JT Cleary, Inc v. National Grid, PLC

CourtDistrict Court, S.D. New York
DecidedOctober 30, 2024
Docket1:22-cv-04533
StatusUnknown

This text of JT Cleary, Inc v. National Grid, PLC (JT Cleary, Inc v. National Grid, PLC) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JT Cleary, Inc v. National Grid, PLC, (S.D.N.Y. 2024).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK -----------------------------------------------------------------X JT CLEARY, INC.,

Plaintiff, 22-CV-4533 (JLR) (VF)

-against- OPINION & ORDER

NARRAGANSETT ELECTRIC COMPANY, d/b/a NATIONAL GRID, PLC,

Defendant. -----------------------------------------------------------------X NARRAGANSETT ELECTRIC COMPANY,

Counterclaim Plaintiff,

-against-

JT CLEARY, INC.,

Counterclaim Defendant. -----------------------------------------------------------------X VALERIE FIGUEREDO, United States Magistrate Judge.

Plaintiff JT Cleary, Inc. (“Plaintiff”) commenced this action on June 1, 2022, against Defendant The Narragansett Electric Company (“Defendant”), alleging that Defendant breached its contract with Plaintiff, pursuant to which Plaintiff was to install an HDPE pipe (the “Conduit”) under the sea floor off the coast of Block Island, Rhode Island. See ECF Nos. 1, 6. Defendant brought breach-of-contract and breach-of-warranty counterclaims against Plaintiff, arising from the collapse of the same contractual relationship, and alleging that Plaintiff delivered a sand and debris-filled Conduit that did not meet the contract’s specifications. See ECF No. 35. Before the Court are two letter motions filed by Plaintiff, seeking to strike the supplemental reports submitted by Defendant’s experts. See ECF Nos. 93, 94. For the reasons explained below, Plaintiff’s letter motions are DENIED. BACKGROUND1 On December 1, 2023, the Court ordered the parties to exchange expert disclosures by March 15, 2024. See ECF No. 72. On March 14 and 15, 2024, Defendant served two expert reports on Plaintiff, one prepared by Rachel Mosier and the other by Brian Dorwart. See ECF No. 93-1; ECF No. 94-1. Defendant retained Ms. Mosier, who is employed by an engineering

consulting firm specializing in design and installation support for underground and submarine cables, to evaluate the design of the project, the cleaning and testing of the Conduit, and the installation of a cable in the Conduit. See ECF No. 93-1 at 3-5.2 Defendant retained Mr. Dorwart, a geologist and geotechnical engineer, to opine on whether Plaintiff adequately secured the ends of the Conduit such that sand and debris would not enter the Conduit. See ECF No. 94-1 at 3-4. Ms. Mosier and Mr. Dorwart were retained to opine on those aspects of the Conduit because Defendant wanted a power cable to pass through the entirety of the Conduit, but the Conduit Plaintiff installed had sand and debris in it, which Defendant contends did not allow for a cable to pass through. See ECF No. 93-1 at 3-4; see also ECF No. 35 at Counterclaim ¶¶ 52-54.

Ms. Mosier was deposed by Plaintiff on April 5, 2024. See ECF No. 93-2. Mr. Dorwart was deposed by Plaintiff on April 12, 2024. See ECF No. 94-2. Under the Court’s scheduling order, expert discovery closed on April 15, 2024. See ECF No. 72 at ¶ 8. On May 29, 2024,

1 The parties’ familiarity with the facts of this case is presumed. Only the facts relevant to the instant dispute are discussed herein.

2 The page numbers referenced herein for citations to the electronic docket (“ECF”) are to the ECF-generated pagination in those documents, except for citations to the transcripts at ECF Nos. 93-2, 94-2, and 107, which are to the original pagination in those transcripts.

