JT Properties of Mt Horeb, LLC v. American Transmission Company LLC

CourtCourt of Appeals of Wisconsin
DecidedMarch 27, 2025
Docket2023AP002322
StatusUnpublished

This text of JT Properties of Mt Horeb, LLC v. American Transmission Company LLC (JT Properties of Mt Horeb, LLC v. American Transmission Company LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JT Properties of Mt Horeb, LLC v. American Transmission Company LLC, (Wis. Ct. App. 2025).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. March 27, 2025 A party may file with the Supreme Court a Samuel A. Christensen petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2023AP2322 Cir. Ct. No. 2021CV2993

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT IV

JT PROPERTIES OF MT HOREB, LLC,

PLAINTIFF-APPELLANT,

V.

AMERICAN TRANSMISSION COMPANY LLC, ATC MANAGEMENT INC., AND DAIRYLAND POWER COOPERATIVE,

DEFENDANTS-RESPONDENTS.

APPEAL from a judgment of the circuit court for Dane County: STEPHEN E. EHLKE, Judge. Affirmed.

Before Blanchard, Graham, and Taylor, JJ.

Per curiam opinions may not be cited in any court of this state as precedent

or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3). No. 2023AP2322

¶1 PER CURIAM. JT Properties of Mt Horeb, LLC (“JT Properties”) appeals a judgment dismissing its challenge to American Transmission Company LLC, ATC Management, Inc., and Dairyland Power Cooperative (collectively, “ATC”) taking a high voltage transmission line easement on a portion of JT Properties’ land (“the Easement”). JT Properties argued that ATC’s taking of the Easement for this purpose rendered the remaining portion of JT Properties’ land an “uneconomic remnant,” as that term is defined in WIS. STAT. § 32.06(3m) (2023-24), and constituted an unnecessary taking because ATC took more rights than was necessary to accomplish the public purpose of providing electricity.1 Following pre-trial briefing, a three-day court trial, and post-trial briefing, the circuit court issued an oral ruling that rejected these claims. It determined that the taking of the Easement did not render the remainder of JT Properties’ land an uneconomic remnant and that the taking of the Easement was reasonably necessary for the public purpose of providing electricity.2 The court thereafter entered an Order for Judgment and Judgment dismissing JT Properties’ complaint. JT Properties appeals.

¶2 On appeal, JT Properties argues that the circuit court incorrectly applied the law in its uneconomic remnant determination because the court assumed that ATC would not exercise all of the rights that it had taken rather than

1 All references to the Wisconsin Statutes are to the 2023-24 version unless otherwise noted. 2 JT Properties’ complaint also raised the following claims: (1) ATC’s hazard tree rights granted in the Easement violated the statutory prohibition in WIS. STAT. § 182.017(7)(h); (2) other cases not involving JT Properties had nullified ATC’s right to acquire the Easement; and (3) ATC violated JT Properties’ Fourteenth Amendment rights as protected by the United States Constitution. The circuit court granted partial summary judgment in favor of ATC on these claims, which JT Properties does not challenge on appeal.

2 No. 2023AP2322

assuming that ATC will exercise all of the rights set forth in the Easement. In the alternative, JT Properties renews its argument that ATC’s jurisdictional offer is void because ATC took more rights than were necessary to accomplish the public purpose of providing electricity. We reject these arguments because they are premised on erroneous interpretations of the Easement language. Accordingly, we affirm.

BACKGROUND

¶3 There is no dispute about the following material facts.

¶4 In 2005 and 2006, respectively, JT Properties purchased two adjacent lots, referred to as Lot 10 and Lot 9, in Blue Mounds, Wisconsin, abutting U.S. Highway 18/151 (“the Property”). The Property, which totaled approximately five acres, required extensive excavation work to prepare it as a commercial building site.

¶5 After the majority of the Property was excavated and graded, John Theobald, the owner of JT Properties, constructed a 12,348-square-foot “shop building” on Lot 10, out of which he runs his family’s glass and mirror business, Mount Horeb Glass. Theobald also resides in a portion of the shop building and rents out other commercial spaces in the building. At its highest point, the shop building is 28 feet tall. In 2015, on the adjacent Lot 9, Theobald built four storage buildings that contain 81 storage units that he rents out. The northernmost storage building is a large “contractor unit” building that, at its highest point, is 23 feet tall. All five buildings were constructed on the graded portion of the Property that is approximately 25 feet lower than the elevation of the highway. A rock wall separates the graded portion of the Property from a small portion of the northern edge of the Property that is parallel to and at the same elevation as the highway.

