Jowite Limited Partnership v. Federal Insurance Company

CourtDistrict Court, D. Maryland
DecidedAugust 17, 2020
Docket1:18-cv-02413
StatusUnknown

This text of Jowite Limited Partnership v. Federal Insurance Company (Jowite Limited Partnership v. Federal Insurance Company) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jowite Limited Partnership v. Federal Insurance Company, (D. Md. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

JOWITE LIMITED PARTNERSHIP, *

Plaintiff, *

v. * Case No.: DLB-18-2413 FEDERAL INSURANCE COMPANY, *

Defendant. *

* * * * * * * * * * * * * *

MEMORANDUM OPINION In this breach of contract case, plaintiff Jowite Limited Partnership (“Jowite”) and defendant Federal Insurance Company (“Federal”) dispute whether, under an all-risk insurance policy, there is coverage for damages to an apartment building that resulted from the defective design and construction of the building’s foundation and the subsequent settlement of the building. At the core of this dispute is whether the ensuing loss clause in the Policy’s defective design and construction exclusion restores coverage. The parties filed cross-motions for summary judgment. ECF Nos. 85, 88.1 For the reasons stated below, the Court will deny Jowite’s motion and grant Federal’s motion. There is no coverage under the Policy for the damage to the building. Judgment as a matter of law will be entered in favor of Federal.

1 The parties fully briefed the motion, including through supplemental briefing after Judge Hollander issued a Memorandum Opinion in another case addressing the issue presented in this case. ECF Nos. 85-3, 88-1, 90, 92, 93. A hearing is not necessary. See Loc. R. 105.6. Factual Background2 The material facts of this case are not in dispute. Jowite owns the Jowite Apartments located at 406 Moton Street, Easton, Maryland 21601. Pl.’s Opp’n & Mem. 1, ECF No. 88-1; Def.’s Mem. 2, ECF No. 85-3. The Jowite Apartments were built in the late 1980s. Pl.’s Opp’n

& Mem. 1; Def.’s Mem. 2. There are three apartment buildings on the property: Buildings 100, 200, and 300. Pl.’s Opp’n & Mem. 1; Def.’s Mem. 2. In about 1999, the property manager, Debra Moxey, observed that the right side of Building 300 “was sinking” into the ground. Moxey Dep. 11:5–12:7, ECF No. 88-9. Moxey said that the management company “fix[ed]” the problem by having “a house moving company . . . plug[] it back up.” Id. at 11:17–12:18. Fourteen years later, in January 2013, a new management company, TM Associates, Inc. (“TM”), took over responsibility for the Jowite Apartments. Mgmt. Agr., ECF No. 88-13. TM hired Rodney Wilkinson for building improvement needs. Immediately after he began working at the property, Wilkinson observed the sinking of Building 300. Wilkinson Dep. 13:10–15, 19:3– 11, ECF No. 85-14.

In 2015, TM retained an engineering firm to evaluate the settlement issues with Building 300. On May 26, 2015, ABBA Engineering, LLC (“ABBA”) inspected Building 300 and observed “uneven floors,” “cracks in the brick facing,” and “standing water” in the crawl space beneath the building. June 9, 2015 ABBA Report, ECF No. 88-15, at 5–6. The firm attributed the issues to “a concentrated load that may not have been accounted for in the original design and over time has sagged due to insufficient support in th[e] area.” Id. The firm noted that “there may be some

2 In ruling on cross-motions for summary judgment, this Court “resolve[s] all factual disputes and any competing, rational inferences in the light most favorable to the party opposing that motion.” Wheelabrator Baltimore, L.P. v. Mayor & City Council of Baltimore, No. GLR-19-1264, 2020 WL 1491409, at *4 (D. Md. Mar. 27, 2020) (quoting Rossignol v. Voorhaar, 316 F.3d 516, 523 (4th Cir. 2003)). settlement going on.” Id. The engineering firm recommended “locat[ing] this area in the crawl space, provid[ing] blocking between the floor joists and beam in the crawl space and if there is not an existing pier close by, provid[ing] a cmu pier under this area” to “arrest the problem.” Id. TM hired a contractor, Willie Guy of Capital Construction Services, LLC (“CCS”), to

