Julius Jonson's Sons v. Buellesbach

119 N.Y.S. 839
CourtAppellate Terms of the Supreme Court of New York
DecidedNovember 30, 1909
StatusPublished

This text of 119 N.Y.S. 839 (Julius Jonson's Sons v. Buellesbach) is published on Counsel Stack Legal Research, covering Appellate Terms of the Supreme Court of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Julius Jonson's Sons v. Buellesbach, 119 N.Y.S. 839 (N.Y. Ct. App. 1909).

Opinion

LEHMAN, J.

The plaintiff sues the maker and the indorser of a note note was. delivered only as security upon a contract for the purchase of iron bases and columns, and that the plaintiff never complied with the contract or furnished the iron. The indorser, Caspar Buellesbach, also-counterclaimed against the plaintiff, alleging that the plaintiff neglected, to make deliveries of the iron as required by the contract, and that—

“this defendant was under contract with the owner of said premises, No. 157-159 West Eighteenth street, Borough of Manhattan, to erect said iron columns, and bases that had been ordered from the plaintiffs, and to complete said erection by the 15th day of November, 1906, and the plaintiffs were duly informed by this defendant of that fact, and that this defendant would suffer by any serious delay in the delivery of said iron toward said building, but wholly owing to the neglect of the plaintiffs, this defendant was unable to complete his contract for the construction of said iron upon said buildings, and thereby forfeited his contract with said owner and suffered damages by being charged with the same by reason of his breach of contract with the said owner, and by reason, also, of his loss of profits which would have accrued if he had not been prevented from fulfilling the said contract by reason of plaintiff’s neglect, in all exceeding the sum of $2,000.”

[841]*841At the trial it clearly appeared that the promissory note was given, not as security, but as part payment under the contract, and the trial justice properly directed a verdict against the maker for the amount of his note, with interest.

The appeal from the direction of this verdict appears to me to be-without merit. It seems to me, however, that the trial justice was in error in his rulings in regard to the indorser’s counterclaim. At the-outset the plaintiff raised the question whether the defendant under his pleadings could show any special damages. The trial justice stated' that in his opinion the special damage was not sufficiently pleaded, but that he would admit testimony subject to be stricken out thereafter. The defendant then presented evidence tending to show that before-he made the contract with the -plaintiff he told the plaintiff that he had or was about to obtain a contract for the erection of the structural-work in a building in West Eighteenth street, and that the building had’ to be finished by November 15th; that he repeated this conversation when he signed the contract with the plaintiff; that the plaintiff unreasonably delayed his deliveries, and the defendant could not complete his contract by November 15th, and it was taken away from him on that day; that his contract was for the price of $7,500 and about $900,. or 12 per cent, of the cost price, was figured as profit; and that the cost of the materials was figured at about $1,400, and about $450 was expended for labor. At the close of the trial the plaintiff moved to-strike out all evidence in regard to the counterclaim, and for the direction of a verdict. The court then denied the motion except that it struck “out all the evidence received under the stipulation, so far as it can in any way relate to the counterclaim for loss of profit, or for loss-of expenditure on the building contracted for,” and further held that “the only question open in this case is whether or not there should be any allowance made against this plaintiff because of failure to perform the contract.” The trial justice then charged the jury as follows:

“There is a conflict in the evidence with respect to the time when the detail for the second tier of columns was received. The defendant’s testimony is to the effect -that the detail was delivered in the latter part of September— I think the 27th or 2Sth, the witness stated. The plaintiff’s testimony is that that detail was not delivered until the middle of October. It appears that the first delivery after the receipt of the detail for the second tier of beams was made by the plaintiff on the 14th of November, and at that time the contract with Mr. Buellesbach and the owners of the building had not been terminated ; and it does appear that subsequently the contract was terminated, and Mr. Buellesbach’s claim is that it was terminated because of the delay in furnishing him with the columns for the second tier.
“The question in this case which I ask you to determine is whether or not, after you fix the time when the detail was received by the plaintiff, if the plaintiff attempted to perform his contract and did within a reasonable time commence to make delivery of the second tier of columns, taking into consideration the time when the detail was received, the character of the work to-be done, and taking all the evidence with respect to the amount of time necessary to make and deliver the goods called for by that detail, and then to say whether or mot the plaintiff did within a reasonable time after the receipt thereof commence to make deliveries. If he did, he did all that he was called' upon to do, and there can be no allowance to the defendant.
“If, on the other hand, there was a delay beyond a reasonable time for the delivery of these columns, and by reason of that delay this contract was lost to the defendant, then all that the plaintiff should have in this case would be [842]*842the sum of money which would represent actually the amount of material he delivered under this contract.”

The jury brought in a verdict for the plaintiff only for the amount . of iron delivered, and therefore, under the justice’s charge, they must have found that the plaintiff’s delay was unreasonable, and not caused , by the defendant’s failure to furnish the detail, and that by reason of the plaintiff’s delay the defendant lost his contract with the owner. In other words, if this judgment is affirmed, the defendant is not only deprived of his profits under his contract, but he is obliged to pay this plaintiff for goods furnished by it, even though these goods were of no benefit to the defendant, solely because of the plaintiff’s negligence.

If the trial justice considered this a case where the defendant could obtain only general damages, then the question whether the defendant lost his contract with the owner was immaterial, and should not have been submitted to the jury. The defendant has neither claimed nor proven any general damages, and, if this were the theory of his counterclaim, there was no question to submit to the jury. The trial justice has, however, apparently found that it was conclusively shown that the defendant had a contract with the owner, and that this contract was in the contemplation of the parties when they made the contract which is the subject of the counterclaim. The jury have found that by reason of the plaintiff’s negligence the defendant was deprived of the benefit of this contract. The loss which the defendant suffered thereby was, therefore, a natural consequence of the plaintiff’s neglect, for which he is liable, and which the defendant has a right to show if it is properly pleaded. Boughton v. Petigny, 72 App. Div. 76, 73 N. Y. Supp. 139, 76 N. Y. Supp. 125, and cases there cited.

The defendant has pleaded, not the contract to erect the iron work for the building, but only a contract to erect the iron bases and columns ordered from the plaintiff. He should, therefore, not be allowed to show his loss arising from a failure to carry out the larger contract ; but he must be allowed to show his entire loss arising from a failure to erect the iron bases and columns.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boughton v. Petigny
72 A.D. 76 (Appellate Division of the Supreme Court of New York, 1902)
Boughton v. Petigny
36 Misc. 209 (Appellate Terms of the Supreme Court of New York, 1901)
Boughton v. Petigny
76 N.Y.S. 125 (Appellate Division of the Supreme Court of New York, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
119 N.Y.S. 839, Counsel Stack Legal Research, https://law.counselstack.com/opinion/julius-jonsons-sons-v-buellesbach-nyappterm-1909.