2 Defendant disclosed two supplemental reports, prepared by Ms. Mosier and Mr. Dorwart. See ECF Nos. 93-3; 93-4; 94-3; 94-4. A. Rachel Mosier’s expert opinion In Ms. Mosier’s expert report, she opined that Plaintiff failed to provide a clean Conduit, and that, as a result, there were excessive pulling tensions, prohibiting the cable from passing

through the Conduit. See ECF No. 93-1 at 5. As Ms. Mosier explained, debris in the Conduit can increase the force required to pull the cable into the Conduit, and thus the cable installation in the Conduit scheduled for the spring of 2021 did not occur, because LS Cable Systems America, Inc. (“LS Cable”), the cable manufacturer, determined that the amount of debris in the Conduit created an unacceptable risk of damage to the cable. Id. at 5-7, 15; see also id. at 11-12 (explaining that debris poses a significant risk of increasing the friction between the cable and the Conduit, including creating excessive pulling tensions on the cable). In her deposition, Ms. Mosier was asked if she calculated the pulling tension on the cable. See ECF No. 93-2 at 25-26. She testified that she did not and added that she did not “offer an

opinion on the pulling tension of the cable.” Id. at 28. Ms. Mosier further explained that the cable manufacturer, LS Cable, determined the maximum pulling tension allowed, noting that the pulling tension calculation “has nothing to do with how you’re pulling the cable.” Id. at 25-28. Ms. Mosier was asked whether the pulling tension would vary based on whether the cable was being pulled by the “armor” or the “core” of the cable. Id. at 27. Ms. Mosier testified that there are two types of armor for “submarine cables” and with a “single-helix armor cable,” as was found in this project, you are not pulling on the “armor” itself and the vast majority of the tension caused by the pull would be on the core. Id. at 21-23, 160. Ms. Mosier was asked if, in

3 this case, there was a “pulling eye” with “armor whips” and she testified that she had not seen “the cutaway of the pulling eye” and would need to see how the “pulling eye was manufactured.” Id. at 23-24. Ms. Mosier nevertheless testified that it did not matter what the “pulling eye looks like” because “[y]ou cannot pull on a single-wire armor” and would have to assume that you are pulling on the “conductor” and not the “armor.” Id. at 160-61. Ultimately, Ms. Mosier testified

that despite not knowing how the pulling head was attached to the cable in this case, because the cable was a single-helix armor cable, she would assume the cable was pulled by the core (or conductor) and not the armor. Id. at 159-163. In Ms. Mosier’s supplemental report, she explains that she learned after her deposition of a January 2020 schematic of the cable’s pulling head, prepared by LS Cable. See ECF No. 93-4 at 2. Ms. Mosier also learned of a table with the specifications of the cable and the actual allowable pulling tension for the cable. See id. at 3. Through these newly identified materials, Ms. Mosier discovered that the pulling head on the cable was attached to the armor, which meant that the cable was pulled by the armor (and not the conductor or core as she had assumed during

her deposition). Id. Ms. Mosier explains that the fact that the cable was pulled by the armor would affect how the cable manufacturer determines the maximum allowable pulling tension, but it did not affect the calculation of the expected pulling tension, as she had testified during her deposition. Id. at 3-4. B. Brian Dorwart’s expert opinion In his expert report, Mr. Dorwart opined that Plaintiff failed to adequately secure the ends of the Conduit, causing debris and sand to enter the Conduit. See ECF No. 94-1 at 3. Specifically, Mr. Dorwart opined that “JT Cleary insufficiently maintained the construction and

4 specifications of the gravity cell during installation and testing of the Conduit on January 31, 2021,” creating the “opportunity for sand to enter the sea end of the Conduit.” See id. at 8. Mr. Dorwart also opined that Plaintiff failed to adequately secure end caps that would “prevent foreign material from entering the Conduit.” Id. at 11. Mr. Dorwart did not quantify the amount of debris or sand in the Conduit. See ECF No. 94-2 at 110.

Further, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ebewo v. Martinez
309 F. Supp. 2d 600 (S.D. New York, 2004)
Cedar Petrochemicals, Inc. v. Dongbu Hannong Chemical Co.
769 F. Supp. 2d 269 (S.D. New York, 2011)
Simo Holdings Inc. v. Hong Kong Ucloudlink Network Tech. Ltd.
354 F. Supp. 3d 508 (S.D. Illinois, 2019)
Izzo v. ING Life Insurance & Annuity Co.
235 F.R.D. 177 (E.D. New York, 2005)
Coene v. 3M Co.
303 F.R.D. 32 (W.D. New York, 2014)
Outley v. City of New York
837 F.2d 587 (Second Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
JT Cleary, Inc v. National Grid, PLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jt-cleary-inc-v-national-grid-plc-nysd-2024.