“repair . . . the support beam under building 300.” Aug. 24, 2015 Ltr. from CCS, ECF No. 85-17. Guy observed that the second floor “was severely out of level.” Guy Dep. 14:22–15:3, ECF No. 85-15. He “went down into the crawl space” and found that “the footer had failed”; it “was cracked and appeared to be sinking.” Id. at 15:4–6, 22:4–17. Guy also noted “severe cracks, settlement cracks” on the walls inside the building. Id. at 36:15–37:11. He stated that it was “obvious to [him] and everyone else that was there that the building was sunk in th[e] corner.” Id. at 25:5–7. Guy installed “20 ton hydraulic jacks” to “raise[] [a] beam back up to correct the hallway.” Id. at 26:15–27:1, 29:17–18. Following that remedial work, on August 24, 2015, Guy informed TM: Upon the execution of the repair to the support beams under building 300 we observed several structural problems we feel need to be addressed. The foundation and the footer on the rear wall have failed causing the building to become extremely out of level. The cracking in the bricks are evidence of severe settling. In addition the loss of support on the outside walls have caused the transfer of weight to the inside floor support beams that were not intended to support this kind of load[;] that is the reason they have failed and have been replaced. We feel there is an excessive amount of water being held under the building causing the footers to have little or no support due to the footing resting on mud. It appears the footer is approximately 5” thick and there are several cracks. We observed w[h]ere work has been done to level the building in the past but feel that attempt did not cure the problem. Aug. 24, 2015 Ltr. from CCS. On September 21, 2015, ABBA inspected Building 300 again. Sept. 21, 2015 Ltr. from ABBA, ECF No. 88-15, at 3. In its report, ABBA noted that “the back exterior wall . . . ha[d] settled,” the floors were “not level,” and “[s]ometime in the past, this exterior wall had some work performed on it in an effort to level up that side of the building.” Id. ABBA recommended replacing the footers and regrading the area around Building 300. Id. The work was not done. Pl.’s Opp’n & Mem. 11. Nearly two years later, on March 2, 2017, another company inspected Building 300. Demolition of the entire building was recommended because six of the twelve piers “ha[d] failed,”

and “[t]he building [was] dropping on the right rear side.” Mar. 2, 2017 Invoice from Done Right, LLC, ECF No. 85-18. Jowite did not demolish the building. On July 18, 2017, Jowite filed an insurance claim with Federal under an all-risk insurance policy that Federal had issued for the Jowite Apartments, including Building 300. Policy, ECF No. 1-1 (March 1, 2017–March 1, 2018 policy period); see also Am. Compl. ¶ 8, ECF No. 24; Def.’s Mem. 7–8. Jowite claimed that “[t]here [were] 8 units that [were] sinking into the ground due to ground settling” and sought coverage for the damage to the building. Claim Confirmation, ECF No. 85-19; Notice, ECF No. 88-24. The Policy provides that Federal “will pay for direct physical loss or damage to: • building; or • personal property, caused by or resulting from a peril not otherwise excluded, not to exceed the applicable Limit Of Insurance for Building Or Personal Property shown in the Declarations.” Policy, ECF No. 1-1, at 211.3 The Policy has a number of exclusions that “apply to all coverages.” Id. at 222. The two exclusions at issue here are: Planning, Design, Materials Or Maintenance This insurance does not apply to loss or damage (including the cost of correcting or making good) caused by or resulting from any faulty, inadequate or defective:

3 Defined terms appear in bold in the Policy. The emphasis is removed where the Policy is quoted in this Memorandum Opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Fister v. Allstate Life Insurance Co.
783 A.2d 194 (Court of Appeals of Maryland, 2001)
Empire Fire and Marine Ins. Co. v. Liberty Mutual Ins. Co.
699 A.2d 482 (Court of Special Appeals of Maryland, 1997)
Cole v. State Farm Mutual Insurance
753 A.2d 533 (Court of Appeals of Maryland, 2000)
Bausch & Lomb Inc. v. Utica Mutual Insurance
625 A.2d 1021 (Court of Appeals of Maryland, 1993)
Megonnell v. United States Automobile Association
796 A.2d 758 (Court of Appeals of Maryland, 2002)
Valliere v. Allstate Insurance
596 A.2d 636 (Court of Appeals of Maryland, 1991)
Universal Underwriters Insurance v. Lowe
761 A.2d 997 (Court of Special Appeals of Maryland, 2000)
Clendenin Bros. v. United States Fire Insurance
889 A.2d 387 (Court of Appeals of Maryland, 2006)
Montefiore Medical Center v. American Protection Insurance
226 F. Supp. 2d 470 (S.D. New York, 2002)
Finci v. American Casualty Co. of Reading
593 A.2d 1069 (Court of Appeals of Maryland, 1991)
Bao v. Liberty Mutual Fire Insurance
535 F. Supp. 2d 532 (D. Maryland, 2008)
Kay v. United Pacific Insurance
902 F. Supp. 656 (D. Maryland, 1995)
Rossignol v. Voorhaar
316 F.3d 516 (Fourth Circuit, 2003)
North American Accident Insurance v. Plummer
176 A. 466 (Court of Appeals of Maryland, 1935)
McEvoy v. Security Fire Insurance
73 A. 157 (Court of Appeals of Maryland, 1909)
Hartford Steam Boiler Inspection & Ins. v. Henry Sonneborn & Co.
54 A. 610 (Court of Appeals of Maryland, 1903)
Ellicott City Cable, LLC v. Axis Insurance Co.
196 F. Supp. 3d 577 (D. Maryland, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Jowite Limited Partnership v. Federal Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jowite-limited-partnership-v-federal-insurance-company-mdd-2020.