Jupiter Energy Corp. v. Federal Energy Regulatory Commission

407 F.3d 346, 166 Oil & Gas Rep. 388, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20080, 2005 U.S. App. LEXIS 5952
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 12, 2005
Docket04-60041
StatusPublished
Cited by11 cases

This text of 407 F.3d 346 (Jupiter Energy Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jupiter Energy Corp. v. Federal Energy Regulatory Commission, 407 F.3d 346, 166 Oil & Gas Rep. 388, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20080, 2005 U.S. App. LEXIS 5952 (5th Cir. 2005).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

Jupiter Energy Corporation petitions this Court for review of the Federal Energy Regulatory Commission’s determination that Jupiter’s two pipelines perform a “transportation” function rather than a “gathering” function, thereby subjecting them to the Commission’s jurisdiction under Section 1(b) of the Natural Gas Act. 1 We grant the petition, vacate the Commission’s decision, and remand.

I

Jupiter owns and operates two natural gas pipelines in the Gulf of Mexico. Both pipelines originate at “Platform 39A,” which is owned by Jupiter’s parent corporation, Union Oil Company of California. The Jupiter system is located roughly 10 miles offshore from Louisiana in about 40 feet of water. The first Jupiter pipeline (the “8-inch line”) is roughly eight inches in diameter and is 3.2 miles long. It heads from Platform 39A and, before reaching the shoreline, feeds into a pipeline owned by Transcontinental Gas Pipe Line Corporation (“Transco”). The Transco line is a lateral line ranging from 12 to 24 inches in diameter and running parallel to the shore *348 at the point of connection with the 8-inch line. The second Jupiter pipeline (the “10-inch line”) is roughly ten inches in diameter and is 10.2 miles long. It runs from Platform 39A (via an abandoned platform) to a land-based pipeline on the shore owned by Tennessee Gas Transmission Company. Platform 39A is itself downstream from other pipelines. Gas arrives at Platform 39A from 16 wells via non-jurisdictional Unocal facilities: ten platforms and several pipelines ranging from four to eight inches in diameter.

In 1966, the Commission’s predecessor, the Federal Power Commission (“FPC”), determined that Jupiter provided gas “transportation” services. That classification was carried on by the Commission, thereby subjecting Jupiter to the Commission’s jurisdiction. On November 4, 2002, Jupiter requested that the Commission change the status of its pipelines from jurisdictional to non-jurisdictional — that is, that the Commission determine that Jupiter is engaged in “gathering” rather than “transportation” of natural gas. The Commission unanimously denied this request, and denied rehearing by a 2-1 vote. Jupiter now seeks our review.

II

Section 1(b) of the Natural Gas Act governs “the transportation of natural gas in interstate commerce.” 2 In Section 1(b), Congress “not only prescribed the intended reach of the Commission’s power, but also specified the areas into which this power was not to extend.” 3 This Section expressly exempts from the Commission’s jurisdiction the “production” or “gathering” of natural gas. 4 However, “[exceptions to the primary grant of jurisdiction in [Section 1(b)] are to be strictly construed,” 5 and the terms “production” and “gathering” are to be “narrowly confined to the physical acts of drawing the gas from the earth and preparing it for the first stages of distribution.” 6

The Commission employs a multi-factor “primary function” test developed in the Farmland Industries case. 7 Under this test, “the Commission determines whether, with reference to the specific facts and circumstances of the particular facility in question, its primary function is gathering.” 8 The test, which has continued to evolve, currently employs both physical and non-physical factors. The physical factors include:

(1) the facility’s length and diameter, (2) the extension of the facility beyond the central point in the producing field, (3) the facility’s geographic configuration, (4) the placement of compressors and processing plants, (5) the location of wells along all or part of the facility, and (6) operating pressures. 9

*349 The non-physical factors are “the purpose, location, and operation of the facility, the general business activity of the owner of the facility, and whether the jurisdictional determination is consistent with the objectives of the NGA and Natural Gas Policy Act.” 10 The Commission “do[es] not consider any single factor to be determinative and recognize[s] that all factors do not necessarily apply in all situations.” 11

In 1990, in Amerada Hess Corporation, the Commission modified the primary function test with respect to offshore facilities by applying “a sliding scale which will allow the use of gathering pipelines of increasing lengths and diameters in correlation to the distance from shore and the water depth of the offshore production area” based on the observation that as a result of “recent advances in engineering and available technology, offshore drilling operations continue to move further offshore and further from existing interstate pipeline interconnections.” 12 Following our 1997 decision in Sea Robin Pipeline Co. v. FERC, 13 the Commission again modified the test with respect to offshore facilities by

(1) adopting an additional analytical element applicable to systems that contain a centralized aggregation point; (2) adjusting the weight to be afforded the “behind-the-plant” criterion so that the location of processing plants is not necessarily determinative and can be outweighed by other factors; and (3) focusing primarily on physical factors. 14

The primary function test, as thus modified, was subsequently upheld. 15

Ill

A

Under the Administrative Procedure Act, an agency determination shall be set aside if it is “arbitrary, capricious, an abuse of discretion or otherwise not in accordance with law.” 16 “The fundamental precept that permits this deferential standard of review is that ‘an agency must cogently explain why it has exercised its discretion in a given manner’ and ‘must supply a reasoned analysis’ for any departure from other agency decisions.” 17 However, “a court is not to substitute its judgment for that of the agency” or “supply a reasoned basis for the agency’s action that the agency itself has not given.” 18

*350 B

Jupiter argues that the Commission’s decision — that Jupiter’s system is trans-portational — is arbitrary and capricious because one of its pipelines is upstream from a gathering pipeline.

Related

MD Anderson v. HHS
Fifth Circuit, 2021
Stage Stores, Inc. v. Jon Gunnerson
477 S.W.3d 848 (Court of Appeals of Texas, 2015)
Hornbeck Offshore Services, L.L.C. v. Salazar
713 F.3d 787 (Fifth Circuit, 2013)
Calhoun v. FCI Warden Texarkana
224 F. App'x 333 (Fifth Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
407 F.3d 346, 166 Oil & Gas Rep. 388, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20080, 2005 U.S. App. LEXIS 5952, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jupiter-energy-corp-v-federal-energy-regulatory-commission-ca5-2005.