3 No. 2023AP2322

The Property also contains a large gravel pile that sits on the graded portion of the Property and that has a maximum height slightly higher than the rock wall.

¶6 In 2019, the Wisconsin Public Service Commission (“PSC”) approved the Cardinal-Hickory Creek high voltage electricity transmission line project. The purpose of the project is to improve the reliability of electrical service, to provide economic benefits to Wisconsin electricity customers, and to increase the percentage of electricity on the market that is generated by clean and renewable sources.

¶7 As part of the Cardinal-Hickory Creek Transmission Line Project, ATC sought to acquire the Easement for the construction of a high-voltage transmission line on a portion of the Property. In November 2021, after negotiations between the parties failed, ATC sent JT Properties a jurisdictional offer for the taking of the Easement.3 Attached to the jurisdictional offer was the Easement document, which grants ATC a “perpetual right and easement to construct, install, operate, maintain, repair, replace, rebuild, remove, relocate, inspect and patrol” a high-voltage electric transmission line and related equipment “upon, in, over and across property owned by the Landowner.” Specifically, the Easement allows ATC to construct, operate, and maintain a double-circuit transmission line with a 345-kilovolt (kV) circuit and a 138-kV circuit strung between a single pole that is up to 191 feet tall in the northeast corner of the

3 One definition of “easement” adopted by Wisconsin courts is “a right or privilege to use land belonging to another, often for a specific purpose.” Hanson Revocable Tr. v. American Transmission Co., 2024 WI App 55, ¶78, 413 Wis. 2d 686, 12 N.W.3d 867 (emphasis omitted); see also Grygiel v. Monches Fish & Game Club, Inc., 2010 WI 93, ¶13, 328 Wis. 2d 436, 787 N.W.2d 6 (“An easement is a liberty, a privilege, or an advantage in lands” that is “distinct from [the] ownership [of the land].”).

4 No. 2023AP2322

Property and other poles outside of the Property. The conductors of the 345-kV circuit consist of three upper electrical wires and the conductors of the 138-kV circuit consist of three lower wires. The Easement specifies the minimum height of the wires as follows: “[m]inimum height above existing landscape (ground level): 20.7 feet.” (Emphasis omitted.)

¶8 The Easement delineates the boundaries of a 1.66-acre strip of land, totaling 877 feet in length and 91 feet in width, which we refer to as the “Easement property,” upon which ATC is granted the right to construct and maintain the high voltage electricity transmission line. Attached to the Easement are exhibits that detail the other obligations of ATC in constructing and maintaining the transmission line as well as “Easement Description Maps.” These maps show that the northern 22 feet of the shop building on Lot 10 and the entire “contractor unit” storage building on Lot 9 are within the Easement property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott N. Waller v. American Transmission Company, LLC
2013 WI 77 (Wisconsin Supreme Court, 2013)
Atkinson v. Mentzel
566 N.W.2d 158 (Court of Appeals of Wisconsin, 1997)
Czarnik v. Sampson Enterprises, Inc.
175 N.W.2d 487 (Wisconsin Supreme Court, 1970)
Falkner v. Northern States Power Co.
248 N.W.2d 885 (Wisconsin Supreme Court, 1977)
Mitton v. Wisconsin Department of Transportation
516 N.W.2d 709 (Wisconsin Supreme Court, 1994)
AKG REAL ESTATE, LLC v. Kosterman
2006 WI 106 (Wisconsin Supreme Court, 2006)
Hunter v. McDonald
254 N.W.2d 282 (Wisconsin Supreme Court, 1977)
Jacobson v. American Tool Cos., Inc.
588 N.W.2d 67 (Court of Appeals of Wisconsin, 1998)
Lessor v. Wangelin
586 N.W.2d 1 (Court of Appeals of Wisconsin, 1998)
Rikkers v. Ryan
251 N.W.2d 25 (Wisconsin Supreme Court, 1977)
Ricardo M. Garza v. American Transmission Co.
2017 WI 35 (Wisconsin Supreme Court, 2017)
Grygiel v. Monches Fish & Game Club, Inc.
2010 WI 93 (Wisconsin Supreme Court, 2010)
Savage v. American Transmission Co.
2013 WI App 20 (Court of Appeals of Wisconsin, 2013)
Kirk v. Credit Acceptance Corp.
2013 WI App 32 (Court of Appeals of Wisconsin, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
JT Properties of Mt Horeb, LLC v. American Transmission Company LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jt-properties-of-mt-horeb-llc-v-american-transmission-company-llc-wisctapp-2025.