Julius Kayser & Co. v. Textron Inc.

132 F. Supp. 49, 1955 U.S. Dist. LEXIS 2988
CourtDistrict Court, W.D. South Carolina
DecidedMay 23, 1955
DocketCiv. A. No. 1600
StatusPublished
Cited by2 cases

This text of 132 F. Supp. 49 (Julius Kayser & Co. v. Textron Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Julius Kayser & Co. v. Textron Inc., 132 F. Supp. 49, 1955 U.S. Dist. LEXIS 2988 (southcarolinawd 1955).

Opinion

WYCHE, Chief Judge.

This case, for alleged breach of contract, was tried by me without a jury at the November term of the court at Anderson, South Carolina, on oral testimony and written exhibits which were introduced by stipulation and without objection. Two depositions which had been taken in New- York, one of Royal Little and W. D. Mewhort taken on motion of plaintiff, and the other of R. C. Kramer, taken on motion of defendant,were introduced, without objection.

The complaint is for the breach of an alleged contract between plaintiff and defendant which it alleges the defendant refused to perform to plaintiff’s damage in the sum of $80,000.

The answer pleads, for a first defense, that there was no contract in that the parties never agreed on some of the terms of the alleged agreement arid that [50]*50there was, therefore, no meeting of the minds of the parties on the agreement. It pleads, for a second defense, that the alleged contract was within the terms of the Statute of Frauds as incorporated in Section 11-101 of the Code of Laws of South Carolina, 1952, in that it is a contract or sale of lands or an interest in or concerning land and that there was no memorandum or note thereof in writing signed by the party sought to be charged therewith or some person thereunto lawfully authorized, and, therefore, no action can be maintained thereon.

The factual situation is involved and it will be helpful in stating the findings of fact to give here the following background of undisputed facts out of which the controversy arose. For convenience, the plaintiff will be hereafter sometimes called Kayser, and the defendant, Tex-tron.

In the early part of 1952, Kayser had •erected at Liberty, South Carolina, an industrial building designed to be used as .a plant for dyeing and finishing full-fashioned hosiery. The cost of erecting the building'was approximately $630,000. ■On July 25, 1952, Kayser conveyed this building to the Lincoln National Life Insurance Company for a consideration of .$665,000, and simultaneously with the delivery of the deed, the insurance company leased the land and building to Kayser under a written contract of lease for .an initial term of fifteen years, beginning August 1, 1952, with the option to the lessee of five additional five-year terms .after the expiration of the initial term. The initial term of the lease ended the :31st day of July, 1967, and the annual rental for the fifteen-year term was $61,-092.48. The rental for the extended terms, if the options therefor were exercised, was to be at a lesser rate. At the beginning of the term of the lease, Kayser installed a certain amount of machinery and equipment in the leased building and began partial operation of the finishing plant with a small force. Kayser shortly thereafter, for certain business reasons, decided to abandon the plant as a finishing plant, and although a certain amount of machinery was maintained therein, and some small operations of the machinery were carried on, at times, until the autumn of the year 1953, it was then completely closed down.

On July 8, 1953, R. C. Kramer, the Chairman of the Board of Kayser, and Royal Little, the Chairman of the Board of Textron, met in the office of Kramer in New York, to negotiate the terms of an agreement whereby Kayser would assign its lease of the building to Textron and Textron would assume the lease and the obligations thereunder to pay the annual rental to the lessor and also to pay insurance premiums and property taxes on the leased property.

The parties agreed on certain terms of the proposed contract and that a memorandum of these terms which Kramer had originally written down in pencil was to be sent to T. Frank Watkins of the law firm of Watkins & Watkins, in Anderson, South Carolina, as a basis for his preparing a written contract, setting out the obligations of the parties. This was done upon the assumption that Watkins was local counsel of both companies. Kramer learned a short while later that while Watkins represented Textron and another company in which Kramer was an officer, the firm of Haynsworth & Haynsworth of Greenville, South Carolina, was the attorney for Kayser in South Carolina. Whereupon, Kramer advised Watkins that Haynsworth & Haynsworth would represent ■ Kayser’s interest in preparing the contract and the two firms should collaborate.

In the negotiations on July 8, 1953, Little took the position that by assuming this lease, Textron would in reality be buying the plant since the total rent for the first fifteen-year term would amortize the cost of the building to the insurance company, with interest. He further contended that the building was more expensively built than Textron would have built it. Both of the negotiators knew that Textron proposed to use the building to house a tricot manufacturing plant. Little stated that the con[51]*51tractor which had erected the building could and would build for Textron a satisfactory plant of the same size and capacity for $130,000 less than the building had cost Kayser because Textron did not need certain expensive features such as tiled walls, extravagant offices and excess water capacity'which the building contained.

Little calculated that the plant he could have built would not cost more than $500,000 and that this cost with interest would be amortized by the payment of the annual rent of $61,092.48 for the portion of the term remaining after September 1, 1954. Upon Kramer calling to his attention that the rent was calculated on an interest rate of 4% per cent, which was one-half of one per cent less than Textron could finance another building for, Little agreed that Textron would begin paying the rent five months earlier, i. e., on April 1, 1954, in view of this favorable interest rate. Kramer first proposed that rental payments start January 1, 1954, but they finally agreed on April 1, 1954, as the starting date for Textron to pay the rent. Little had stated that Textron could not begin operations in the building prior to April 1, 1954, since it would have to acquire machinery, and an estimated four-months time would be required to make the necessary changes in the electrical system and the air conditioning and to set up the tricot manufacturing machinery which he proposed to install in the building.

At this point in the negotiations, Kramer stated that it would not be fair to Kayser if Textron should begin the “use” of the building prior to April 1, 1954, and that if Textron’s plans were changed so that it could begin the use of the building prior to April 1, Textron should pay the prorata rent from the time it began to use the building. Little testified that he agreed that if Textron should use the building for manufacturing operations prior to April 1, Textron would pay the rent from the beginning of such prior operations on a prorata basis.

Kramer’s memorandum on this point provided that Textron would pay the rent accruing after April 1, 1954, and in case of “earlier occupancy”, it should pay the rent from the date of such earlier occupancy. Little testified that in view of what they had both said, he understood the term earlier occupancy to mean earlier occupancy for operation of the plant and, as he understood the agreement, that Textron could enter the plant to prepare it for its new and changed use prior to April 1, without being liable to pay the prorata rent for this term of preparation for use.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meyer v. Meyer
952 So. 2d 384 (Court of Civil Appeals of Alabama, 2006)
Julius Kayser & Co. v. Textron, Incorporated
228 F.2d 783 (Fourth Circuit, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
132 F. Supp. 49, 1955 U.S. Dist. LEXIS 2988, Counsel Stack Legal Research, https://law.counselstack.com/opinion/julius-kayser-co-v-textron-inc-southcarolinawd-1955.