Clifton Savings Bank
14 A.3d 36 (Supreme Court of New Jersey, 2011)
Cumberland Farms, Inc. v. New Jersey
148 A.3d 767 (New Jersey Superior Court App Division, 2016)
Fastenberg v. Prudential Insurance
707 A.2d 209 (New Jersey Superior Court App Division, 1998)
State v. Heisler
29 A.3d 320 (New Jersey Superior Court App Division, 2011)
Kupfersmith v. Delaware Insurance
86 A. 399 (Supreme Court of New Jersey, 1913)