Judge Development Corp & SW Corner LLC
This text of Judge Development Corp & SW Corner LLC (Judge Development Corp & SW Corner LLC) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
STATE OF VERMONT
ENVIRONMENTAL COURT
} In re: } Judge Development Corp. and SW Corner, LLC } Docket No. 189-9-05 Vtec Act 250 Permit Amendment Application } }
Decision and Order on Motion to Alter or Amend
Appellant-Applicants are represented by Eric M. Knudsen, Esq. and Erin M. Heins,
Esq.; the Land Use Panel of the Natural Resources Board is represented by John H. Hasen,
Esq.; the State of Vermont Division for Historic Preservation is represented by Julie
Kelliher, Esq. and John Kessler, Esq.; and the Town of Williston is represented by Paul S.
Gillies, Esq.
Appellant-Applicants Judge Development Corporation and SW Corner, LLC,
appealed from a decision of the District 4 Environmental Commission, denying their
application for an amendment of Act 250 Land Use Permit #4C0388-A-12 to relocate the
historic building known as the Blair House from its present location. The District
Commission had not reached the merits of the relocation application; rather, it decided that
the proposal did not meet the criteria for consideration of an amendment application
under former Environmental Board Rule (EBR) 34(E).
In this Court’s Decision and Order on Cross-Motions for Summary Judgment issued
on August 7, 2006, the Court determined first that the application must be analyzed under
EBR 34(E). In the summary judgment order the Court also then determined, under
subsection (1) of EBR 34(E), that the requirement at issue in the amendment application
(that the Blair House remain in its original location) was included in the 1985 Permit to
resolve a critical issue: “it is clear that leaving the main block of the Blair House in its
original location was critical to allowing the remainder of it (and its outbuildings) to be
1 removed.” In re: Judge Development Corp. and SW Corner, LLC, Docket No. 189-9-05
Vtec, slip op. at 7-8 (Vt. Envtl. Ct., August 7, 2006). The summary judgment order further
determined, under subsection (2) of EBR 34(E), that Appellants are not merely seeking to
relitigate or undermine the requirement that the Blair House remain in its original location.
The summary judgment order determined that material facts were disputed as to
whether finality outweighs flexibility in this particular case, under subsection (3) of EBR
34(E). After an evidentiary hearing and oral argument on the issue of whether, under
former Environmental Board Rule (EBR) 34(E)(3), Appellant-Applicants had met the
criteria for having the District Commission consider their amendment application on its
merits, the Court issued a ruling on an audio tape record.
The Division for Historic Preservation requested a written ruling including findings,
which the Court issued on March 22, 2007. That written decision and order incorporated
by reference the findings as to the building’s general location, history, and permit history
in the Decision and Order on Cross-Motions for Summary Judgment issued on August 7,
2006. That incorporation, as noted by the order, incorporated from the summary judgment
decision the conclusions that EBR 34(E) is applicable; that, under EBR 34(E)(1), the
requirement sought to be amended had been included in the 1985 Permit to resolve a
critical issue; and that under EBR 34(E)(2), Appellants were not merely seeking to relitigate
or undermine that requirement.
The March 2007 written order proceeded to state the Court’s findings supporting
the earlier ruling from the bench that in this particular case, under EBR 34(E)(3), flexibility
outweighs finality as to the contested requirement. In that order the Court rejected the
argument that the increase in development in the area in the twenty years since the
issuance of the permit should justify the consideration of the proposed amendment,
reasoning that such development was contemplated when the permit was issued.
The Court found in the March 2007 order that the significance of the building in the
2 historic preservation context was not in its setting, which had already been compromised
by the time the permit condition was imposed, but in its location with respect to the
roadways and the intersection. The Court found that the critical rationale for the contested
requirement was to allow the building to be capable of being “read” or perceived by the
traveling public as an historic inn building oriented towards the intersection, reflecting the
history of the intersection itself.
The Court went on to find that three elements affecting the building’s location in
relation to the intersection had changed since the permit was issued. First and most
importantly, the Court found that the roadway in front of the building had been widened
to add a right-turning lane for eastbound traffic turning to the south, which reduced the
distance between the roadway and the building, and made the bank between the roadway
and the building steeper.
The Court also found that the elevation of the land around the building had been
increased by the roadway construction and site work at the intersection, so that more of the
building’s foundation is covered and the building sits in a slight depression. Because the
Court also found that this aspect of the changes at the intersection was in part within
Appellant-Applicants’ control, the Court noted that this change in relative elevation by
itself was not persuasive. The Court also found that the trees around the building had
grown so large that they now obscure the building from the perception of the traveling
public from certain directions, especially in the summer.
The Court concluded, both in its ruling from the bench and in its written ruling of
March 22, 2007, that the present need for flexibility outweighs finality for the single reason
that “the relative location of the roadway to the building has changed in the time since the
issuance of the previous permit and was beyond the Appellant-Applicants’ control.” The
decision emphasized that this ruling was “specifically . . . NOT . . . due to the development
in the surrounding area” but rather that it was due to changes in the configuration of the
3 intersection that affect the reason for which the contested requirement was imposed. That
is, the Court concluded that flexibility outweighs finality so that the changes in the
intersection would be evaluated in light of the rationale for the contested requirement, to
determine if those changes prevent the building from being “read” or perceived by the
traveling public not only as an historic inn building, but as an historic inn building oriented
towards an historic intersection.
The March 22 ruling emphasized that it specifically did NOT make any
determination on the merits of the amendment application. Although some evidence was
presented on these issues, the Court specified that it was not then determining whether the
building needs to be moved in order to be preserved, either to the location for which
Appellants have applied or to any other location, and that it made no ruling on whether
the alternative preservation techniques presented in evidence (such as raising the building
up and improving the foundation or placing moisture barriers below it) would allow the
building to stay in its present location or whether continuing maintenance is feasible in that
location.
Rather, the Court stated that it is for the District Commission in the first instance to
Free access — add to your briefcase to read the full text and ask questions with AI
Cite This Page — Counsel Stack
Judge Development Corp & SW Corner LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/judge-development-corp-sw-corner-llc-vtsuperct-2007.