J.S. Rugg Construction, Inc. v. Ouachita Parish School Board

895 So. 2d 713, 2005 La. App. LEXIS 540, 2005 WL 476985
CourtLouisiana Court of Appeal
DecidedMarch 2, 2005
DocketNo. 39,340-CA
StatusPublished
Cited by1 cases

This text of 895 So. 2d 713 (J.S. Rugg Construction, Inc. v. Ouachita Parish School Board) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.S. Rugg Construction, Inc. v. Ouachita Parish School Board, 895 So. 2d 713, 2005 La. App. LEXIS 540, 2005 WL 476985 (La. Ct. App. 2005).

Opinion

I,CARAWAY, J.

The unsuccessful bidder for a public works contract sued the school board and the successful contractor/bidder for damages. In 2003, this court, on the supervisory writ application of the school board, granted the peremptory exception of no cause of action. The case was remanded to allow plaintiff to amend its pleadings to request injunctive relief under La. R.S. 38:2220(B), if “still available,” or to allege the circumstances that existed which made the filing of a timely suit for injunction impossible. On remand after the amendment of the petition, the trial court granted the school board’s and contractor’s exceptions of no cause of action. Additionally, the plaintiffs claim against the State Licensing Board for Contractors for its licensing of the successful contractor/bidder was also dismissed by the trial court. Finding no error in the rulings of the trial court, we affirm.

Facts

On May 28, 2002, the Ouachita Parish School Board (“School Board”) voted to advertise Construction Project No. 01102A involving renovations for West Monroe High School. The project, described as “Technology & Classroom Additions,” required a base bid for the “technology wing” and bids for three alternates, which included (1) covering an open drainage ditch between the football stadium and the parking lot; (2) constructing an auditorium handicap ramp; and (3) extending and recovering the new athletic track.

| thereafter, the project was advertised and a pre-bid meeting occurred. The bids were opened and tabulated by the School Board on August 6, 2002. The following week, the School Board convened at its regular meeting and voted 4 to 3 to accept James Holyfield Construction, Inc. (“Holy-field”) as the lowest base bidder. The bids pertaining to the alternate items for the project were completely excluded by the School Board. On August 21, 2002, the School Board and Holyfield executed a $6,647,000 contract for the project.

J.S. Rugg Construction, Inc. (“Rugg”) filed suit against Holyfield and the School Board on August 22, 2002, contending that it should have been recognized as the lowest bidder and awarded the contract because the aggregate of its base bid and its bids on the alternate items rendered it the lowest bidder, not Holyfield. Rugg further alleged that by excluding the bids on the alternate items, the School Board unfairly and fraudulently manipulated the bid process in violation of state law. The petition also alleged that no work had yet begun on the project. The petition concluded with a prayer asking that it be paid its $6,865,000 bid price upon its performance of the work. However, the petition requested no injunctive relief. Alternatively, the petition sought recovery of Rugg’s lost profits and damages.

The School Board answered, also urging a peremptory exception of no cause of action. In support of its exception, the School Board argued that Rugg failed to file the proper action under La. R.S. 38:2220(B), which, requires an aggrieved [716]*716bidder to pursue injunctive relief in contesting the |3award of a public contract. After the trial court denied the School Board’s exception, this court granted a supervisory writ in 2003, and reversed the trial court, as follows:

In order for an unsuccessful bidder on a contract which is subject to the provisions of the public bid law to be able to maintain an action for damages, it is required to timely seek an injunction preventing the public body from awarding the contract and/or preventing performance under the contract, or state in its petition the reasons why seeking such an injunction was not possible. Airline Construction Company, Inc. v. Ascension Parish School Board, 568 So.2d 1029 (La.1990); Webb Const., Inc. v. City of Shreveport, 27,761 (La.App.2d Cir.12/6/95), 665 So.2d 653. In the present case, it appears clear that the unsuccessful bidder had the requisite knowledge to file a timely suit for injunction to prevent performance under the contract. The present suit seeking nullification of the contract and damages was filed two days after the award of the contract and, thus presumably before any substantial work could be performed on the project. The purpose of the public bid law is to protect the taxpayer from extortionate prices and public officials who might award public contracts on the basis of favoritism. Haughton Elevator Division v. State, Through Division of Administration, 367 So.2d 1161 (La.1979). In essence, the law attempts to ensure the wise use of the taxpayers’ money. To allow a suit for damages by an unsuccessful bidder which failed to avail itself of its injunctive remedies without just cause would reward the bidder which fails to mitigate its damages at the expense of the taxpayers.
J.S. Rugg’s petition does not state in specific detail the circumstances which would have prevented it from filing a timely suit to enjoin performance under the contract. Nor do we know whether such relief might still be available as the timeliness of a suit for injunction depends on the facts and circumstances of the particular case. Accordingly, we reverse the trial court and grant the School Board’s exception of no cause of action. However, J.S. Rugg should be allowed the opportunity to amend its pleading to request injunctive relief, if it is still available, or to make any other allegations which might remove the grounds on which the exception is being granted. La. C.C.P. [art.] 934. Consequently, the matter is also remanded to the trial court and J.S. Rugg shall have 30 days within the date of this order to amend its pleading so as to |4remove the grounds of the exception. If J.S. Rugg cannot or does not so amend its pleadings, then the action shall be dismissed. La. C.C.P. [art.] 934.

The day after the date of the above order, Rugg amended its petition to add as a defendant, the State Licensing Board for Contractors (“Licensing Board”), alleging that it breached its duty to insure compliance under La. R.S. 37:2150 for the licen-sure requirements for Holyfield. One month later, Rugg again amended its petition, alleging that because it had been required to maintain a $6.8 million performance bond in order to be eligible to bid for the contract, it was financially impossible for Rugg to also obtain the security bond ostensibly required for the pursuit of injunctive relief.

Thereafter, the Licensing Board moved for summary judgment. The School Board and its insurer urged a second peremptory exception of no cause of action, or alternatively, a motion for summary judgment, in which they argued that Rugg’s [717]*717petition, as amended after remand, still did not state a cause of action. Holyfield also again urged the peremptory exception of no cause of action, or alternatively a motion for summary judgment, arguing that Rugg’s simple failure to pursue an injunction as required by the public bid law precluded it from obtaining relief.

The trial court rendered judgment in favor of the School Board and its insurer, and Holyfield, granting their respective exceptions. The trial court also granted the Licensing Board’s motion for summary judgment, and denied plaintiffs motion for summary judgment. It is from this judgment that Rugg appeals.

| sDiscussion

The leading case dealing with this type of public bid law dispute is Airline Const. Co., Inc. v. Ascension Parish School Bd., 568 So.2d 1029 (La.1990). Airline

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
895 So. 2d 713, 2005 La. App. LEXIS 540, 2005 WL 476985, Counsel Stack Legal Research, https://law.counselstack.com/opinion/js-rugg-construction-inc-v-ouachita-parish-school-board-lactapp-2005.