Joyce v. Sauk County

246 N.W. 413, 210 Wis. 243, 1933 Wisc. LEXIS 334
Procedural entryThis page is a short order in Joyce v. Sauk County. Read the opinion of the Court — 206 Wis. 202
Wisconsin Supreme Court·Decided January 10, 1933·Published

Opinion

Rosenberry, C. J.

Upon this appeal a great many questions are raised with reference to procedure upon the trial, particularly the admission of evidence over the objection of the defendant. We have examined these assignments of error with care. Most of them can be disposed of as nonprejudicial for the reason that they related to matters which were found in favor of the defendant by the jury. As to the remainder we find nothing prejudicial or which merits special treatment.

The controversy between the parties to this action relates mainly to two principal questions: (1st) the classification of the yardage admittedly excavated by the plaintiff under his contract; and (2d) the right of the plaintiff to recover for yardage in excess of that allowed him by the estimate of the engineer and in excess of that indicated by the plans and specifications.

(1) The contract provides the method of measurement.

“12.8 Method of measurement. All accepted road excavation shall be measured in its original position by the method of average end areas with no correction for curvature. Solid rock in ledges shall be measured from cross-sections taken before and after the cuts are opened. The yardage of loose rock in the form of cut’ shall be determined [247]*247by estimating its percentage of the entire cut. The yardage of loose and solid rock in the form of detached boulders shall be determined by estimating three dimensions. In all cases where classification of excavation is necessary such classification shall be made by the engineer as the work progresses, and in conference with the contractor or his authorized representative. If dispute arises as to the proper classification the contractor shall file his protest in writing within twenty-four hours, otherwise no change in classification will be allowed.”

The contract also contains the following provision:

“5.1 Authority of engineer. The engineer shall decide any and all questions which may arise as to the quality or acceptability of materials furnished and work performed and as to the manner of performance and rate of progress of the work and shall decide all questions which may arise as to the interpretation of the plans and specifications, and all questions as to the acceptable fulfilment of the contract on the part of the contractor, and as to compensation. His decisions shall be final and he shall have executive authority in accordance with paragraph 8.8 and other measures within these specifications to enforce and make effective such decisions and orders as the contractor fails promptly to carry out.”

A consideration of paragraph 12.8 indicates that a proper classification of material involves the exercise of judgment and is not a mere matter of mathematical computation. It appears from the evidence that the engineer never made any classification in conference with the plaintiff as the work progressed. He made it when and as convenient for him and the result of his classification was not disclosed until the completion of the work. After the completion of the work, Mr. Greenwood, the engineer, allowed the plaintiff 29,807 cubic yards of excavation classified as follows: 24,983 cubic yards of earth, 2,809 cubic yards of loose rock, and 2,015 cubic yards of solid rock. The arbitrators, Burch, Bean, and Busby, found that there were 30,576 cubic yards of excavation classified: earth 21,810 cubic yards, loose [248]*248rock 3,511 cubic yards, and solid rock 5,255 cubic yards. The discrepancy between the amount allowed by the arbitrators and the amount allowed by Mr. Greenwood, the engineer, arises principally with respect to classification. According to Mr. Greenwood’s estimate the estimated price of the work, not including grubbing and laying of pipes, was $13,784. He allowed $18,629.34. The arbitrators awarded $23,964.30. If plaintiff be allowed his claim for extra yardage the total amount would be $28,098.62, which is more than double the amount of the estimate. The arbitrators testified as witnesses upon the trial, they were examined and cross-examined exhaustively, and the jury found that the arbitrators had correctly classified the amount of yardage allowed by the engineer. So far as classification is concerned, it must be held that the determination of the engineer is not conclusive because not made in conformity with the contract. His estimates, as already pointed out, were never made in conference with the contractor. If the defendant is to claim the benefit of finality for the engineer’s findings, such findings must be made in accordance with the terms of the contract. No such provision is inserted in'the contract at other points, apparently for the reason that with respect to other matters there is not the opportunity for such divergence of opinion as there is in the classification of material. Requiring the classification to be done in conference with the contractor gives the contractor a right to be heard and advises him of the result.

The arbitrators were all experienced engineers of established reputation. They pursued the method usually and customarily employed by engineers in work of that character. The evidence which they gave upon the trial abundantly sustains the finding of the jury with respect to classification. In this connection it is contended by the plaintiff that the judgment should be modified by allowing a recovery of approximately $190.38 on account of yardage claimed to [249]*249be due under the testimony of Mr. Greenwood but not included in his allowance. The plaintiff in this case had judgment exactly in accordance with his second motion for judgment which was for the sum of $4,934.70 with interest. There appears to have been no motion in the court below to amend this judgment or correct it in accordance with the claim now mkde nor was the contention now made brought to the attention of the trial court. The plaintiff having had judgment in his favor for the amount asked, he has no reason to complain on appeal. While it may be argued that the amount of $190.38 was included in the larger claim, what was claimed was compensation for the total amount of yardage, not compensation on account of an error in Mr. Greenwood’s computation. The engineer’s determination as to quantity is final unless impeached for fraud or mistake. No issue of that kind was litigated on the trial.

(2) The plaintiff in performing the contract excavated • 35,844 cubic yards or 6,037 cubic yards more than he received compensation for under the verdict. The jury by its fourth finding found against the plaintiff’s contention, and the trial court denied plaintiff’s motion for judgment for compensation for extra excavation, which motion was based upon the proposition that the plaintiff was entitled to recover therefor as a matter of law. Plaintiff’s contention is based upon this: that the county highway committee and engineer by their conduct as the work progressed ratified and authorized the changes made by the plaintiff and thereby assumed and agreed to pay therefor at the contract rate. A determination of this question requires us to examine somewhat the authority of the county highway committee and the engineer in the premises.

Sec. 83.04 (1), Stats., among other things, provides :

“The manner of advertising for bids and the forms of bids, contracts and bonds shall be prescribed by the State Highway Commission and shall be uniform.” '

[250]*250In the awarding of contracts the county highway committee acts for the county (sec.

Free access — add to your briefcase to read the full text and ask questions with AI

Joyce v. Sauk County, 246 N.W. 413, 210 Wis. 243, 1933 Wisc. LEXIS 334 (Wis. 1933).

246 N.W. 413 (Joyce v. Sauk County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.